Reading
Thirteen lessons have taught how mechanical and fuel gas systems are designed and installed. Two things prove the finished work. Inspections say who looks, at what point, and what must stay uncovered until they do. Tests say how each system is shown to be tight and safe before it is covered or put in service. Chapter 1 of the 2021 IMC and IFGC sets the inspection and testing rules for both books, and four places set the specific tests: IMC Sections 1011, 1110 and 1208, and IFGC Section 406. Texas cities choose their own mechanical code and Houston enforces the Uniform Mechanical Code (Lesson 1), so treat every number here as a 2021 IMC or IFGC value and confirm the adopted code and any local test rule before you rely on one. This lesson teaches the tests, then reviews the whole course.
Each system has its own medium, pressure and hold time, and the pipe stays exposed until its test is done.
The three inspections (IMC 108.2, IFGC 112.2)
Both books name the same three inspections. The underground inspection comes after trenches are excavated and bedded and the piping is installed, and before backfill. The rough-in inspection comes after the roof, framing, fireblocking and bracing are in place and everything to be concealed is complete, and before wall or ceiling membranes go up. The final inspection comes when the installation is complete. The permit holder schedules each one, tells the code official when the work is ready, and provides access (108.2.2, 112.2.2). The official may add other inspections (108.2.1). Two provisions from Lesson 1 belong beside them: a ground-source loop tested under IMC 1210.10 may be backfilled before inspection, and replacement heating equipment may keep running if an inspection is requested within 48 hours and before anything is concealed.
Inspection
Work must be
Tests that normally go with it
Underground
Bedded and piped, before backfill
Underground gas piping test (IFGC 404.20, 406); loop test (IMC 1210.10)
Rough-in
Complete but visible, before wall or ceiling membranes
Hydronic (1208.1), refrigerant (1110), gas piping (406), grease duct light test (506.3.2.5)
Final
Installation complete
Boiler acceptance test (1011), hood performance test (507.6), leak check when gas is turned on (IFGC 406.6)
The codes do not tie each test to a named inspection, so the last column is normal practice. It follows from the rule that piping stays exposed until it is tested and from Section 108.2.3.
Who tests, and what a failure means (IMC 108.3, IFGC 112.3)
Tests are made by the permit holder and observed by the code official. New systems, and altered, extended, renovated or repaired parts of old ones, are tested to disclose leaks and defects. The permit holder furnishes the apparatus, material and labor (the IFGC adds instruments). Work that fails is corrected and resubmitted for inspection and testing (108.3.3, 112.3.3). Under 108.2.3 no work goes past an inspection point without approval, and any portion that does not comply is corrected and not covered until the code official authorizes it. The IFGC repeats the same words in 112.2.3, so the rule for both books is short: nothing is hidden until it is approved.
Boilers: the acceptance test (IMC 1011)
When a boiler or pressure vessel is assembled and installed, acceptance tests are run under the ASME Boiler and Pressure Vessel Code or the manufacturer's requirements, and the tests must be approved. Copies of the test documents and the manufacturer's data reports go to the code official (1011.1). The code text prints no test pressure of its own, so the number comes from ASME or the maker. It does control the gauge. An indicating gauge is connected directly to the boiler where the operator can see it throughout the test, it is calibrated and certified by the test operator, and its scale runs from not less than 1.5 to not more than 4 times the maximum test pressure (1011.2).
Refrigerant piping: strength, then vacuum (IMC 1110)
Field-erected refrigerant piping, other than ammonia, is pressure tested for strength and leak tested for tightness after installation and before operation, on both the high and low sides. Listed and labeled equipment such as compressors and condensers need not be tested (1110.1), and field pipe and joints stay exposed until the tests are done (1110.2). The medium is oxygen-free nitrogen, helium or argon, with carbon dioxide allowed for R-744 and water for R-718. Air, oxygen and combustible gases are never used, although a system with tubing not over 5/8 inch outside diameter may test with the refrigerant on its nameplate (1110.3). Two tests are required (1110.5). First, pressure is held not less than 60 minutes at not less than the lower of the design pressures or the relief setting, with no gas added after the start and no pressure loss. Second, a vacuum of 500 microns is pulled, the pump is isolated, and the pressure may not rise above 1,500 microns for at least 10 minutes. Parts inside a duct that carries air to occupied spaces are tested at 150 percent of the higher of the design pressure or the relief setting (1110.5.1). A system holding 55 pounds or more needs a signed certificate of test for the code official (1110.8). These tests are Section 1110, not Section 1108, which covers joints.
