Residential Building 100%

2021 IRC Chapters 9 & 10

Lesson 12: Roof Coverings, Reroofing, Insulation, and Chimneys

IRC R905, R908, R702.7, R1001, R1003 · 14 practice questions

0:00 / --:--

Reading

This lesson covers what keeps water out of a finished roof, what governs putting a new roof over an old one, and the masonry fireplace and chimney provisions a GCHS inspection often checks on the same visit as the roof above them. The numbers below come from 2021 IRC Sections R905, R908, R702.7, R1001, and R1003, checked against the code text. Always confirm the edition and any local amendment a given city has adopted.

Asphalt shingles: slope, underlayment, and fastening

Section R905.2.2 sets a 2:12 minimum roof slope for asphalt shingles. Between 2:12 and 4:12, the code requires doubled underlayment, a 19-inch starting strip followed by 36-inch-wide sheets overlapped 19 inches so coverage under the shingles is effectively two layers deep (Table R905.1.1(2)), because water drains slowly enough on a low slope to be driven back under a single layer's laps. At 4:12 and steeper, underlayment is applied shingle fashion with a minimum 2-inch lap, except that where wind design is required by Figure R301.2.1.1 the table calls for the two-layer method on any slope. Fastening matters as much as slope: Section R905.2.6 sets four nails as the minimum for a standard strip shingle, with manufacturer instructions often calling for six in high-wind areas, which govern where stricter. Two- and three-nail installations are a routine and preventable cause of wind-blown shingle claims.

Ice barriers, drip edge, and flashing

In areas with a history of ice forming along the eaves and backing water up under the covering, as designated in the local climatic design criteria table, Section R905.1.2 requires an ice barrier, either two layers of cemented underlayment or a self-adhering polymer-modified bitumen sheet, extending from the lowest roof edge to a point at least 24 inches inside the exterior wall line, and on roofs 8:12 or steeper also at least 36 inches up the slope from the eave edge. That reach matters because an ice dam can back water up well past the eave; a barrier stopping at the fascia does not protect the point where the dam forms. Whether it applies is a jurisdictional call in the adopted design criteria table, not contractor preference, and once required, the section lists no substitute for the membrane (detached accessory structures without conditioned floor area are excepted).

Drip edge at the eave must extend below the sheathing and back onto the deck, under Section R905.2.8.5 not less than 1/4 inch below the sheathing (so water clears the fascia) and not less than 2 inches back onto the deck, fastened at not more than 12 inches on center, with segments overlapped at least 2 inches. At a roof-to-wall intersection, step flashing, individual pieces woven in with each shingle course so each laps the one below and is covered by the next, sheds water onto the shingle beneath rather than behind it; sealant along that joint is maintenance, never a substitute. An open valley works the same way at larger scale: a lining goes down before the shingles (metal at least 24 inches wide, or two plies of mineral-surfaced roll roofing, per R905.2.8.2), with the shingles cut back from the centerline so the lining does the actual waterproofing. A skylight needs the same layered approach, a properly flashed curb or the manufacturer's integral kit, woven into the courses in sequence.

Key numbers: shingles, ice barrier, reroofing
  • Minimum slope for asphalt shingles: 2:12 (R905.2.2)
  • Double underlayment required: 2:12 up to 4:12 slope (R905.2.2)
  • Ice barrier extension: at least 24 in. inside the exterior wall line (R905.1.2)
  • Minimum fasteners per strip shingle: 4 (often 6 in high-wind areas) (R905.2.6)
  • Recover not allowed over 2 or more existing applications of any covering (R908.3.1.1)

Reroofing: recover versus tear-off

Section R908.3 makes removal of the existing coverings down to the deck the default, and R908.3.1.1 bars a recover where the existing roof has two or more applications of any type of covering. A roof already carrying two layers cannot receive a third; the accumulated weight, the lost nailing base, and the impossibility of inspecting or fastening into a deck buried under two old layers all require complete removal first. Even short of that limit, a recover is never permitted where the existing covering is water-soaked or deteriorated past serving as an adequate base, or consists of slate, or of clay, cement, or asbestos-cement tile, materials a new asphalt layer cannot fasten into or bed against. A tear-off is also the one point in a reroof when the deck is actually visible, so verifying sound, properly fastened sheathing, and replacing anything deteriorated, belongs at that stage; it cannot be checked once the new covering is on.

Insulation and vapor retarders

R-value measures a material's resistance to conductive heat flow at a given thickness; higher is better, and R-values of layers in series add together for an assembly total. Ceiling insulation levels come from the energy provisions by climate zone. Vapor retarders in frame walls are governed separately, by Section R702.7, which calls for the retarder on the interior side of the wall; for the ceiling, Section R806.2 asks for a Class I or II retarder on the warm-in-winter side only in Climate Zones 6, 7, and 8 when the reduced attic vent ratio is used. Moisture in conditioned indoor air moves toward a colder surface, so in a cold climate a vapor retarder belongs on the warm-in-winter side, the room side, below the insulation, not above it; a retarder on the attic side instead puts a condensing surface right where the moisture arrives. Vapor retarders are classified by permeance into Class I (0.1 perm or less), Class II (over 0.1 up to 1.0 perm), and Class III (over 1.0 up to 10 perms). Table R702.7(2) sets which classes are permitted on the interior side of a frame wall by climate zone, and no wall vapor retarder is required in Climate Zones 1, 2, and 3. R-value markers or a posted insulation certificate let installed thickness and R-value be verified after the fact, since blown insulation settles and is easy to under-install in hard-to-reach corners.

