Day 14: Plan and Manage Finance

About 4.1% of the exam content - about 90 minutes - 14 practice questions

0:00 / --:--

Reading

Every GCHS project is somebody's money: a HUD pass-through, a foundation grant, a county bond allocation, a donor's check. Planning and managing finance means answering three questions honestly and repeatedly: What will this cost? How much money do we actually have, and when? Are we still on track? The PMP exam tests the vocabulary and the discipline around those questions, in both predictive (fully-planned) and adaptive (iterative) settings.

Reading planned value, earned value, and actual cost at a status date A cumulative cost S-curve chart. Three separate lines are plotted: planned value (PV) rises from the project start all the way to the full budget of 1,000,000 dollars at completion. Earned value (EV) and actual cost (AC) are drawn only up to a dashed vertical status date line partway through the project, since they only exist for work done so far. At the status date, PV has reached 500,000 dollars, AC has reached 480,000 dollars, and EV has reached 440,000 dollars, so EV sits below both PV and AC. A bracket between the PV and EV lines is labeled schedule variance, -60,000 dollars, behind schedule. A bracket between the EV and AC lines is labeled cost variance, -40,000 dollars, over budget. A legend identifies the three line colors. A closing note explains that a negative schedule variance and a negative cost variance are two different problems needing two different responses. Cumulative cost Time Status date PV $500,000 AC $480,000 EV $440,000 SV = -60,000: behind schedule CV = -40,000: over budget PV: planned value AC: actual cost EV: earned value Here EV trails PV (behind schedule) while AC exceeds EV (over budget): two separate problems, read from the same status date, each needing its own response.
At any status date, comparing PV, EV, and AC on the cost S-curve separates schedule performance from cost performance.

Estimating: four techniques, four levels of confidence

An estimate is a considered prediction, not a promise. PMI expects you to know which technique fits which moment in the project.

TechniqueHow it worksWhen to use itAccuracy
Analogous (top-down)Use the actual cost of a similar past project and adjust. “The Rockport ramp job ran 14,000 dollars; this one is bigger, call it 18,000.”Very early, little detail, need a number todayLowest: fast and cheap
ParametricMultiply a unit rate by a quantity. 1,850 sq ft of rehab at 92 dollars per sq ft.When you have reliable historical unit rates and a scalable scopeModerate to high, if the rate data is good
Bottom-upEstimate each work package or activity, then roll the numbers up.When the WBS is decomposed and you need a defensible number Highest: also slowest and most expensive
Three-point (PERT)Blend optimistic, most likely, and pessimistic values to account for uncertainty.When an item is risky and a single number would be misleadingImproves any of the above by exposing range

The beta (PERT) formula is E = (O + 4M + P) / 6. The simpler triangular formula is E = (O + M + P) / 3. PERT weights the most likely value four times as heavily, so it usually lands closer to M. The standard deviation of a PERT estimate is (P − O) / 6, and the variance is that number squared. Roughly 68% of outcomes fall within one standard deviation of the mean, 95% within two, 99.7% within three.

Estimates also carry an implied accuracy range. A rough order of magnitude (ROM) estimate is commonly stated as −25% to +75%; a definitive estimate as −5% to +10%. Telling a board member “about 200,000 dollars” without saying which of those two you mean is how nonprofits get into trouble.

Key points
  • Analogous = fast, cheap, least accurate; bottom-up = slow, expensive, most accurate
  • PERT: E = (O + 4M + P) / 6  |  SD = (P − O) / 6  |  Variance = SD squared
  • Triangular: E = (O + M + P) / 3, with no extra weight on the most likely value
  • Estimates get more accurate as the project progresses: this is progressive elaboration, and re-estimating is normal, not a failure

Reserves: contingency versus management

Two very different pots of money, and the exam loves the distinction.

Contingency reserveManagement reserve
CoversKnown risks: things on your risk register (“we may find asbestos tile in pre-1980 units”)Unknown risks: the events nobody identified
Sized byRisk analysis, often expected monetary valueSet by organizational policy and held outside the baseline
Controlled byUsually the project managerManagement / the sponsor
Part of the cost baseline?YesNo
To use itPM draws on it directly and reports the drawdownRequires management approval, and adding it to the baseline requires an approved change request

So: Cost baseline = sum of the work package estimates + contingency reserve. Total project budget = cost baseline + management reserve. Performance is measured against the baseline, never against the total budget. If a GCHS rehab has 420,000 dollars of estimated work, 38,000 of contingency, and 25,000 of management reserve, the cost baseline is 458,000 and the project budget is 483,000.

