19% of the exam - about 2.5 hours - 14 practice questions
0:00 / --:--
Reading
What a Construction Manager actually does
A Construction Manager (CM) is a professional retained to plan, coordinate, and oversee a construction
project on the owner's behalf, using systematic project management practices from inception through
closeout. That last phrase, "from inception through closeout," is the detail exam questions lean on most:
a CM is not simply a job-site superintendent hired once a contractor mobilizes. Depending on the delivery
method, a CM's engagement can begin during feasibility and programming, long before a design is complete,
and it typically does not end until warranties are logged and the owner has taken full possession of a
functioning facility.
CMAA's Standards of Practice frame the CM's core duty as protecting the owner's interests throughout
planning, design, and construction, regardless of which delivery method is in play. That duty does not
change; what changes from method to method is the CM's contractual authority to act on it, which is why
this course treats "the CM's role" and "delivery methods" as one topic rather than two.
The CM's core duties across the project life cycle
A CM's day-to-day responsibilities touch nearly every domain this course covers, so it helps to see the
whole shape of the job before this course goes deep on any one piece of it in later modules:
Program and project management: setting up the project's governance, defining
the project management plan, and representing the owner's interests across the full life cycle (this
module).
Cost management: developing and tracking budgets, estimates, and cost
control against the owner's program.
Time management: building and maintaining the project schedule and
identifying and resolving delays.
Contract administration: managing RFIs, submittals, change orders, and
payment applications against the contract documents.
Quality management: setting inspection, testing, and acceptance criteria and
verifying the work meets them.
Safety management: overseeing site safety programs and incident
recordkeeping.
Risk management: identifying, allocating, and mitigating project risk,
contractually and operationally.
Professional practice: the ethical and legal obligations that run underneath
all of the above.
Sustainability and technology: life-cycle thinking, energy performance, BIM,
and field technology, which increasingly touch every other domain rather than standing apart from them.
Every one of those domains gets its own module later in this course. This first day is about the frame
all of them sit inside: what authority does the CM actually have to act on each of these duties, and that
authority is set by the delivery method.
Agency CM vs. Construction Manager at Risk
Before naming individual delivery methods, it helps to fix two broad postures a CM can occupy, because
every named method below is a variation on one of these two:
Agency CM (CM as Advisor): The CM is retained as a fee-for-service professional
advisor. The CM has no contract with the trade contractors and does not guarantee cost or schedule
outcomes; the CM's value is expertise, oversight, and advocacy for the owner. Because the CM holds no
construction contract, the CM's authority over means and methods is limited to what the owner's contract
with the CM, and the owner's contract with the builder, actually grant.
Construction Manager at Risk (CM at Risk / CMAR): The CM converts from an advisory
role into the party holding the construction contract, typically under a Guaranteed Maximum Price (GMP).
The CM typically takes on bonding and performance obligations comparable to a general contractor's, and in exchange gets real authority to direct the work and control cost and schedule outcomes within the GMP.
Why this distinction matters more than the method names
Most Program and Project Management exam questions are scenario-based: "given this arrangement, what
can the CM do?" If you can first place a scenario into Agency or At-Risk, you already know the shape of
the answer before you match it to one of the four named methods below.
Design-Bid-Build (DBB)
The traditional, and still most common, delivery method. The owner contracts separately with a designer
and, after design is complete, a contractor selected through competitive bid, typically to the lowest
responsive and responsible bidder on public work. The CM here is almost always an Agency CM: the CM
represents the owner's interests but typically holds no direct contract with the trades, so the CM's
authority is advisory rather than directive.
DBB's strength is price competition on a complete design, which gives the owner cost certainty before
construction starts. Its weakness is sequence: design must finish before bidding, and bidding before
construction, so the overall schedule is strictly linear (sequential) rather than overlapped. It is also
the method with the least room to resolve design errors cheaply, since the contractor had no hand in
developing the design they are now pricing and building.
Construction Manager at Risk (CMAR)
The CM is brought on during design, providing preconstruction services such as constructability review,
cost estimating at each design milestone, and scheduling input, and later converts to holding the
construction contract directly, usually under a GMP. This gives the CM (and the owner) earlier visibility
into cost and schedule risk than DBB allows, because the CM is pricing and buying out the work as the
design develops rather than bidding a finished set of drawings cold.
