Finishing a grant properly, on the deadlines that actually apply · 14 practice questions
0:00 / --:--
Reading
Closeout is the formal end of a grant, the point at which the
recipient (or subrecipient) has finished the work, submitted its final
paperwork, and settled every financial obligation tied to the award.
2 CFR 200.344 governs closeout, and its deadlines are specific, and
specific numbers are exactly the kind of detail a rushed grants manager
gets wrong under pressure at the end of a project.
The closeout deadlines: 120 days, 90 days
Under 200.344, a recipient must submit all required closeout reports,
and settle all outstanding financial obligations, no later than 120
calendar days after the conclusion of the period of performance. A
subrecipient reporting to a pass-through entity works on a shorter clock,
90 calendar days after the subaward's period of performance ends (or an
earlier date agreed with the pass-through entity), which in practice leaves
the pass-through entity time to roll subrecipient information into its own
120-day closeout package. When justified, the federal agency or pass-through entity
may approve extensions, but neither is automatic; an organization that expects to need more time
should ask for an extension before the deadline passes, not after.
What "settling financial obligations" covers
Closeout is not only paperwork, it requires liquidating (paying off
and finalizing) every financial obligation tied to the award within the
same 120-day (or 90-day, for a subrecipient) window. That includes
paying final invoices, resolving any outstanding cost questions, and
making sure the accounting records reconcile to what was actually drawn
down and spent. Costs of administrative closeout can be incurred until the
due date of the final reports, but they must be liquidated before that date
(200.403(h)).
Unobligated funds must be returned
Any federal funds that were paid to the recipient or subrecipient but
never obligated, and that the organization is not authorized to keep,
must be promptly refunded to the federal agency or pass-through entity
that paid them. Sitting on unspent, unobligated federal money past
closeout is not a minor administrative lapse, it is federal funds the
organization has no authority to hold.
Property still has to be accounted for
If the award funded the purchase of property or equipment, or the
organization received government property to carry out the work,
closeout requires that property to be accounted for consistent with the
property management rules elsewhere in 2 CFR 200 (Subpart D's property
standards, sections 200.310 through 200.316, and 200.330, which covers
reporting on real property). Closeout does not erase the property
recordkeeping requirement: 200.344(g) expressly requires property acquired
with federal funds, or received from the federal government, to be
accounted for under those sections.
The one-year outer boundary for the federal agency
200.344 also puts a target on the federal agency's own side of
closeout: the federal awarding agency is expected to make every effort
to complete all closeout actions no later than one year after the end
of the period of performance. This is framed as an expectation for the
agency to complete its own closeout review and sign-off, not a deadline
the recipient itself is racing against, the recipient's own deadlines
are the 120- and 90-day figures above.
Why closeout connects back to everything already covered
Closeout is where every earlier domain converges. The final
performance report due at closeout is built on the same reporting
discipline from lesson 4 (financial data connected to program
accomplishments). Any indirect costs charged in the award's final months
have to meet the same 200.403 allowability factors from lesson 2.
Property purchased mid-award has to be accounted for using the same
rules referenced here. And a pass-through entity closing out its own
award to a federal agency has to have already collected clean closeout
information from every subrecipient it oversees, tying back to lesson
6's monitoring duties. A grants manager who treats closeout as a
separate, late-stage task disconnected from everything that came before
will find the 120-day window is not nearly long enough to fix problems
that should have been caught earlier.
Subrecipients close out to their pass-through entity in 90 days; the pass-through entity (or a direct recipient) closes out to the federal agency in 120 days, giving the shorter subrecipient window time to roll up into the longer one.
Practice questions
1. Under 2 CFR 200.344, how many calendar days does a direct recipient have to submit all closeout reports and settle financial obligations after the period of performance ends?
30 days
90 days
120 days
365 days
Answer: c. A direct recipient has 120 calendar days after the period of performance ends to submit closeout reports and settle obligations.
2. How many calendar days does a subrecipient have to complete the same closeout steps, reporting to its pass-through entity?
120 days
90 days
30 days
180 days
Answer: b. A subrecipient has 90 calendar days, shorter than the recipient's 120, so the pass-through entity has time to roll subrecipient closeout data into its own submission.
3. Are the 120-day and 90-day closeout deadlines ever extendable?
Yes, when justified and approved, so an extension should be requested before the deadline passes
No, both deadlines are absolute and the agency has no authority to approve an extension for any reason
Only the 90-day subrecipient deadline can be extended, never the 120-day recipient deadline, under any circumstances
Yes, extensions are granted automatically to every organization that simply asks for more time in writing
Answer: a. 200.344(b) and (c) let the federal agency or pass-through entity approve extensions when justified, but they must be requested and approved, not assumed, and ideally before the original deadline passes.
4. What must happen to federal funds that were paid out but never obligated, and that the organization has no authority to keep?
They can be kept as a reserve for the organization's next federal award, if it is in the same program
They can be transferred to a different federal program the organization already administers, without approval
They can be held for one more year and refunded with the next annual report, as long as they are tracked
They must be promptly refunded to the federal agency or pass-through entity that paid them
Answer: d. 200.344(e) requires the recipient or subrecipient to promptly refund any unobligated funds that were paid to it and that it is not authorized to retain.
5. Does closeout eliminate the requirement to account for property purchased with federal funds?
Yes, property records can be discarded once the closeout reports are filed and accepted
No, 200.344(g) still requires property acquired with federal funds to be accounted for under the property standards
Property accounting only applies to construction awards and real property acquisitions
Property accounting is optional at the recipient's discretion once the period of performance ends
Answer: b. 200.344(g) requires property acquired with federal funds, or received from the federal government, to be accounted for under 200.310 through 200.316 and 200.330. Closeout is not a point where the requirement disappears.