In the field

A homeowner who builds a plywood storage platform on ceiling joists, over existing blown insulation, creates two problems worth flagging on the same visit: the insulation under the platform is compressed and no longer performs at its rated R-value, and the joists were very likely sized for an uninhabitable attic with no storage load, not whatever gets stacked on the platform later. Both are common in older GCHS rehab houses where a previous owner added attic storage without consulting a span table.

Reroof decision: recover versus tear-off, and the ice barrier zone A flowchart-style diagram showing a roof cross-section with an ice barrier membrane extending from the eave to at least 24 inches inside the exterior wall line, and a decision box showing that a roof may receive at most two total layers of asphalt shingles, with tear-off required where the existing covering is water-soaked, deteriorated, or made of slate, tile, or asbestos-cement. Ice barrier 24 in. min. inside wall line (R905.1.2) Reroof decision (R908.3) 2 existing layers already? → tear-off required for a 3rd Water-soaked, deteriorated, or slate/tile/asbestos-cement? → tear-off, no exceptions
Two independent triggers for a full tear-off: reaching the two-layer limit, or an existing covering unsuited to a recover regardless of layer count.

Masonry fireplaces: hearth, clearances, and firebox

Section R1001.10 sets hearth extension dimensions by opening size: under 6 square feet, the extension reaches at least 16 inches in front and 8 inches beyond each side; at 6 square feet or larger, those figures grow to 20 and 12 inches, since a larger opening throws sparks and embers farther. The hearth itself, under the fire, must be at least 4 inches thick (R1001.9.1); the extension in front, protecting the floor rather than supporting the fire, can be thinner, at least 2 inches (R1001.9.2). Reversing those two figures is a frequent mistake. The firebox needs a minimum depth of 20 inches (R1001.6), keeping the fire back enough that heat and sparks stay contained and giving the smoke chamber above the geometry to draft correctly. Combustible forms used to build the hearth extension must be removed once the masonry cures; leaving them in place puts combustible material directly beneath the surface meant to protect the floor from embers.

Section R1001.11 sets clearance from the fireplace to combustible framing at not less than 2 inches from the front and sides and 4 inches from the back face. Trim and mantels are stricter: nothing combustible within 6 inches of the opening, and within 12 inches, combustible material may project no more than 1/8 inch for each inch of distance from the opening. A deep mantel mounted close above an opening is a common violation and a real fire risk, since sustained heat exposure can char wood over years before it ignites.

Masonry chimneys: walls, footing, clearance, and termination

A masonry chimney's walls must be solid masonry units, or hollow units grouted solid, at not less than 4 inches nominal thickness, plus an approved flue lining, clay tile, a listed liner, or other approved material, since the lining contains the hot gases and acidic condensate that would otherwise attack the mortar joints over time. Combustible framing must clear the exterior surface of the chimney by at least 2 inches where the chimney is inside the building, reduced to 1 inch where it sits entirely outside the exterior walls and sheds its heat outdoors rather than into surrounding framing. The footing must be at least 12 inches thick and extend at least 6 inches beyond the face of the foundation or support wall on every side (R1003.2), since a tall, narrow chimney has a genuine overturning tendency that a wider, thicker footing resists. Where a chimney's width, measured perpendicular to the roof slope, exceeds 30 inches, a cricket or saddle is required on the ridge side (R903.2.2), since the flat catchment area behind a wide chimney otherwise collects enough water, snow, and debris to defeat ordinary flashing.

Termination height follows the 3-2-10 rule: the chimney must extend at least 3 feet above the highest point where it passes through the roof, and at least 2 feet higher than any part of the building, including the ridge, within 10 feet horizontally, whichever produces the taller result. Where a spark arrestor is installed, its mesh openings must be sized between 3/8 inch and 1/2 inch: smaller openings clog with creosote and restrict the flue, while larger openings let burning embers through. A factory-built, listed metal fireplace and chimney is a different animal from masonry entirely; it must be installed exactly to the terms of its listing and the manufacturer's instructions, and mixing masonry clearance rules with a listed assembly invalidates both.

Worked example: is this chimney's termination height compliant?

A masonry chimney passes through a roof plane 6 feet from the ridge, the tallest part of the building within 10 feet. Under the 3-2-10 rule the chimney needs at least 3 feet above its own roof penetration point, and separately, because the ridge sits within that 10-foot radius, at least 2 feet of clearance above the ridge itself. If the ridge is 4 feet higher than the penetration point, a chimney only 3 feet above that point would sit 1 foot short of the 2-foot ridge clearance, so the ridge clearance governs here, not the flat 3-foot figure: the chimney needs at least 6 feet above its penetration point (4 feet to reach the ridge height, plus 2 more) to satisfy both parts of the rule at once.