Hydronic piping and ground loops (IMC 1208, 1210.10)
Hydronic piping is tested hydrostatically at 1.5 times the maximum system design pressure, but not less than 100 psi, for not less than 15 minutes (1208.1). PEX may be tested with compressed gas only where every manufacturer's instructions for the installed pipe and fittings authorize it and no other rule prohibits it. Radiant piping to be embedded in concrete is tested before the pour and held at operating pressure during it (1209.2). A ground-source loop is tested with water at 100 psi for 15 minutes before the header trenches are backfilled, then flow and pressure loss are compared with the design. A difference of more than 10 percent means the cause must be found and corrected (1210.10).
Fuel gas piping (IFGC 404.20 and 406)
Gas piping is tested gastight before it is put in service or concealed (404.20). Section 406 requires a visual inspection and a pressure test before acceptance and initial operation (406.1). Repairs and additions get a test of the affected piping, but a minor repair needs only inspection and leak-detecting fluid (406.1.2), and a new branch to a new appliance needs only its own test (406.1.3). The medium is air, nitrogen, carbon dioxide or an inert gas, never oxygen (406.2), and the joints stay exposed (406.3). The pressure is not less than 1-1/2 times the maximum working pressure and never below 3 psig (406.4.1). The duration is 1/2 hour for each 500 cubic feet of pipe volume or fraction, 10 minutes for under 10 cubic feet or a single-family dwelling, and never more than 24 hours (406.4.2). The pressure is read with a manometer or a device that shows a loss, and a mechanical gauge's top of scale may not exceed five times the test pressure (406.4). Any drop is a leak unless it can readily be explained by something else (406.5). Lesson 13 covered the leak check when gas is turned on and purging.
Key numbers: tests and inspections
Three inspections: underground before backfill, rough-in before wall or ceiling membranes, final on completion (IMC 108.2, IFGC 112.2)
Permit holder tests and furnishes the equipment; the code official observes; failed work is corrected, resubmitted and stays uncovered until authorized (108.3, 108.2.3, 112.3)
Boiler test gauge scale: 1.5 to 4 times the test pressure (IMC 1011.2)
Refrigerant piping: nitrogen, helium or argon, never air; 60 minutes; vacuum to 500 microns, then no rise above 1,500 microns for 10 minutes; 150 percent for parts in air ducts; certificate at 55 pounds (1110)
Hydronic: 1.5 times design pressure, at least 100 psi, at least 15 minutes (1208.1). Ground loop: 100 psi, 15 minutes, flow within 10 percent of design (1210.10)
Fuel gas: 1.5 times working pressure and at least 3 psig; 1/2 hour per 500 cubic feet or fraction; gauge top of scale at most five times the test pressure (IFGC 406.4)
Grease duct light test: 100 watt lamp, before use or concealment (506.3.2.5). Hood performance test before final approval (507.6)
Worked example. A Group B clinic has a hydronic loop designed for 90 psi, so the test is 1.5 x 90 = 135 psi for at least 15 minutes, well over the 100 psi floor. Its rooftop unit has a refrigerant coil in the supply duct, with a 300 psi design pressure and a 350 psi relief setting. The coil is tested at 150 percent of the higher value, 1.5 x 350 = 525 psi. The boiler acceptance test runs at 120 psi, so the gauge scale must run from 1.5 x 120 = 180 psi to 4 x 120 = 480 psi, which a 0 to 200 or 0 to 300 psi gauge satisfies. The gas system operates at 2 psig, so 1.5 x 2 = 3 psig, exactly the floor. Its pipe holds 1,300 cubic feet, and 1,300 / 500 = 2.6, which counts as 3 periods, so the test lasts 3 x 1/2 hour = 1-1/2 hours. A mechanical gauge for that test may not top out above 5 x 3 = 15 psi.