6. What is the federal awarding agency's own target for completing all closeout actions on its side?
No later than one year after the end of the period of performance
Within 30 days of the recipient's submission of its final reports, whichever date is earlier
Within 120 days, identical to the recipient's own deadline, so both close out together
There is no target; agencies may take as long as they wish, with no stated expectation
Answer: a. 200.344(h) says the federal agency must make every effort to complete all closeout actions no later than one year after the end of the period of performance.
7. What is the practical effect of a subrecipient's closeout deadline falling 30 days before a direct recipient's deadline?
It has no functional effect; the pass-through entity's own closeout is unaffected by when its subrecipients report
Subrecipients are penalized with a shorter window because they are presumed less trustworthy than direct recipients
It leaves the pass-through entity time to roll subrecipient closeout information into its own 120-day submission
Subrecipients always have smaller awards, which close out faster than larger awards do under the closeout rule
Answer: c. The 30-day gap between the subrecipient's 90-day deadline and the recipient's 120-day deadline, in practice, leaves the pass-through entity time to incorporate subrecipient data into its own submission to the federal agency.
8. Which of the following is part of "settling financial obligations" at closeout?
Only submitting a final narrative report, with no financial reconciliation required
Paying final invoices, resolving outstanding cost questions, and reconciling accounting records to actual drawdowns and spending
Only refunding 10 percent of unspent funds
Financial obligations are settled automatically once the period of performance ends, with no action needed
Answer: b. Settling financial obligations means actually finishing the financial side, paying final invoices, resolving cost questions, and reconciling records, not just filing a narrative report.
9. Which section of 2 CFR 200 governs closeout?
200.318
200.403
200.512
200.344
Answer: d. 2 CFR 200.344, Closeout, is within Subpart D, Post Federal Award Requirements.
10. A grants manager waits until the 118th day of the 120-day closeout window to discover unresolved cost questions on the award. What does this scenario illustrate?
Closeout problems usually trace back to issues that should have been caught earlier, not left to the deadline
This is a normal and expected way to run closeout, since the full 120 days is meant to be used for discovery of problems
The 120-day window exists specifically to allow last-minute discoveries like this to be fixed at the very end of the award
Nothing; the deadline is only advisory and can be moved by the grants manager without any agency approval
Answer: a. Closeout works best when earlier domains, cost allowability, reporting discipline, monitoring, were handled well throughout the award; problems discovered only at the deadline rarely leave enough time to fix within the window.
11. GCHS is closing out a subgrant it made to a partner nonprofit. Whose closeout deadline governs when GCHS needs the subrecipient's final numbers in hand?
The subrecipient has no deadline of its own; only GCHS's 120-day deadline to the federal agency applies to the subaward
The subrecipient's 90-day deadline to GCHS, which leaves GCHS time before its own 120-day deadline
Both deadlines are 120 days, identical, because the subaward and the prime award share one closeout date
The subrecipient has one year, matching the federal agency's own target for completing closeout actions
Answer: b. The subrecipient's 90-day deadline (or an earlier agreed date) runs to GCHS as the pass-through entity, leaving GCHS the remaining time before its own 120-day deadline to the federal agency (200.344(b)).
12. How does this course group closeout among NGMA's four exam domains?
Grant Guidance only, since closeout is a pre-award planning topic covered in the notice of funding opportunity
Mainly Grant Award, as the last stage of the award lifecycle, drawing on the other domains too
Fiscal Management only, since closeout consists entirely of financial reconciliation and refunds
None of the four domains address closeout, so the course leaves it ungrouped and unassigned
Answer: b. This course places closeout mainly in Grant Award, as the formal end of the award's lifecycle, while it draws on Fiscal Management (financial reconciliation) and Program Management (final performance reporting). NGMA's blueprint lists tasks rather than closeout by name, so treat the grouping as a study aid.
13. If final closeout reporting deadlines mirror the reporting deadlines discussed in lesson 4, what should a grants manager expect the final performance report deadline to be for a direct recipient?
120 days after the period of performance ends, per 200.329(c) and 200.344(b)
30 days, unrelated to the closeout deadline, so it can be filed well before financial reports
One year, matching the federal agency's own target for finishing its closeout actions
There is no deadline for a final performance report as long as financial reports are on time
Answer: a. 200.329(c) makes the recipient's final performance report due no later than 120 calendar days after the period of performance, and 200.344(b) sets the same 120 days for all closeout reports (90 days for a subrecipient reporting to a pass-through entity).
14. What is the practical risk of treating closeout as an isolated, late-stage task disconnected from how the award was managed throughout its life?
There is no risk; closeout is entirely independent of earlier award management
Closeout automatically corrects any earlier compliance problems
The 120- (or 90-) day window is rarely long enough to fix problems, unresolved cost questions, missing documentation, incomplete monitoring records, that should have been caught earlier
Closeout has no deadlines, so there is no real risk either way
Answer: c. Closeout's short window means problems that trace back to earlier stages of the award (cost allowability, reporting, subrecipient monitoring) are difficult to fix if only discovered at closeout.
Glossary
Closeout
The formal end of a grant: final reports submitted, financial obligations settled, unobligated funds refunded, and property accounted for.
2 CFR 200.344
The Uniform Guidance section governing closeout, including its 120-day (recipient) and 90-day (subrecipient) deadlines.
Unobligated funds
Federal funds paid out but never committed to an allowable purpose; must be promptly refunded if the organization has no authority to keep them.
Period of performance
The window of dates during which costs may be incurred under an award; closeout deadlines are measured from its end.