Lesson 5: Allowable Height and Area

IBC 504, 505, 506 · 14 practice questions

0:00 / --:--

Reading

Chapter 5 answers three questions for every new building: how tall, how many stories, and how big. All three come from a lookup that uses the same three inputs: the occupancy group (Lessons 2 and 3), the construction type (Lesson 4), and whether the building has an automatic sprinkler system. This lesson reads Tables 504.3, 504.4 and 506.2, adds the frontage increase, and works one one-story example. Local adoption governs, so confirm the tables in the adopted code.

One-story store: frontage open space and allowable area A plan of a 300 by 150 foot one-story Group M building with open space of 80 feet at the front, 30 feet on the right, 25 feet on the left and 12 feet at the back. The back does not count. The other sides are 66.7 percent of the perimeter, the smallest open space is 25 feet, and the frontage factor is 0.42. An elevation and two check boxes complete the example. Plan (not to scale), dashed line is the lot line Group M, Type IIB 300 ft x 150 ft one story, sprinklered Street (public way) Front: 80 ft (yard plus street) counts 30 ft counts 25 ft counts Back: 12 ft, under 20 ft, does not count Green counts as open space (20 ft or more). Orange does not. Front elevation 22 ft One story Height check (Tables 504.3, 504.4) 75 ft and 3 stories, sprinklered 55 ft and 2 stories, nonsprinklered One story at 22 ft: passes either way Area check (Equation 5-1) Open: 600 of 900 ft = 66.7 percent Smallest W = 25 ft, so If = 0.42 Sprinklered: 50,000 + (12,500 x 0.42) = 55,250 sq ft, so 45,000 fits Nonsprinklered: 12,500 + 5,250 = 17,750 sq ft, so 45,000 fails
A one-story store with open space on three sides: the smallest counted open space sets the frontage factor, and the sprinkler column changes everything.

How height, stories and area are measured

Building height is the vertical distance from grade plane to the average height of the highest roof surface. Grade plane is the average of the finished ground level at the exterior walls (on a slope, the lowest points between the building and the lot line, or a point 6 feet from the building if the lot line is farther). A story above grade plane has its finished floor entirely above grade plane, or the floor next above is more than 6 feet above grade plane, or more than 12 feet above the finished ground at any point. A basement is any other story, and Section 506.1.3 lets it go uncounted in allowable area when its total area does not exceed what a one-story building is allowed. Building area is measured inside the surrounding exterior walls (or exterior walls and fire walls), excluding vent shafts and courts.

Table 504.3 and Table 504.4: height and stories

Height is in feet and stories are counted separately. S means sprinklered throughout under 903.3.1.1. One row covers Groups A, B, E, F, M, S and U in Table 504.3.

Height, ft (Groups A, B, E, F, M, S, U)IAIBIIAIIBIIIAIIIBVAVB
NonsprinkleredUL160655565555040
SprinkleredUL180857585757060

UL means unlimited. Type IV-A sprinklered allows 270 feet, IV-B 180 feet, and IV-C and IV-HT 85 feet. Group R with 13R gets 60 feet in every type. The nonsprinklered R values apply only when evaluating existing buildings, because new Group R must be sprinklered (903.2.8). Section 903.3.1.2 adds its own limit on 13R: four stories or fewer, with the highest floor 30 feet or less above fire department vehicle access.

StoriesIIAIIBIIIAIIIBVAVB
B nonsprinklered / sprinklered5 / 63 / 45 / 63 / 43 / 42 / 3
M nonsprinklered / sprinklered4 / 52 / 34 / 52 / 33 / 41 / 2
R-2 sprinklered (NFPA 13)555543

Type IA is unlimited for these groups, and Type IB allows 11 stories nonsprinklered or 12 sprinklered. R-2 with 13R gets 4 stories, or 3 in Type VB.

Table 506.2: tabular area

Table 506.2 gives the tabular area At in square feet for one story. NS is nonsprinklered. S1 is a one-story building sprinklered under 903.3.1.1. A separate SM value covers sprinklered buildings of two or more stories and is not shown here.