Other tests: grease ducts and hoods (IMC 506.3.2.5, 507.6)
A grease duct gets a light test before any part is used or concealed. The permit holder passes a lamp of at least 100 watts through the whole duct so every welded or brazed joint shows it is liquid tight (506.3.2.5). A commercial cooking hood gets a performance test on completion and before final approval. It verifies the exhaust rate, the makeup air and, with the appliances at operating temperature, capture and containment (507.6).
Approval and utility connection (IMC 111 and 112, IFGC 108 and 110)
When the prescribed tests and inspections show that the work complies, the code official issues a notice of approval (IMC 111.1, IFGC 108.1). It can be revoked in writing if it was issued in error (IMC 111.2, IFGC 108.2). No one connects a utility, fuel or power source to a system that needed a permit until the code official authorizes it (IMC 112.1, IFGC 110.1), although a temporary connection for testing may be allowed (IMC 112.2, IFGC 110.2).
In the field
A GCHS inspector arrives to observe the gas piping test on a two-story community center rehab. The plumber has a 0 to 100 psi dial gauge on a system tested at 3 psig, the pipe is already behind new ceiling board, and gas has been turned on at the meter. Three things fail: the gauge top of scale may be no more than 15 psi (406.4), the piping had to be tested before it was concealed (404.20), and the connection had to wait for the code official (IFGC 110.1). Under 108.3.3 and 112.3.3 the work is corrected, resubmitted and retested, and the ceiling comes down where the joints are.
Course review
The review walks the six modules in order and repeats the numbers used most often. It teaches nothing new, and every value carries the hedges of its lesson. Where a lesson said to check the adopted code, do the same here.
Module 1: Administration and General Regulations (Lessons 1 and 2)
Every job starts with which code binds. Lesson 1's dated check found that Texas names no statewide mechanical code, that cities adopt their own, and that Houston has enforced the 2021 Uniform Mechanical Code with Houston amendments since early January 2024. This course teaches the IMC and IFGC as the model, so a Houston plan review is written against UMC numbers, not these. Lesson 2 gathered the physical rules for equipment: listing, location, clearances, access and condensate.
Key numbers: Lessons 1 and 2
180-day clocks: an application is abandoned after 180 days (106.3.2), a permit expires if work does not start or stops for 180 days (106.4.3), and one extension of up to 180 days costs half the fee (106.4.4)
Exempt: self-contained refrigeration with 10 pounds of refrigerant or less, or motors of 1 horsepower or less (106.2). Emergency replacement: permit application by the next working business day, inspection request within 48 hours (106.1, 108.2)
Working space at the control side 30 in by 30 in (306.1). Room door and passage 36 in by 80 in (306.2)
Attic: opening 20 by 30 in; passage 30 in high, 22 in wide and 20 ft long at most; solid floor 24 in wide (306.3). Roof access required above 16 ft (306.5)
Guards where equipment is within 10 ft of an edge more than 30 in high, 42 in tall (304.11). Equipment at grade: 3 in above grade on a slab, or hung 6 in above it (304.10)
Condensate slope 1/8 in per ft, line at least 3/4 in (307.2.1, 307.2.2). Reduced-clearance protection at least 1 in from the appliance (308.3)
Module 2: Ventilation and Exhaust (Lessons 3 to 5)
Lesson 3 built the outdoor air number, Lesson 4 sent air out of the building, and Lesson 5 treated a commercial kitchen exhaust system as one fire safety assembly. The outdoor air rates are Table 403.3.1.1 values and Houston's Uniform Mechanical Code has its own provisions, so the adopted code gives the actual rate.
