Day 10: Develop and Manage Scope

about 4.1% of the exam content - about 90 minutes - 14 practice questions

0:00 / --:--

Reading

Scope is the single biggest source of project failure in our line of work. A homeowner thought the roof was included. A grant officer thought the ramp came with a handrail on both sides. A crew lead "just fixed" a rotted sill plate nobody budgeted for. Every one of those is a scope problem, and every one of them is preventable with the practices in this task: collect requirements properly, define scope explicitly, decompose it into work you can assign and estimate, trace it, and validate it with the customer before you call it done.

Work breakdown structure tree for a bathroom accessibility retrofit A three-level tree. The top box is the project, bathroom accessibility retrofit. It branches into three deliverables: demolition and prep, ramp and doorway, and bathroom fixtures. Each deliverable branches into two work packages at the bottom level: demolition and prep splits into remove old fixtures and protect work area; ramp and doorway splits into frame ramp structure and widen doorway; bathroom fixtures splits into install grab bars and install zero-threshold shower. A note by the project box states the 100 percent rule: child elements roll up to exactly their parent, no more and no less. A note under the work packages states the 8/80 heuristic: each work package is roughly 8 to 80 hours of work. Bathroom accessibility retrofit (project) Demolition & prep Ramp & doorway Bathroom fixtures Remove old fixtures Protect work area Frame ramp structure Widen doorway Install grab bars Install shower (zero-threshold) 100% rule: each row of child boxes rolls up to exactly its parent, nothing more, nothing less 8/80 heuristic: each work package is roughly 8 to 80 hours of estimable, assignable work
A work breakdown structure decomposes the project by deliverable, not by who does the work or by chronological steps. The 100% rule keeps every child summing exactly to its parent; the 8/80 heuristic keeps the bottom-level work packages small enough to estimate and assign reliably.

Product scope vs project scope

Two different things, and PMI tests the difference. Product scope is the features and functions of the thing being delivered: a 36-inch doorway, a zero-threshold shower, a 1:12 ramp slope. Project scope is the work required to deliver it: permitting, demolition, inspection, homeowner coordination, closeout documentation. Product scope is measured against requirements; project scope is measured against the plan. Project scope usually includes work that is not part of the product.

Collecting requirements

Requirements come from stakeholders, and getting them wrong early is the most expensive mistake available. Techniques you should recognize:

  • Interviews: one on one, best for sensitive or detailed information (a homeowner's actual mobility limitations)
  • Focus groups: moderated discussion among a stakeholder class
  • Facilitated workshops: cross-functional sessions that resolve differences fast; JAD sessions and QFD are examples
  • Questionnaires and surveys: many respondents, geographically dispersed
  • Observation (job shadowing): watching real use; catches what people cannot articulate, such as how someone actually transfers from a wheelchair
  • Prototypes and mock-ups: a taped-out bathroom floor plan, a cardboard grab bar mock-up; produce feedback far better than a drawing
  • Benchmarking, document analysis, brainstorming, nominal group technique, affinity diagrams, multicriteria decision analysis

Requirements get recorded in requirements documentation and classified: business requirements, stakeholder requirements, solution requirements (functional and non-functional), transition and readiness requirements, project requirements, and quality requirements. A good requirement is unambiguous, testable, traceable, consistent, and accepted by stakeholders. "The bathroom should be accessible" fails that test. "Clear floor space of at least 30 by 48 inches at the lavatory, per TAS" passes it.

Key points
  • The requirements traceability matrix links each requirement forward to design, build, test, and acceptance, and backward to the business need it satisfies
  • Traceability is how you prove a requirement was delivered, and how you spot requirements nobody asked for
  • Unresolved competing requirements are decided by prioritization with stakeholders, not by the PM picking a favorite

Defining scope and the scope baseline

The project scope statement describes the deliverables, acceptance criteria, exclusions, assumptions, and constraints. Exclusions matter as much as inclusions. Writing "roof replacement is excluded; roof is assumed watertight at start" prevents a fight three weeks in.

The work breakdown structure (WBS) decomposes the total scope into a hierarchy of deliverables. The lowest level is a work package: small enough to estimate and assign reliably. Two rules to remember. The 100% rule: the WBS contains all the work of the project and nothing more; child elements roll up to exactly their parent. The 8/80 heuristic: work packages typically land between 8 and 80 hours, though this is guidance, not law. A WBS is decomposed by deliverable, not by who does the work and not by chronological steps; an organization chart is not a WBS.