GroupIIB NSIIB S1VA NSVA S1VB NSVB S1
B23,00092,00018,00072,0009,00036,000
M12,50050,00014,00056,0009,00036,000
S-117,50070,00014,00056,0009,00036,000

Equation 5-1 gives the allowable area per story for a single-occupancy building up to three stories above grade plane: Aa = At + (NS x If). At is the table value for the sprinkler condition, NS is the nonsprinklered table value even when the building is sprinklered, and If is the frontage factor. For more than three stories, Equation 5-2 sets a total allowable area, and no floor may exceed its Equation 5-1 value. For multistory buildings, confirm which sprinkler column applies with the adopted code and the building official.

The frontage increase (Section 506.3)

A building must adjoin or have access to a public way, and at least 25 percent of its perimeter must be on a public way or open space (506.3.1). The open space may be on the same lot or dedicated to public use, reachable from a street or approved fire lane. The frontage distance W is measured at right angles from the building face to the closest interior lot line, across the entire width of a street, alley or public way, or to the face of another building on the same property (506.3.2). Only open space of 20 feet or more counts, and the increase uses the smallest counted space. In 2021, Table 506.3.3 replaced the old equation.

Perimeter with open space of 20 ft or moreW 20 to under 25 ftW 25 to under 30 ftW 30 ft or more
25 to under 50 percent0.170.210.25
50 to under 75 percent0.330.420.50
75 to 100 percent0.500.630.75

Below 25 percent of the perimeter, or with W under 20 feet, If is 0. The largest possible If is 0.75.

Key numbers
  • Type IIB height: 55 ft nonsprinklered, 75 ft sprinklered (Table 504.3)
  • Aa = At + (NS x If): the frontage factor multiplies the nonsprinklered value, never the sprinklered one
  • Frontage: 25 percent of perimeter, 20 ft or more, maximum If 0.75 (Table 506.3.3)
  • Mezzanines: one-third of the room's floor area; 7 ft clear above and below (505.2)

Sprinklers, mixed occupancies and mezzanines

In 2021, Section 504.2 is about mixed occupancy: no occupancy may exceed the height and story limits for that occupancy. Sprinklers are a column choice in the tables: S is 903.3.1.1, S13R is 903.3.1.2, and S13D is 903.3.1.3, and the area increase is built into the S1 and SM values. For mixed occupancies, area follows Section 508.3.2 (nonseparated) or 508.4.2 (separated, where the sum of the ratios of actual area to allowable area on each story cannot exceed 1).

A compliant mezzanine is part of the story below. It adds nothing to the number of stories or the building area, although its area counts toward the fire area, and it needs at least 7 feet clear above and below. Under 505.2.1, all the mezzanines in a room together may cover no more than one-third of that room's floor area. The one-half exceptions are narrow: sprinklered Type I or II buildings with emergency voice/alarm communication, and mezzanines inside a dwelling unit of a sprinklered building.

Worked example: the one-story store

A developer proposes a 45,000 square foot, one-story Group M store, 300 feet by 150 feet, of Type IIB construction. The perimeter is 2 x (300 + 150) = 900 feet. Open space is 80 feet at the front, 30 feet on the right, 25 feet on the left, and 12 feet at the back, which is under 20 feet and does not count. Counted perimeter is 300 + 150 + 150 = 600 feet, or 66.7 percent, the 50 to under 75 percent row. The smallest counted open space is 25 feet, so Table 506.3.3 gives If = 0.42. Table 506.2 gives Group M Type IIB an NS of 12,500 and an S1 of 50,000. Sprinklered: Aa = 50,000 + (12,500 x 0.42) = 55,250 square feet, so 45,000 fits. Nonsprinklered: Aa = 12,500 + 5,250 = 17,750 square feet, so it does not. Height and stories pass either way.

In the field

An owner asks GCHS to estimate a 6,000 square foot addition to a 5,000 square foot, one-story, unsprinklered Group B office of Type VB. The total, 11,000 square feet, is over the 9,000 square foot nonsprinklered base for that group and type. Either generous open space has to carry the frontage increase, or a sprinkler system, which moves the base to 36,000, has to be priced in. Ask the building official which before pricing.

