Day 11: Acceleration, Recovery, and Module Mini-Exam
9% of the exam - about 2.5 hours - 14 practice questions
0:00 / --:--
Reading
Recovery versus acceleration are distinct and the exam separates them.
Recovery: the contractor's own obligation
Recovery is the contractor's obligation to get back on schedule after a non-excusable delay that the contractor caused. The contractor bears the cost. A recovery schedule is typically required by contract once the contractor falls behind by a defined threshold, and the CM reviews it like a baseline, checking that the proposed recovery is physically achievable rather than a paper exercise.
Directed acceleration: crashing and fast-tracking
Acceleration is compressing the schedule to finish earlier than the current contractual completion date. If the owner directs it, it is directed acceleration and the owner pays. The classic methods are crashing, which adds resources to critical activities and raises cost, and fast-tracking, which overlaps activities that would normally run in sequence and raises risk of rework.
When crashing, the correct target is the critical activity with the lowest cost per day saved. Adding resources to a non-critical activity buys nothing but cost. This is a common exam question, and the right answer is always to crash on the critical path, cheapest first, rechecking after each compression because the critical path can shift.
Crash the cheapest critical days first. As compression continues, sustained overtime and trade stacking degrade productivity, so the cost of each additional day saved rises steeply rather than staying flat.
Constructive acceleration
Constructive acceleration is the subtle one, and it appears on the exam. It occurs when the contractor experiences an excusable delay, requests a time extension it is entitled to, the owner refuses or fails to act on the request, and the contractor is then compelled to accelerate to meet the original date. The owner never issued an acceleration directive, but the effect is the same, and the contractor may recover acceleration costs. The elements usually cited are an excusable delay, a timely request for extension, denial or unreasonable failure to grant, some owner insistence on the original completion date, and actual acceleration costs incurred.
The practical lesson for the CM is direct. Sitting on a legitimate time extension request does not save the owner money. It converts a time-only exposure into a time-and-money exposure. When a question offers "defer the extension request and require the contractor to maintain the original date," that is usually the wrong answer.
Diminishing returns in acceleration
Overtime, added shifts, and crew stacking all reduce productivity per labor hour. Sustained overtime is generally understood to degrade productivity meaningfully, and trade stacking in confined areas degrades it further. The CM evaluating an acceleration proposal should expect the cost per day saved to rise steeply as compression increases, and should be skeptical of proposals that claim linear cost for nonlinear compression.
Time impact analysis, revisited
The forward-looking, contemporaneous method generally preferred for evaluating a delay is a time impact analysis. You take the schedule update in effect immediately before the delay event, insert a fragnet representing the delay, recalculate, and measure the movement of the project completion date. Because it uses the schedule as it stood at the time, it avoids the hindsight distortion of as-built analyses performed years later. Contracts increasingly require TIA for any time extension request.
Practice Questions
1. A contractor falls behind due to its own low productivity. The schedule compression required is:
Constructive acceleration
Recovery, contractor pays
Directed acceleration, owner pays
Force majeure
Answer: b. The contractor caused it, so the contractor pays to recover. Directed acceleration is when the owner asks for early completion; that is a different thing and the owner funds it.
2. When crashing a schedule, resources should be added to:
The critical activity with the lowest cost per day saved, rechecking each round
Non-critical activities, to build float that protects the critical path from further slippage
The longest activity regardless of path
All activities equally
Answer: a. Crash the cheapest critical day first, then recheck. Compressing one path can make a different path critical, so continuing without rechecking spends money without shortening the project.
3. Fast-tracking primarily increases:
Retainage
Direct cost only, because overlapping activities require added crews on both activities
Risk of rework from overlapping activities
Float
Answer: c. Fast-tracking overlaps work that would normally run in sequence, which means starting the successor before the predecessor is fully settled. When the predecessor changes, the successor gets reworked.
4. Constructive acceleration generally requires:
A force majeure event that shuts down the critical path for longer than the contract's stated limit
Contractor default after the CM rejected two recovery schedules and the owner terminated the contractor for cause
An excusable delay, a timely extension request, its denial, insistence on the original date, and added cost
A written acceleration directive from the owner
Answer: c. Constructive acceleration has five parts: an excusable delay, a timely request for extension, the owner's denial or silence, insistence on the original date, and actual acceleration costs. All five, or it is not constructive.