Key numbers: Lessons 3 to 5
Vbz = Rp x Pz + Ra x Az, then Voz = Vbz / Ez. Office: Rp 5, Ra 0.06. Classroom age 9 plus: Rp 10, Ra 0.12. Ez is 1.0 for cool supply, 0.8 for warm ceiling supply with ceiling return, 0.7 for warm floor supply. The classroom example is 400.8 cfm, or 501 cfm with warm ceiling supply (403.3.1.1)
Natural ventilation opening 4 percent of floor area (402.2). Intakes 10 ft from lot lines and contaminant sources (401.4). Demand control never below Ra x Az (403.3.1.3)
Environmental air outlets: 3 ft from lot lines and openings, 10 ft from mechanical intakes. Hazardous exhaust: 30 ft from lot lines (501.3.1)
Dryer duct: no screens, 4 in nominal, 35 ft equivalent length, 3 ft from openings if the maker is silent (504)
Type I hood No. 18 gage steel; grease duct No. 16 gage; hood 18 in from combustibles; filters at 45 degrees or steeper; duct velocity at least 500 fpm (507.2, 506.3)
Exhaust by the heaviest appliance, per linear foot of wall canopy: 200, 300, 400 and 550 cfm for light, medium, heavy and extra-heavy duty (507.5)
Grease duct slope 1/4 in per ft, cleanouts 20 ft apart at most, outlet 40 in above the roof and 10 ft from buildings (506.3). Makeup air about equal to exhaust (508.1)
Module 3: Ducts and Combustion Air (Lessons 6 and 7)
Lesson 6 kept air, smoke and flame moving where the code wants them, and Lesson 7 fed appliances the air they need. Add up shared duct systems before you decide a detector is not required, and size combustion air from the total input of every appliance in the room.
Key numbers: Lessons 6 and 7
Duct smoke detector in a return system above 2,000 cfm, shared systems added together; a return riser serving two or more stories, or any part of a return system above 15,000 cfm, gets a detector at each story (606.2)
Plenum surfaces flame spread 25 or less and smoke-developed 50 or less (602.2). Flexible air connector 14 ft at most (603.6.2)
Fire damper 1-1/2 hr in assemblies under 3 hr and 3 hr in assemblies of 3 hr or more (Table 607.3.2.1). Release at about 50 degrees F above normal and not below 160 degrees F (607.3.3.1)
Smoke damper detector within 5 ft; damper access door 12 in square; label letters 1/2 in high (607.3.3.2, 607.4)
Indoor combustion air: 50 cu ft per 1,000 Btu/h; openings 1 sq in per 1,000 Btu/h and at least 100 sq in (IFGC 304.5)
Outdoor air, two openings: 1 sq in per 4,000 Btu/h direct or by vertical duct, 1 sq in per 2,000 Btu/h by horizontal duct. One opening: 1 sq in per 3,000 Btu/h. Within 12 in of top and bottom; least dimension 3 in (304.6)
Mechanical supply 0.35 cfm per 1,000 Btu/h (304.9). Garage ignition source at least 18 in above the floor (305.3)
Module 4: Chimneys, Vents, Appliances, and Boilers (Lessons 8 and 9)
Lesson 8 followed flue gas out through the vent, and Lesson 9 covered the boiler, its safety devices and its room. The terminal distances are checked against the appliance's listing and data plate, and boilers already under federal or state inspection may have another authority (Lesson 9).
Key numbers: Lessons 8 and 9
Gas vent: 2 ft above the roof passage and above anything within 10 ft, and 5 ft above the draft hood. The worked example gives 17 ft (IFGC 503.6)
Connector slope 1/4 in per ft; horizontal length 75 percent of vent height single-wall, 100 percent Type B (503.10)
Terminal 12 in above grade; direct-vent to an openable window 6, 9 or 12 in by input; nondirect-vent 4 ft below or beside a window and 1 ft above; prohibited under a porch open on one side only (Table 503.8)
Boiler: 18 in passage on all sides, top clearance 2 ft (3 ft with a manhole) (IMC 1004.3). Controls follow ASME CSD-1 under 12,500,000 Btu/h and NFPA 85 at or above it (1004.1)
Relief valve set at or below the nameplate pressure; discharge rigid, full size, no valves, tees or threads, ending 6 in or less above the floor at an air break (1006.4, 1006.6)
Low-water cutoff on steam and hot water boilers (1007). Table 1009.2: a 300 gal system needs a 25 gal diaphragm or 45 gal nonpressurized tank
Module 5: Refrigeration and Hydronics (Lessons 10 and 11)
Lesson 10 asked how much refrigerant is in one circuit compared with the room people occupy, and Lesson 11 moved water through the building. Houston follows the Uniform Mechanical Code, so check the adopted code before you write a correction on either topic.