The WBS dictionary gives each element its detail: description, responsible party, acceptance criteria, resources, cost estimate. Together, scope statement + WBS + WBS dictionary = the scope baseline, a component of the project management plan changed only through change control.

ComponentWhat it containsIn the scope baseline?
Project scope statementDeliverables, acceptance criteria, exclusions, assumptions, constraintsYes
WBSHierarchical decomposition of scope down to work packagesYes
WBS dictionaryDetail for each WBS element: owner, criteria, estimatesYes
Requirements documentationAll collected and classified requirementsNo, project document
Traceability matrixLinks requirements to deliverables and testsNo, project document
Product backlogOrdered list of features and stories (adaptive)No, adaptive artifact

Scope in adaptive work: backlog, stories, DoR and DoD

Adaptive projects hold scope in a product backlog owned and ordered by the product owner. Items are usually written as user stories ("As a case manager, I want to flag a home as storm-damaged so that repair crews can be dispatched first") with acceptance criteria that say specifically what must be true for that story to be accepted.

Backlog refinement (grooming) is the ongoing activity where the team and product owner clarify, split, estimate, and reorder items, an ongoing activity that takes a steady share of team capacity. Items are estimated relatively, in story points, often using planning poker; relative sizing is faster and more reliable than absolute hour estimates for uncertain work.

Two definitions get confused constantly and are prime exam material:

  • Definition of ready (DoR): the team's agreed checklist for whether a backlog item is well enough understood to be pulled into an iteration. It is a common team working agreement, not a Scrum Guide element.
  • Definition of done (DoD): the team's standard, applying to every item, for what complete means: coded, tested, documented, integrated, inspected.
  • Acceptance criteria: specific to one item, describing what that particular story or deliverable must do to be accepted.

So: DoD is universal and team-owned; acceptance criteria are item-specific and typically product-owner or customer-owned. A story can meet its acceptance criteria and still not be done if the team's DoD requires documentation nobody wrote.

Scope creep vs gold plating

Scope creep is uncontrolled expansion driven by outside requests that were never approved; the homeowner keeps adding "one more thing" and nobody logs it. Gold plating is the team adding unrequested extras on its own initiative; the crew installs a nicer faucet than specified because they had one on the truck. Both are uncontrolled scope change. The distinction on the exam is the source: creep comes from outside the team, gold plating comes from inside. Both are prevented the same way: a clear baseline plus disciplined change control, and both are wrong even when well intentioned.

Prioritization and MoSCoW

When there is more want than budget, prioritize explicitly with stakeholders rather than deciding silently. MoSCoW is a common technique.

CategoryMeaningGCHS accessibility retrofit example
Must haveNon-negotiable; without it the delivery failsCode-compliant ramp slope and landing
Should haveImportant but not vital; painful to omitSecond handrail; lever door hardware
Could haveDesirable if time and money allowCovered porch roof over the landing
Won't have (this time)Explicitly out of scope for this releaseKitchen counter lowering, deferred to a later grant

Other prioritization tools worth knowing: Kano analysis (basic, performance, delighter features), weighted shortest job first (WSJF), paired comparison, and simple 100-point allocation. The point of all of them is the same: make the trade-off visible and shared.

Validating and controlling scope

Two processes people mix up. Validate scope is the customer or sponsor formally accepting deliverables; its output is accepted deliverables and, where rejected, change requests. Control quality is the internal check that the deliverable meets requirements; its output is verified deliverables. Quality control normally comes first: you verify internally, then take it to the customer for acceptance. Handing an uninspected deliverable to a homeowner for sign-off is the sequence error PMI likes to test.

Control scope is monitoring status and managing changes to the baseline, using variance analysis to see where actual scope diverges from approved scope. In adaptive work the equivalent is the iteration review or demo, where the product owner accepts or rejects completed items and unfinished work returns to the backlog rather than being carried as partial credit.

Common trap

A crew finds unforeseen termite damage behind a wall during an accessibility retrofit. The tempting answers are "fix it, it is the right thing to do" or "stop the whole job." The PMI answer is: it is new work not in the baseline, so document the finding, assess impact on scope, cost, schedule and safety, and submit a change request. If it creates an immediate safety hazard you make the area safe first (protecting people never waits for a CCB), but the repair itself still goes through change control.