5. An owner delays acting on a legitimate time extension request to avoid granting time. The likely consequence is:
Cost savings to the owner
Contractor default, since the contractor may no longer rely on the extension request it filed
No effect
Turning a time-only exposure into a time-and-money exposure (constructive acceleration)
Answer: d. Refusing to grant time the contractor is entitled to does not save the owner money. It converts an obligation to grant days into an obligation to pay acceleration costs.
6. Time impact analysis is generally preferred because it:
Eliminates the need for notice
Uses the schedule in effect immediately before the delay, avoiding hindsight distortion
Is the cheapest method, because it needs only the final as-built schedule and no update history
Always favors the owner
Answer: b. Time impact analysis inserts the delay into the schedule as it stood just before the event, so the analysis reflects what was actually critical at the time rather than what turned out to matter later.
7. A contractor proposes accelerating 20 days at a cost that scales linearly with days saved. The CM should be:
Satisfied, since a linear cost curve makes the proposal easy to check against the contractor's unit rates and the independent estimate
Indifferent
Skeptical, since overtime and trade stacking degrade productivity and cost per day saved normally rises
Required to accept it
Answer: c. Acceleration cost is not linear. Sustained overtime and trade stacking degrade productivity, so each additional day saved costs more than the one before it.
8. A recovery schedule should be reviewed by the CM primarily to check that it is:
Signed by the surety, since the surety guarantees completion on the original contract date
Physically achievable rather than a paper exercise
Identical to the original baseline
Funded entirely by the owner
Answer: b. A recovery schedule that looks good on paper but assumes impossible productivity gains does not actually get the project back on track. The CM's review checks feasibility, not just arithmetic.
9. Which of the following is a required element of constructive acceleration?
A timely extension request that the owner denies or ignores, plus insistence on the original date
Termination of the contract
A written directive from the owner to accelerate, issued after the owner denied the contractor's extension request in writing
A non-excusable delay caused by the contractor
Answer: a. Constructive acceleration requires an excusable delay, a timely extension request, the owner's denial or unreasonable inaction, continued insistence on the original date, and actual acceleration costs. No formal directive is ever issued, which is exactly why it is "constructive."
10. On the crash-cost curve, why does the cost per day saved rise steeply after the first several days of compression?
Because standard contracts prohibit crashing more than ten days without a new notice to proceed
Because crashing only ever affects non-critical activities
It doesn't; cost per day saved is always constant
Sustained overtime and trade stacking degrade productivity as compression increases
Answer: d. The first days crashed are typically the cheapest available options. As compression continues, overtime premiums and productivity losses from crew stacking push the marginal cost of each additional day saved higher.
11. Fast-tracking and crashing both compress the schedule, but they differ because:
Fast-tracking always costs less than crashing, because overlapping work needs no added resources
Crashing is never used on the critical path
They are the same technique with different names
Crashing adds resources to shorten durations; fast-tracking overlaps sequential activities
Answer: d. Crashing buys duration with more resources at higher cost. Fast-tracking buys duration by overlapping work that would normally wait, at higher risk of rework instead.
12. A CM continues crashing a schedule without rechecking the critical path after each round of compression. The risk is:
Spending money crashing a path that is no longer critical, buying nothing
Answer: d. Compressing one path can make a different path critical. Continuing to crash the original path after that shift spends money without shortening the project at all.
13. Recovery and directed acceleration differ primarily in:
Who caused the need to compress the schedule, and therefore who pays
Recovery is always cheaper
There is no meaningful difference
Both are always owner-funded
Answer: a. Recovery responds to the contractor's own delay, so the contractor pays. Directed acceleration responds to the owner's wish to finish early, so the owner pays. Same compression techniques, different party bears the cost.
14. A time impact analysis is generally preferred over a purely retrospective as-built comparison because it:
Reflects what was actually critical at the time of the event, rather than being distorted by hindsight
Never requires notice
Applies only to non-excusable delay
Is always faster to prepare
Answer: a. Because a TIA models the schedule as it stood right before the event, it avoids the distortion of judging criticality with the benefit of hindsight, years after the fact.
Glossary
Recovery
Contractor-funded effort to get back on schedule after a contractor-caused delay.
Directed acceleration
Owner-directed compression of the schedule to finish earlier than the contractual date; owner pays.
Crashing
Adding resources to critical activities to shorten duration, raising cost.
Fast-tracking
Overlapping activities that would normally run in sequence, raising rework risk.
Constructive acceleration
Contractor forced to accelerate after an owner denies or ignores a legitimate time extension request; owner bears the acceleration cost despite issuing no formal directive.
Time Impact Analysis (TIA)
Forward-looking delay analysis method that inserts a delay fragnet into the schedule as it stood immediately before the event.