Key numbers: Lessons 10 and 11
Table 1103.1 pounds per 1,000 cu ft: R-410A 26, R-134a 13, R-32 4.8, R-290 0.56. Institutional amounts cut 50 percent. Listed equipment of 6.6 lb or less needs no machinery room (1104.2)
Machinery room: normal exhaust the larger of 0.5 cfm per sq ft or 20 cfm per person; over 1,000 sq ft needs two exits, 150 ft maximum to an exit; relief discharge 15 ft above grade and 20 ft from openings (1105)
Refrigerant piping: exposed pipe 7 ft 3 in above the floor; labels every 20 ft with letters 1/2 in high (1109); soldered joints only for A1 refrigerants at 200 psi or less (1108.3.3)
Hydronic tanks: 400 gal needs 33 gal diaphragm or 60 gal nonpressurized; a closed tank above 30 psi is ASME certified; an open tank sits 4 ft above the highest element (1009)
Clearance 1 in where pipe exceeds 250 degrees F (1206.5). Transfer fluid flash point 50 degrees F above the maximum operating temperature (1207.1)
Tests: see this lesson (1110, 1208, 1210.10)
Module 6: Fuel Gas and Review (Lessons 12 to 14)
Lesson 12 built the gas piping, Lesson 13 sized and tested it, and this lesson gathered every test. The Btu-to-cfh conversion is not stated in the 2021 Chapter 4 text, so use the supplier's heating value, and check the adopted code for lengths between table rows.
Key numbers: Lessons 12 to 14
Steel pipe not lighter than Schedule 10; PVC and CPVC never for fuel gas (403). Yellow label every 5 ft on exposed pipe other than steel and CSST (401.5)
Shield plates No. 16 gage where pipe is within 1-1/2 in of a framing face, extending 4 in each side (404.7). Burial 12 in, or 8 in for outdoor light and grill lines; outdoor pipe 3-1/2 in above ground (404)
CSST without an arc-resistant jacket: 6 AWG copper bonding jumper, 75 ft at most (310.2)
Support spacing for steel pipe: 6 ft for 1/2 in, 8 ft for 3/4 or 1 in, 10 ft for 1-1/4 in and larger (Table 415.1). Appliance valve within 6 ft in the same room; connector 6 ft at most, one per appliance (409.5.1, 411.1.3.1)
Sizing: demand is every appliance at once (402.2). Table 402.4(1) is for natural gas under 2 psi with a 0.3 in w.c. drop. The longest length method uses one row for every section (402.4.1)
Purge outdoors above 2 psig or for Table 406.7.1.1 sizes; discharge 10 ft from ignition sources and openings, 25 ft from intakes; stop at 90 percent gas (406.7.1)
Tests and inspections: see this lesson. Nothing is covered until approved, and no utility is connected until authorized
The practice exam
The practice exam is the next step. It draws 60 questions, weighted by each topic area's share of the question bank, with a 120-minute time limit. It is a practice tool GCHS built for its own staff development. On an actual project, the locally adopted code, not this course, governs.
Practice questions
1. A hydronic loop in a Group R-2 building has a maximum system design pressure of 70 psi. Under IMC 1208.1, what is the least hydrostatic test pressure and duration?
70 psi for not less than 15 minutes
105 psi for not less than 15 minutes
100 psi for not less than 15 minutes
105 psi for not less than 60 minutes
Answer: b. One and one-half times 70 is 105 psi, which is over the 100 psi floor, so 105 psi governs. The test is held not less than 15 minutes (1208.1).