Practice Questions

1. Which of the following BEST describes the difference between product scope and project scope?

  1. Product scope applies only to adaptive projects, and project scope applies only to predictive projects
  2. Product scope is the work performed; project scope is the features delivered
  3. Product scope is the features and functions; project scope is the work to deliver them
  4. They are the same thing described from different perspectives

2. The scope baseline consists of which three items?

  1. Charter, scope statement, and requirements documentation
  2. WBS, schedule, and cost estimate
  3. Requirements documentation, WBS, and traceability matrix
  4. Project scope statement, WBS, and WBS dictionary

3. A crew installs a higher-grade faucet than specified because they believe the homeowner will appreciate it. This is an example of:

  1. Gold plating
  2. Value engineering
  3. Progressive elaboration
  4. Scope creep

4. A homeowner repeatedly asks the crew for small additions and the crew accommodates them without documentation. This is:

  1. Acceptable customer service
  2. Progressive elaboration
  3. Gold plating
  4. Scope creep

5. The 100% rule of the WBS states that:

  1. The WBS includes all project work and nothing else, with children summing to their parent
  2. Each work package must be 100 hours or less
  3. The WBS must be 100% complete before execution begins
  4. 100% of the team members and sponsors must formally sign off on the WBS before it is baselined

6. Which of the following is NOT a valid way to decompose a WBS?

  1. By major deliverable
  2. By project phase
  3. By subproject
  4. By the organizational chart of who reports to whom

7. Two funders request conflicting requirements for a rehab program's reporting format. What should the project manager do?

  1. Ignore both requests and use the standard GCHS reporting format for every funder and program
  2. Ask the board to decide immediately without stakeholder input
  3. Pick whichever funder's requirement seems more important
  4. Facilitate prioritization among the stakeholders rather than deciding alone

8. A project manager wants to see how a wheelchair user actually transfers onto a shower bench, catching details the homeowner could not describe in words. Which requirements collection technique is this?

  1. Interview
  2. Focus group
  3. Observation (job shadowing)
  4. Questionnaire

9. A user story meets its acceptance criteria, but the team's definition of done requires documentation that was never written. What is the status of the story?

  1. Not done, since the definition of done applies to every item
  2. Done, since documentation is optional
  3. The story should be removed from the backlog entirely
  4. Done, since every acceptance criterion written for the story was met in testing

10. A crew completes a ramp and wants to schedule the homeowner's formal acceptance walkthrough. What should happen FIRST?

  1. Ask the homeowner to inspect it herself for defects and report them before the formal walkthrough
  2. Schedule the homeowner walkthrough immediately
  3. Perform internal quality control checks before taking it to the homeowner
  4. Skip inspection since the crew is experienced

11. A GCHS accessibility retrofit has more homeowner requests than budget allows. Using MoSCoW, a covered porch roof over the ramp landing, desirable but not essential, would be classified as:

  1. Should have
  2. Could have
  3. Won't have
  4. Must have

12. During demolition, a crew discovers active termite damage that does not create an immediate safety hazard. What should the project manager do?

  1. Stop the entire project until a full structural inspection of the house is complete
  2. Document the finding, assess its impact, and submit a change request
  3. Repair it immediately since it is clearly necessary
  4. Ignore it since it was not in the original scope

13. A caseworker adds an unrequested feature to the intake software because she believes users will like it, without telling the product owner. This is:

  1. A validated requirement
  2. Gold plating
  3. Scope creep
  4. Value engineering

14. Which document links each requirement forward to design, build, test, and acceptance, and backward to the business need it satisfies?

  1. Requirements traceability matrix
  2. Project scope statement
  3. Product backlog
  4. WBS dictionary

Glossary

Product scope vs project scope
Product scope is the features and functions of the deliverable; project scope is all the work required to produce it.
Requirements traceability matrix
A document linking each requirement forward to design, build, test, and acceptance, and backward to the business need it satisfies.
Work breakdown structure (WBS)
A hierarchical decomposition of total project scope into deliverables and work packages, organized by deliverable, not by team or chronology.
Work package
The lowest level of the WBS, small enough to estimate and assign reliably; typically 8 to 80 hours under the 8/80 heuristic.
Scope baseline
The project scope statement, WBS, and WBS dictionary together, approved and changed only through change control.
Definition of ready / definition of done
DoR is the team's checklist for whether a backlog item is understood enough to start; DoD is the team's universal standard for what complete means for every item.
Scope creep vs gold plating
Scope creep is uncontrolled expansion from outside requests; gold plating is unrequested extras the team adds on its own initiative.
MoSCoW
A prioritization technique sorting items into Must have, Should have, Could have, and Won't have (this time).