The GMP itself is a negotiated cost ceiling, not a bid price: the CM is responsible for costs above the
GMP absent an owner-approved change, and any savings below the GMP are typically shared with the owner
under a formula set in the CM's contract. Because the GMP is negotiated rather than competitively bid on a
complete design, CMAR contracts are commonly "open book," meaning the owner has visibility into the CM's
actual buyout costs, general conditions, and fee, which is the main safeguard against the CM's added
authority being used against the owner's interest.
Design-Build (DB)
A single entity, the design-builder, holds one contract with the owner for both design and construction.
This collapses DBB's three separate relationships (owner-designer, owner-contractor, and the CM's advisory
role between them) into one, which typically compresses schedule because design and construction can
overlap under one party's control.
The tradeoff is that the owner gives up direct control of the design process to the design-builder. An
owner in Design-Build commonly still retains an independent CM, not to perform construction, but to act as
an owner's representative verifying the design-builder is actually meeting the owner's program and quality
expectations, since the owner no longer has a separate designer of its own checking that work.
A variation worth knowing by name is Progressive Design-Build, where the design-builder
is selected early, on qualifications, before a price or a completed design exists, and the price is
negotiated progressively as the design develops, similar in spirit to how a GMP develops under CMAR. The
core difference from CMAR is still which single entity holds the construction contract: in Progressive
Design-Build it is the design-builder, not a CM.
Integrated Project Delivery (IPD)
Owner, designer, and builder sign one multi-party agreement and share risk and reward, often through a
shared contingency pool and incentive-based compensation tied to hitting target cost and schedule together
rather than through separate contracts each managing its own risk. Because no single party is contractually
positioned as an adversary to be managed, the CM's role shifts away from single-point owner advocacy and
toward being an integrator and facilitator of the collaborative team.
IPD asks the most of all parties' trust and collaborative maturity, which is why it remains the least
common of the four named methods even though its cost and schedule outcomes are frequently favorable where
the owner and team have the experience to run it well.
Other delivery approaches worth recognizing
Two additional arrangements come up on real projects, and occasionally on the exam, even though they are
not one of the four "headline" methods above:
Multiple Prime Contracting: The owner holds separate direct contracts with several
prime contractors (for example, one each for site work, structure, and mechanical/electrical/plumbing)
instead of one general contractor holding all the trade subcontracts. This can save the owner the
general contractor's markup on subcontracted work, but it also means the owner (or the owner's CM) takes
on the coordination role a single general contractor would otherwise have carried between those primes.
Job Order Contracting (JOC): An indefinite-delivery, indefinite-quantity arrangement
where an owner selects a contractor (or contractors) once, often through a competitively bid multiplier applied to a published unit-price book, then
issues individual job orders against that pre-negotiated pricing as specific repair, renovation, or minor
construction needs come up, without re-bidding each individual job. It is common for public agencies and
institutions with a steady stream of smaller projects, where re-bidding every single job would be too
slow and too costly to administer.
How owners choose a delivery method
A CM is frequently asked to advise an owner on delivery method selection itself, so it is worth knowing
the factors that actually drive the choice, not just the mechanics of each method in isolation:
Risk transfer: How much cost and schedule risk does the owner want to transfer to a
single contracted party, versus retain and manage directly? Risk transfer generally increases moving from
DBB toward CMAR toward DB, while IPD spreads risk across all parties rather than concentrating or
transferring it.
Schedule urgency (fast-tracking): Can the owner tolerate, or does the owner need,
design and construction to overlap to compress the overall schedule? DBB cannot fast-track by design;
CMAR, DB, and IPD all can, to varying degrees.
Budget certainty needed, and when: DBB gives cost certainty only after a complete
design is bid. CMAR and Progressive Design-Build give earlier, but still evolving, cost visibility as the
design develops. An owner that needs a firm number before the design is well advanced is asking for
something none of these methods can honestly promise.
Design complexity and market conditions: A highly specialized or first-of-its-kind
facility often benefits from the contractor's means-and-methods expertise early (CMAR or DB), while a
well-understood building type in a competitive bidding market can do perfectly well under DBB.
Owner's in-house capability: An owner with a strong internal project management
and design-review staff can manage more of the coordination burden itself; an owner without that staff
often leans on a CM, or on a single-point-of-responsibility method like Design-Build, to carry more of
that burden contractually.
Read for the delivery method before evaluating any scenario question. Most Program and Project Management traps put a CM as advisor doing something only a contract holder could do.Delivery Methods: Who Holds Which ContractRisk transfer and schedule compression are the two questions to ask first when a scenario describes an unfamiliar arrangement: who ends up holding the cost risk, and can design and construction run at the same time?Scenario Clue to Delivery Method: a quick reference for reading the question stem before picking an answer.