2. A Group B clinic's field-erected R-410A system has 7/8 inch tubing. Under IMC 1110.3, which test medium may be used for the strength test?
Dry compressed shop air
Oxygen
The refrigerant on the nameplate
Oxygen-free nitrogen
Answer: d. The medium is oxygen-free nitrogen, helium or argon. Air and oxygen are never allowed, and the nameplate refrigerant is allowed only for tubing not over 5/8 inch outside diameter.
3. After a field-erected refrigerant system in a Group B building is pulled down to 500 microns and the vacuum pump is isolated, what does IMC 1110.5 require?
The pressure stays at or below 1,500 microns for at least 10 minutes
The pressure stays at or below 1,500 microns for at least 60 minutes
The pressure stays at or below 5,000 microns for at least 10 minutes
The pressure stays at 500 microns for at least 1 minute
Answer: a. The vacuum test reaches 500 microns, isolates the pump, and allows no rise above 1,500 microns for not less than 10 minutes.
4. A new gas system in a Group A-3 community building has a maximum working pressure of 0.5 psig. Under IFGC 406.4.1, what is the least test pressure?
0.75 psig
1.5 psig
3 psig
7.5 psig
Answer: c. One and one-half times 0.5 is 0.75 psig, but the test pressure is never less than 3 psig, irrespective of design pressure.
5. The gas piping of a Group B campus building holds 620 cubic feet of pipe volume. Under IFGC 406.4.2, what is the least test duration?
30 minutes
1 hour
10 minutes
24 hours
Answer: b. The test lasts 1/2 hour for each 500 cubic feet or fraction. 620 divided by 500 is 1.24, which counts as 2 periods, so 2 x 1/2 hour is 1 hour.
6. A boiler acceptance test in a Group A-3 community center will be run at 150 psi. Under IMC 1011.2, which test gauge scale is acceptable?
0 to 300 psi
0 to 150 psi
0 to 100 psi
0 to 1,000 psi
Answer: a. The scale must run from not less than 1.5 times (225 psi) to not more than 4 times (600 psi) the maximum test pressure. A 0 to 300 psi gauge fits; 0 to 150 is too small and 0 to 1,000 is too large.
7. A GCHS estimator is pricing the mechanical rehab of a Group B office in Houston and plans to quote IMC section numbers. What is the right first step (Lesson 1)?
Go ahead, because every Texas city has adopted the IMC without local changes
Go ahead, because Houston still enforces the 2015 Uniform Mechanical Code edition
Confirm the adopted code first, because Houston enforces the 2021 UMC with local amendments
Go ahead, because Houston enforces the 2021 IMC with its own local amendments
Answer: c. Lesson 1 found that Texas cities adopt their own mechanical codes and that Houston moved to the 2021 UMC with amendments in early January 2024. IMC section numbers do not apply to a Houston plan review.
8. At the rough-in inspection of a Group R-2 building, a duct joint above a corridor ceiling fails. The drywall crew is booked for Monday. What do IMC 108.2.3 and 108.3.3 require (Lesson 1)?
Hang the board and recheck the joint at the final inspection with the rest
List the joint on the final inspection request and cover it in the meantime
Cover it once the contractor signs a statement that the joint was repaired and tight
Correct the joint, resubmit it, and keep it uncovered until the code official authorizes it
Answer: d. 108.2.3 keeps a portion that fails from being covered until the code official authorizes it, and 108.3.3 has the corrected work resubmitted for inspection and testing.
9. An attic furnace in a Group B clinic is reached by a passage 30 inches high and 22 inches wide, with solid flooring 24 inches wide, that measures 28 feet along the centerline. Under IMC 306.3 (Lesson 2), what fails?
The height, which must be at least 36 inches for any attic passage
The length, which may not exceed 20 feet for a passage this low
The width, which must be at least 30 inches along the whole passage
The flooring, which must be at least 36 inches wide along the passage
Answer: b. The attic passage is at least 30 inches high and 22 inches wide and no more than 20 feet long, with flooring at least 24 inches wide. The 50 foot allowance needs a passage 6 feet high, so this one fails on length.