Practice questions

1. Under Section R905.2.2, asphalt shingles may be installed on a roof slope no lower than:

  1. 1:12
  2. 2:12
  3. 3:12
  4. 4:12

2. In an area with a history of ice damming, Section R905.1.2 requires the ice barrier to extend from the eave edge to a point at least:

  1. 12 inches inside the exterior wall line
  2. To the ridge
  3. 24 inches up the roof slope, measured from the eave edge
  4. 24 inches inside the exterior wall line

3. An existing roof already carries two layers of asphalt shingles, and a third is proposed. Under Sections R908.3 and R908.3.1.1, the inspector should require:

  1. Approval, since three layers are allowed with proper fastening
  2. Removal of only the top layer
  3. Nothing; reroofing over existing shingles is always exempt
  4. Complete removal of the existing roof coverings down to the deck

4. A recover over an existing roof covering is not permitted, regardless of how many layers already exist, when the existing covering:

  1. Is water-soaked or too deteriorated to serve as a base, or is slate, clay, cement, or asbestos-cement tile
  2. Is more than 5 years old, since covering age alone limits any recover to a single layer
  3. Was installed by a different contractor, since a recover must be done by the installer of the original roof
  4. Has a Class B fire rating, since only Class A coverings may be recovered

5. The minimum number of fasteners for a standard strip asphalt shingle under Section R905.2.6 is:

  1. 2
  2. 4
  3. 3
  4. 8

6. Which statement correctly describes R-value?

  1. A lower R-value indicates better insulating performance, because less material resists the flow
  2. R-value measures moisture resistance, not heat flow, so it says nothing about conductive loss
  3. R-value measures resistance to heat flow; higher is better, and layers in series add
  4. R-value applies only to fiberglass batt insulation

7. Under Section R702.7, where a vapor retarder is used on a cold-climate exterior frame wall, it belongs:

  1. On the exterior side, outside the wall sheathing
  2. On both sides of the insulation
  3. On the interior side of the wall, the warm-in-winter side
  4. Anywhere, since placement does not affect performance

8. The hearth extension for a masonry fireplace with an opening of 6 square feet or larger must extend, at minimum:

  1. 20 inches in front and 12 inches beyond each side
  2. 16 inches in front and 8 inches beyond each side
  3. 12 inches in front and 6 inches beyond each side
  4. 24 inches in front and 16 inches beyond each side

9. Minimum thickness for a masonry fireplace hearth and its hearth extension are, respectively:

  1. 2 inches and 4 inches
  2. 4 inches and 2 inches
  3. 4 inches and 4 inches
  4. 2 inches and 2 inches

10. The walls of a masonry chimney must be constructed of solid masonry units (or hollow units grouted solid) not less than:

  1. 2 inches nominal thickness
  2. 8 inches nominal thickness
  3. 3 inches nominal thickness
  4. 4 inches nominal thickness

11. A masonry chimney footing must be at least 12 inches thick and extend beyond the face of the foundation or support wall on all sides by at least:

  1. 2 inches
  2. 4 inches
  3. 6 inches
  4. 12 inches

12. A chimney passes through the roof 4 feet from the ridge, and the ridge is the tallest part of the building within 10 feet. If the ridge sits 5 feet higher than the roof penetration point, the chimney's termination must reach at least:

  1. 3 feet above the penetration point, since the 3-foot minimum always governs over the ridge clearance
  2. 7 feet above the penetration point, since it must clear the ridge (5 ft) by 2 more feet
  3. 5 feet above the penetration point, level with the ridge
  4. 2 feet above the penetration point

13. Where a spark arrestor is installed on a chimney, its mesh openings must be sized:

  1. Not less than 3/8 inch and not more than 1/2 inch
  2. Not less than 1/8 inch and not more than 1/4 inch
  3. Exactly 1 inch
  4. Any size, as long as the mesh is metal

14. A chimney passing through a roof measures 36 inches wide, perpendicular to the roof slope. What does the code require on the ridge side of that chimney?

  1. Nothing beyond standard step flashing
  2. A second layer of ice barrier only
  3. A cricket or saddle, since the chimney's width exceeds 30 inches
  4. A skylight-style curb

Glossary

Ice barrier
A self-adhering or doubled underlayment membrane required in ice-dam-prone jurisdictions, extending at least 24 inches inside the exterior wall line.
Recover
Installing a new roof covering over an existing one without removing it; permitted only over a sound, dry base and never where the roof already has two or more applications of any covering.
Vapor retarder
A material limiting moisture movement through a wall or ceiling assembly; in a cold climate it belongs on the warm-in-winter (room) side.
Hearth extension
The noncombustible surface in front of and beside a fireplace opening, sized to the opening's area, protecting the floor from sparks and embers.
Cricket (saddle)
A small secondary roof built on the ridge side of a wide chimney or other penetration to divert water and debris around it.
3-2-10 rule
The chimney termination rule: at least 3 feet above the roof penetration point, and at least 2 feet higher than any part of the building within 10 feet.