Why this matters for the exam
A large share of Program and Project Management questions are scenario-based: "given this delivery
method, what can the CM do?" You must be able to identify the delivery method (and whether the CM is
Agency or At-Risk) from context clues, GMP, single contract, separate design and build contracts, shared
risk pool, unit-price book, multiple direct owner contracts, and correctly state the CM's authority under
it. Knowing the mechanics of each method in isolation is necessary but not sufficient; the exam tests
whether you can move between the method named in a scenario and the specific authority, risk, and duty
that method actually gives the CM.
Why this matters for GCHS
GCHS's own construction management, inspection, and estimating work sits inside whichever delivery
method a given funder or municipality has already chosen, most often something close to Agency CM under
a DBB-style structure on CDBG and HOME-funded rehabilitation work. Recognizing when a project instead
uses CMAR, Design-Build, JOC, or Multiple Prime contracting changes what GCHS staff can and cannot direct
on site, independent of what the construction documents themselves say.
Practice Questions
1. Under a Design-Bid-Build delivery method, the CM's authority over the contractor's means and methods is:
Equal to the architect's, since both may direct the contractor's means and methods
Established only by verbal agreement
Absolute, since the CM represents the owner and the contractor must follow any CM direction on how to build
Limited: the CM is typically advisory and does not direct means and methods
Answer: d. Under DBB, the CM (as agent/advisor) has no direct contract with the contractor and generally cannot dictate means and methods, which remain the contractor's responsibility.
2. A CM who converts from preconstruction services to holding the construction contract under a GMP is operating under:
Design-Build
IPD
CM at Risk
Design-Bid-Build
Answer: c. This conversion from advisor to at-risk contract holder under a GMP is the defining feature of CM at Risk.
3. In Design-Build, why might an owner still retain an independent CM?
To perform the actual construction work
Because Design-Build prohibits CMs
To act as the owner's representative, verifying the design-builder meets the program
To co-sign the design-builder's contract so the CM shares liability for the design-builder's performance
Answer: c. Design-Build gives the owner one entity for design and construction, which is efficient but removes the owner's independent check on whether the design meets the program. The CM restores it.
4. Under IPD, the CM's role shifts primarily toward:
Sole owner advocate, negotiating against the builder and designer for the owner
Permit expediter only
Bonding agent that guarantees the team's performance to the owner
Integrator/facilitator within a shared-risk team
Answer: d. IPD replaces the adversarial contract structure with a shared-risk, shared-reward agreement. There is no longer one party to advocate against, so the CM's value shifts from advocacy to integration.
5. Which delivery method typically requires the CM to carry performance and payment bonds?
CM at Risk
Multiple Prime Contracting
CM as Advisor under DBB
IPD
Answer: a. Once the CM holds the construction contract (at risk), bonding obligations typically transfer to the CM like any general contractor.
6. CMAA's Standards of Practice describe the CM's core duty as:
Serving as the architect of record and sealing the design documents for the permit submittal
Protecting the owner's interests across planning, design, and construction
Maximizing contractor profit
Acting as project attorney
Answer: b. CMAA frames the CM as the owner's professional agent. The duty runs across the whole life cycle, not just the construction phase, which is why the answer names all three stages.
7. A scenario states: "the owner holds one contract for both design and construction, delivered by a single entity." This is:
DBB
Design-Build
CM at Risk with a GMP
IPD
Answer: b. One contract, one entity, both design and construction, is the definition of Design-Build. DBB splits them into two contracts; CM at Risk keeps design separate and puts the CM in the builder's seat.
8. An owner holds separate direct contracts with a site-work contractor, a structural contractor, and an MEP contractor, with no single general contractor over all three. This is:
Integrated Project Delivery
Design-Build
Multiple Prime Contracting
Job Order Contracting
Answer: c. Multiple Prime Contracting is the owner holding direct contracts with several prime contractors instead of one general contractor holding all the subcontracts. It shifts inter-trade coordination onto the owner or the owner's CM.
9. A public agency selects a contractor once, with pricing tied to a unit-price book, and then issues individual job orders for repair and renovation work as it comes up, without re-bidding each job. This describes:
Design-Bid-Build
Progressive Design-Build, with price negotiated as design develops
Job Order Contracting (JOC)
CM at Risk
Answer: c. JOC is an indefinite-delivery, indefinite-quantity arrangement built around a pre-negotiated unit-price book, used where re-bidding every small job would be too slow to administer.