10. A Group B office of 2,000 square feet has a table density of 5 people per 1,000 square feet, Rp 5 cfm per person and Ra 0.06 cfm per square foot. Warm air is supplied from the ceiling with a ceiling return (Ez 0.8). What is the zone outdoor airflow (Lesson 3)?
170 cfm
136 cfm
About 213 cfm
340 cfm
Answer: c. Vbz = 5 x 10 people + 0.06 x 2,000 = 50 + 120 = 170 cfm. Voz = Vbz / Ez = 170 / 0.8 = 212.5, about 213 cfm.
11. A toilet room exhaust fan on the roof of a Group B clinic discharges 6 feet from an outdoor air intake. Under IMC 501.3.1 (Lesson 4), how far must an environmental air exhaust outlet be from mechanical air intakes?
10 feet, so the outlet fails
3 feet, so the outlet passes
6 feet, so the outlet passes
30 feet, so the outlet fails
Answer: a. Environmental air exhaust needs 10 feet from mechanical air intakes, and 3 feet from property lines and operable openings. Thirty feet is the hazardous exhaust distance to property lines.
12. A 12-foot wall-mounted canopy hood serves a medium-duty griddle and a heavy-duty under-fired broiler in a Group A-2 restaurant. Using the heavier duty in IMC 507.5 (Lesson 5), what is the exhaust rate?
3,600 cfm, the medium-duty rate
7,200 cfm, the island heavy-duty rate
2,400 cfm, the light-duty rate
4,800 cfm, at 400 cfm per linear foot
Answer: d. The heaviest appliance governs: 400 cfm per linear foot for a wall-mounted canopy times 12 feet is 4,800 cfm. Lighter appliances under the hood do not lower it.
13. Three air handlers in a Group E school wing share one return plenum, at 1,000, 800 and 600 cfm. Under IMC 606.2.2 (Lesson 6), what applies?
The combined 2,400 cfm is over 2,000, so the shared return gets a duct detector
No detector is needed, because no single air handler is over 2,000 cfm
Detectors are needed only where the shared return exceeds 15,000 cfm
A detector is needed only in each story served by a return riser
Answer: a. Where several air handlers share a return and the combined design capacity is above 2,000 cfm, the shared return gets detectors. Each unit alone is under the limit, but the total is 2,400 cfm.
14. A Group B mechanical room holds natural-draft appliances totaling 240,000 Btu/h. Two permanent openings, top and bottom, open directly to the outdoors. Under IFGC 304.6.1 (Lesson 7), what net free area does each opening need?
120 square inches
80 square inches
60 square inches
240 square inches
Answer: c. Openings direct to outdoors, or through vertical ducts, need 1 square inch per 4,000 Btu/h. 240,000 / 4,000 is 60 square inches each. The 120 square inch answer is the horizontal duct rate.
15. A Type B gas vent has its draft hood outlet 9 feet above the floor. It passes through the roof 13 feet above the floor and is closer than 8 feet to a part of the building that rises to 16 feet, 6 feet away. Under IFGC 503.6 (Lesson 8), what is the lowest the vent may end above the floor?
14 feet
15 feet
16 feet
18 feet
Answer: d. The tests are 9 + 5 = 14 feet above the hood, 13 + 2 = 15 feet above the roof, and 16 + 2 = 18 feet above the taller part within 10 feet. The highest, 18 feet, controls.
16. Which relief valve discharge arrangement on a hot water boiler in a Group A-3 fellowship hall complies with IMC 1006.6 (Lesson 9)?
A rigid, full-size pipe ending in a threaded fitting so a hose can be attached to it
A rigid, full-size pipe with no valves, ending at an air break 4 inches above the floor
A rigid pipe tee'd into the floor sink drain line to keep the boiler room dry
A rigid, full-size pipe with a trap in the line to keep sewer odors out of the room
Answer: b. The discharge pipe is rigid and full size, with no traps, valves, tees or threaded ends, and it ends at an air break in the boiler room not more than 6 inches above the floor or receptor.