Practice questions

1. Under Table 504.3, the allowable height of a Group B building of Type IIB construction sprinklered throughout under 903.3.1.1 is:

  1. 55 feet
  2. 65 feet
  3. 85 feet
  4. 75 feet

2. Under Table 504.3, the allowable height of a nonsprinklered Group M building of Type VB construction is:

  1. 50 feet
  2. 40 feet
  3. 55 feet
  4. 60 feet

3. Under Table 504.4, a nonsprinklered Group B building of Type IIB construction may be at most:

  1. 3 stories
  2. 2 stories
  3. 4 stories
  4. 5 stories

4. Under Table 504.4, a sprinklered Group M building of Type VB construction may be at most:

  1. 1 story
  2. 3 stories
  3. 2 stories
  4. 4 stories

5. An inspector measures the average height of the highest roof surface of a sprinklered Group B building of Type VB at 64 feet above grade plane. What is the finding?

  1. It complies, because the sprinklered limit is 70 feet
  2. The building exceeds the 60 foot limit for a sprinklered Type VB building
  3. It complies, because roof height is not measured
  4. It complies, because Group B has no height limit

6. In Equation 5-1, Aa = At + (NS x If), the term NS represents:

  1. the number of stories
  2. the sprinkler increase
  3. the net site area
  4. the nonsprinklered tabular area, used even when the building is sprinklered

7. To earn any frontage increase, Section 506.3.1 requires at least what share of the building perimeter on a public way or open space?

  1. 10 percent
  2. 33 percent
  3. 25 percent
  4. 50 percent

8. For the frontage increase, open space counts toward W only when it is at least:

  1. 20 feet
  2. 10 feet
  3. 15 feet
  4. 30 feet

9. An inspector reviews a one-story building with open space of 32 feet or more on 80 percent of its perimeter, the smallest open space being 32 feet. Table 506.3.3 gives an If of:

  1. 0.50
  2. 0.63
  3. 0.25
  4. 0.75

10. A one-story, nonsprinklered Group B building of Type IIB construction has a frontage factor If of 0.25. Using Table 506.2 (NS 23,000), the allowable area under Equation 5-1 is:

  1. 23,000 square feet
  2. 28,750 square feet
  3. 34,500 square feet
  4. 46,000 square feet

11. A one-story, sprinklered Group B building of Type IIB has NS 23,000, S1 92,000, and If of 0.25. The allowable area under Equation 5-1 is:

  1. 97,750 square feet
  2. 92,000 square feet
  3. 115,000 square feet
  4. 28,750 square feet

12. An inspector reviews a Group B room of 6,000 square feet in an unsprinklered Type IIB building. What is the maximum aggregate mezzanine area in that room?

  1. 3,000 square feet
  2. 4,000 square feet
  3. 2,000 square feet
  4. 6,000 square feet

13. A mezzanine that complies with Section 505.2 is treated as:

  1. a separate story that adds to the story count
  2. part of the story below, adding neither to the number of stories nor to building area
  3. part of the building area, added to the story below
  4. exempt from all other code provisions

14. An inspector finds a lower level with its finished floor below grade plane, but the floor next above is 8 feet above grade plane. Under the definitions, that lower level is:

  1. a basement
  2. a basement only if unsprinklered
  3. not counted unless the floor above is 12 feet above grade plane
  4. a story above grade plane

Glossary

Grade plane
The reference plane of average finished ground level at the exterior walls, used to measure height and to decide which floors are stories above grade plane.
Story above grade plane
A story whose finished floor is entirely above grade plane, or whose next floor above is more than 6 ft above grade plane or more than 12 ft above finished ground at any point.
Basement
A story that is not a story above grade plane; it may go uncounted in allowable area if it does not exceed the area allowed for a one-story building (506.1.3).
Tabular area (At)
The allowable area value in Table 506.2 for an occupancy group, type and sprinkler condition, before any frontage increase.
Frontage increase (If)
The factor from Table 506.3.3 for open perimeter and open space width, applied to the nonsprinklered tabular value in Equation 5-1.
Mezzanine
An intermediate level within a room that counts as part of the story below when open, at least 7 ft clear above and below, and within the one-third limit.
NS, S1, SM
Table 506.2 columns for nonsprinklered, one-story sprinklered, and multistory sprinklered buildings.