10. In a CM at Risk arrangement, a GMP contract is best described as:
A negotiated cost ceiling: the CM bears costs above it absent an approved change, and savings are typically shared
A price that can never be exceeded under any circumstance, including owner-directed changes to scope, and that is set by competitive bid on complete drawings
A price set only after construction is complete
A fixed bid price identical to a DBB contract
Answer: a. A GMP is negotiated, not bid, and it caps the owner's exposure while making the CM responsible for overruns absent an approved change order. Savings below the GMP are typically shared per the CM contract's terms.
11. Which factor most directly favors choosing a fast-track-capable delivery method (CMAR, Design-Build, or IPD) over Design-Bid-Build?
The owner needs design and construction to overlap to compress the overall project schedule
The project is simple and well understood with no schedule pressure
The owner wants maximum price competition on a fully completed design
The owner wants the lowest possible number of contracts to manage regardless of schedule
Answer: a. DBB cannot fast-track because bidding requires a complete design first. An owner that needs to compress schedule by overlapping design and construction needs a method built to allow that.
12. "Open book" in a CM at Risk arrangement refers to:
A public bidding requirement under DBB
The design-builder's obligation to publish its drawings
A term with no defined meaning in construction management
The owner's access to the CM's actual buyout costs, general conditions, and fee
Answer: d. Because a GMP is negotiated rather than competitively bid, open-book cost visibility into the CM's actual costs and fee is the owner's main safeguard against the CM's added contractual authority working against the owner's interest.
13. In Progressive Design-Build, who holds the construction contract, and how does that differ from CM at Risk?
No one holds a construction contract in Progressive Design-Build
The owner holds it directly, as in Multiple Prime Contracting, while the design-builder only supplies design services
The CM holds it, identical to CMAR in every respect, with the design-builder acting only as a subconsultant
The design-builder holds it, together with the design; under CMAR a separate CM holds it and design stays separate
Answer: d. Progressive Design-Build develops price progressively much like a GMP does under CMAR, but the design-builder, not a CM, is the single entity holding both design and construction.
14. An owner needs a firm, bid-certain construction cost before committing further funds, is not in a schedule hurry, and is building a well-understood facility type. Which delivery method best fits, and why?
IPD, because shared risk always produces the lowest cost
Design-Bid-Build, because a complete, competitively bid design gives the strongest cost certainty when schedule compression is not required
Job Order Contracting, because it avoids bidding entirely
Progressive Design-Build, because price is negotiated instead of bid
Answer: b. DBB's core strength is cost certainty from competitive bidding on a complete design. Where schedule compression is not needed and the building type is well understood, that strength outweighs DBB's inability to fast-track.
Micro-Assignment
Pick a real or hypothetical project you're familiar with. Write 4-6 sentences identifying which delivery method it used (or would suit) and whether the CM's posture is Agency or At-Risk, then state specifically what the CM's authority would and would not include under that method. Save this, since you'll reuse the format in Day 3's Project Management Plan exercise.
Glossary
Agency CM (CM as Advisor)
CM represents the owner as a fee-for-service advisor without holding the construction contract directly.
CM at Risk (CMAR)
CM converts from an advisory role to holding the construction contract, typically under a GMP, taking on contractor-like bonding and performance obligations.
GMP (Guaranteed Maximum Price)
A negotiated contract cost ceiling; the CM/contractor is responsible for costs above it absent an owner-approved change, with savings typically shared per the contract's terms.
Open book
The owner's contractual right to see the CM's actual buyout costs, general conditions, and fee, common in negotiated GMP arrangements.
Design-Build (DB)
A single entity holds one contract with the owner for both design and construction.
Progressive Design-Build
A Design-Build variant where the design-builder is selected on qualifications before a price exists, and price develops progressively as design matures.
IPD
Integrated Project Delivery: one multi-party agreement among owner, designer, and builder, sharing risk and reward.
Multiple Prime Contracting
The owner holds separate direct contracts with several prime contractors instead of one general contractor holding all the trade subcontracts.
Job Order Contracting (JOC)
An indefinite-delivery, indefinite-quantity arrangement built on a pre-negotiated unit-price book, used to issue individual job orders without re-bidding each one.
Fast-track
Overlapping design and construction to compress overall project schedule; not possible under Design-Bid-Build.