The S-curve, funding limits, and cash flow

Plot cumulative planned spend over time and you get an S-curve: slow at the start while you mobilize and permit, steep through the middle when crews and materials hit, flattening at closeout. The S-curve is the time-phased cost baseline, and it is what you compare actual spending against.

Funding limit reconciliation is the step where you compare that spend curve to the money actually available in each period. Grants rarely arrive as one lump sum; a HUD draw may be quarterly, a foundation may release the second tranche only after an interim report. If your S-curve wants 180,000 dollars in Q2 and the funding calendar only releases 120,000, you do not simply overspend: you reschedule work to flatten the curve, or you request a change to the funding schedule. The usual remedy is to move activities, which is why funding limit reconciliation often changes the schedule too.

Watch for this on the exam

When an item says spending is outrunning available funding, the tested answer is rarely “ask for more money” and never “keep going and sort it out later.” It is reconcile the funding limit: re-time the work so the spend curve fits the money, then take any remaining gap through change control.

Business-case measures: is this project worth doing?

Finance is not only about spending; it is about justifying the spend. These four measures show up in selection questions, usually as “which project should the organization choose?”

  • Net present value (NPV): the value of all future cash flows discounted back to today's dollars, minus the investment. Higher NPV is better; a positive NPV is worth doing. When a question gives you several NPVs, pick the biggest, and ignore the project durations unless the question asks something else.
  • Internal rate of return (IRR): the discount rate at which NPV equals zero. Think of it as the project's effective annual yield. Higher is better.
  • Benefit–cost ratio (BCR): benefits divided by costs. Above 1.0 means benefits exceed costs. Higher is better. Careful: a cost–benefit ratio is the inverse, where lower is better; read the question.
  • Payback period: how long until cumulative benefits repay the investment. Shorter is better. Its weakness is that it ignores everything that happens after payback and ignores the time value of money.

A related trap: sunk costs. Money already spent is irrelevant to the decision about whether to continue. If GCHS has burned 90,000 dollars on a site that turns out to be in a re-mapped floodway, the only question is whether the remaining spend is justified by the remaining benefit. Opportunity cost is the value of the best option you gave up by choosing this one.

Lifecycle cost and sustainability

Cost over the whole asset life matters, not just the cost of the project. Lifecycle costing adds operating, maintenance, and disposal costs to the acquisition cost. For GCHS this is the real argument for spending more up front: a high-SEER heat pump and closed-cell foam cost more at install, but a fixed-income homeowner on the coast lives with the utility bill for twenty years. Bringing energy modeling and end-of-life material disposal into the estimate is ESG-aware cost planning, and it is a legitimate justification for a higher first cost.

AI-assisted forecasting is a growing practice: models trained on your historical actuals can flag that a work package is trending over before a human notices. Treat the output as an input to your judgment: you still validate the data, still investigate root cause, and still own the forecast you give the sponsor.

Managing budget the adaptive way

Agile projects still cost money; they just commit it differently. Instead of locking a full scope and deriving a budget, teams often use incremental funding: fund the next few iterations, inspect the value delivered, then decide whether to fund more. Because a stable team costs a predictable amount per iteration (a run rate), cost forecasting becomes a question of how many iterations remain. Scope, not budget, is the variable that flexes. The finance discipline is unchanged: you still track actuals, still keep reserves, and still report honestly, but the decision point moves to the end of each increment, which is exactly what makes an adaptive approach attractive when funding itself is uncertain.

Do not do this

Do not quietly move money between work packages to hide an overrun, and do not spend management reserve on your own authority. Both are integrity failures before they are process failures, and on a federally funded rehab they are audit findings. Report the variance, analyze the cause, and route the remedy through change control.

Practice Questions

1. An activity is estimated at 6 days optimistic, 10 days most likely, and 20 days pessimistic. Using the beta (PERT) three-point formula, what is the expected duration?

  1. 12 days
  2. 10 days
  3. 12.5 days
  4. 11 days

2. A GCHS project has work package estimates totaling 420,000 dollars, a contingency reserve of 38,000 dollars, and a management reserve of 25,000 dollars. What is the cost baseline?

  1. 420,000 dollars
  2. 445,000 dollars
  3. 458,000 dollars
  4. 483,000 dollars

3. Using the same figures (420,000 dollars of work packages, 38,000 dollars contingency, 25,000 dollars management reserve), what is the total project budget?

  1. 420,000 dollars
  2. 458,000 dollars
  3. 483,000 dollars
  4. 445,000 dollars

4. A rehab scope is 1,850 square feet and the organization's validated historical unit rate is 92 dollars per square foot. What is the parametric estimate, and what technique is this?