17. A 30 pound R-410A circuit serves a nursing home (institutional occupancy) whose smallest occupied space is 1,200 cubic feet. Table 1103.1 allows 26 pounds per 1,000 cubic feet, and institutional amounts are cut 50 percent (Lesson 10). What is the result?
The allowance is 15.6 pounds, so 30 pounds needs a machinery room or outdoors
The allowance is 31.2 pounds, so 30 pounds passes with room to spare
The allowance is 26 pounds, so 30 pounds is 4 pounds over the limit
No limit applies to an A1 refrigerant such as R-410A in an occupied area
Answer: a. 26 x 1.2 = 31.2 pounds, and halving it for an institutional occupancy gives 15.6 pounds (1104.2.1). Thirty pounds exceeds it, so the components go in a machinery room or outdoors.
18. A church hall's hydronic system holds 500 gallons, and the design data for tank sizing are not known. Under Table 1009.2 (Lesson 11), what is the least closed diaphragm expansion tank?
33 gallons
25 gallons
42 gallons
75 gallons
Answer: c. Table 1009.2 lists 42 gallons for a diaphragm tank at 500 gallons of system volume. The 75 gallon figure is the nonpressurized tank, and 33 gallons is the 400 gallon row.
19. A Group A-2 restaurant rehab uses CSST that has no arc-resistant jacket. Under IFGC 310.2 (Lesson 12), how is it bonded?
With a 10 AWG copper jumper, at most 75 feet long, to the nearest cold water pipe
With a 6 AWG copper jumper, at most 75 feet long, to the service grounding electrode system
Through the grounding conductor of the appliance it serves, with no jumper
No bonding is needed, because listed CSST is already electrically continuous
Answer: b. CSST without an arc-resistant jacket is bonded to the grounding electrode system with a jumper not smaller than 6 AWG copper and not longer than 75 feet, using listed connection devices.
20. A Group A-3 community building's gas system is sized with the longest length method from Table 402.4(1). The longest run is 50 feet, and a unit heater at the end is rated 200,000 Btu/h (200 cfh at about 1,000 Btu per cubic foot). The 50 foot row carries 55 cfh in 1/2 inch, 114 in 3/4 inch, 215 in 1 inch and 442 in 1-1/4 inch. What is the smallest pipe (Lesson 13)?
1/2 inch
3/4 inch
1-1/4 inch
1 inch
Answer: d. The smallest pipe whose capacity in the 50 foot row is at least 200 cfh is 1 inch, at 215 cfh. Three-quarter inch carries only 114.
Glossary
Acceptance test
The test run on a boiler or pressure vessel after it is assembled and installed, under ASME or the manufacturer's requirements, with the documents sent to the code official (IMC 1011.1).
Hydrostatic test
A leak and strength test that fills piping with water. Hydronic piping is tested at 1.5 times the maximum design pressure, at least 100 psi, for at least 15 minutes (IMC 1208.1).
Micron
A unit of very low pressure used to measure a vacuum. A refrigerant system is pulled to 500 microns and may not rise above 1,500 microns in 10 minutes (IMC 1110.5).
Manometer
A gauge that shows small pressure differences, used to read a pressure loss from leakage during a gas piping test (IFGC 406.4).
Light test
A grease duct leakage test that passes a lamp of at least 100 watts through the duct to show that welded and brazed joints are liquid tight (IMC 506.3.2.5).
Capture and containment test
A hood test run with the cooking appliances at operating temperature to show that the exhaust holds the plume, part of the performance test before final approval (IMC 507.6.1).
Rough-in inspection
The second required inspection, made after framing and fire protection are in place and the concealed work is complete, and before wall or ceiling membranes (IMC 108.2, IFGC 112.2).
Notice of approval
The approval a code official issues after the prescribed tests and inspections show that the work complies (IMC 111.1, IFGC 108.1).