  1. 170,200 dollars, parametric estimating
  2. 170,200 dollars, analogous estimating
  3. 185,000 dollars, parametric estimating
  4. 166,500 dollars, bottom-up estimating

5. Which statement about contingency reserve versus management reserve is correct?

  1. Management reserve covers known risks and the project manager spends it freely
  2. Contingency reserve is outside the cost baseline and is released by the sponsor
  3. Both are inside the cost baseline and both are controlled by the project manager
  4. Contingency reserve covers known risks and is inside the cost baseline; management reserve covers unknown risks and is outside it

6. Two projects are under consideration. Project A has an NPV of 240,000 dollars over five years; Project B has an NPV of 310,000 dollars over seven years. Which should be selected on this information alone?

  1. Neither: NPV cannot be compared across different durations
  2. Project A, because it pays back sooner
  3. Project B, because its NPV is higher
  4. Project A, because a shorter project carries less risk

7. A GCHS rehab program has PV = 500,000 dollars, EV = 440,000 dollars, and AC = 480,000 dollars at the status date. What is the cost performance index (CPI), and what does it indicate?

  1. CPI = 1.09; the project is under budget
  2. CPI = 0.88; the project is behind schedule
  3. CPI = 1.08; the project is under budget, earning 1.08 dollars of value per dollar spent
  4. CPI = 0.92; over budget, earning 0.92 dollars of value per dollar spent

8. Using the same figures: PV 500,000 dollars, EV 440,000 dollars, AC 480,000 dollars, what is the schedule performance index (SPI), and what does it indicate?

  1. SPI = 0.88; the project is behind schedule
  2. SPI = 0.92; the project is over budget
  3. SPI = 1.14; the project is under budget
  4. SPI = 1.09; the project is ahead of schedule

9. The program's BAC is 1,000,000 dollars and CPI is 0.92 (440,000 / 480,000). If cost performance continues at this rate, what is the estimate at completion (EAC)?

  1. 920,000 dollars
  2. 960,000 dollars
  3. 1,040,000 dollars
  4. 1,090,909 dollars

10. Continuing the same scenario (EV 440,000; AC 480,000; BAC 1,000,000 dollars), what is the to-complete performance index (TCPI) needed to still finish at the original BAC?

  1. 0.88, because matching the current SPI on the remaining work is sufficient
  2. 1.08, the team must work more efficiently than planned to meet the budget
  3. 0.92, matching the current CPI is sufficient
  4. 1.00, no change in performance is needed

11. A GCHS S-curve calls for 180,000 dollars of spend in Q2, but the funding calendar only releases 120,000 dollars that quarter. What is the BEST response?

  1. Overspend and request forgiveness later
  2. Reconcile the funding limit by re-timing the work to fit available funds, then use change control for any remaining gap
  3. Ask the funder for an early lump-sum release without analysis
  4. Halt the entire project until Q3

12. GCHS has spent 90,000 dollars on site work before learning the site is in a re-mapped floodway. What is the only relevant question now?

  1. Whether the remaining spend is justified by the remaining benefit
  2. Whether the sponsor will be embarrassed by stopping
  3. Whether the 90,000 dollars already spent can be justified to the funder
  4. How much have we already invested?

13. A high-SEER heat pump costs more to install than a standard unit but saves substantially on the homeowner's utility bill over twenty years. Justifying the higher first cost this way is an example of:

  1. Lifecycle costing
  2. Contingency reserve drawdown
  3. Gold plating
  4. Sunk cost reasoning

14. An agile GCHS team funds only the next few iterations at a time, inspects the value delivered, and decides whether to fund more. Forecasting cost in this model becomes primarily a question of:

  1. The contingency reserve balance
  2. The team's run rate multiplied by the number of remaining iterations
  3. The original fixed-price contract ceiling
  4. The independent should-cost estimate

Glossary

Planned value (PV)
The authorized budget assigned to scheduled work as of a given point in time.
Earned value (EV)
The value of work actually completed, expressed in terms of the approved budget for that work.
Actual cost (AC)
The realized cost incurred for the work performed as of a given point in time.
Cost performance index (CPI)
EV divided by AC; below 1.0 means the project is spending more than the value it is earning.
Schedule performance index (SPI)
EV divided by PV; below 1.0 means less work is completed than planned.
Estimate at completion (EAC)
The forecast total cost of the project based on current performance; commonly BAC divided by CPI.
To-complete performance index (TCPI)
The cost efficiency required on remaining work to meet a target such as the BAC or a revised EAC.
Funding limit reconciliation
Comparing the time-phased cost baseline to the money actually available each period, and re-timing work to fit it.