Day 20: Compliance

about 3.3% of the exam content - about 90 minutes - 14 practice questions

0:00 / --:--

Reading

Compliance means the project follows every rule that applies to it: laws, regulations, contract terms, funder conditions, internal policies, safety codes, and privacy obligations. For a construction manager this is familiar territory under different words: you already know that a permit, a lead-safe certification, and a Davis-Bacon wage sheet are not optional. PMI's contribution is a repeatable process for finding those requirements, planning for them, verifying them, and handling violations.

The exam treats compliance seriously. It is one of the few areas where stopping work and escalating immediately are correct answers rather than avoidance.

The non-compliance response sequence Five boxes connected left to right by arrows. Box one, stop the unsafe or non-compliant activity. Box two, determine the facts and root cause. Box three, notify the required parties such as the compliance officer, legal, sponsor, or regulator. Box four, contain and correct the specific instance and apply corrective action. Box five, update the risk register, issue log, and lessons learned. A caption states that stopping the activity always comes first when there is risk of harm or of the violation worsening, and that this is one of the few situations where escalating immediately is the correct exam answer. 1. Stop the unsafe or non-compliant act 2. Determine facts and root cause 3. Notify the required parties 4. Contain and correct; apply fix 5. Update risk, issue, lessons log Stopping the activity (step 1) always comes first when there is risk of harm or of the violation worsening. Compliance is one of the few domains where escalating immediately, rather than analyzing first, is correct.
When non-compliance creates a risk of harm or of the violation worsening, the activity is stopped first, before facts are fully gathered, and only then does the sequence move through fact-finding, notification, correction, and updating the project's records.

Classifying compliance requirements

Before you can plan for compliance you have to know what kind of requirement you are dealing with, because the source determines who enforces it and what happens when it is broken.

CategorySourceGCHS exampleConsequence of violation
Regulatory / legalGovernment statute or ruleEPA Renovation, Repair and Painting lead-safe rule; ADA accessibility standards; local building codeFines, stop-work orders, license loss, criminal liability
ContractualAgreement between partiesHUD or TDHCA grant agreement terms, subcontractor insurance requirements, warranty termsBreach of contract, clawback of funds, termination, damages
Internal policyYour own organizationGCHS procurement thresholds, code of conduct, three-bid ruleDiscipline, audit findings, loss of internal approval
Health and safetyOSHA, state rules, site policyFall protection, silica dust controls, hurricane-season site securingInjury, citations, criminal exposure, project shutdown
Data privacyLaw and policyClient income, disability, and medical documentation; consent for photosRegulatory penalty, breach notification duty, loss of trust
Sustainability / ESGFunder, regulator, boardEnergy-efficiency standards, Section 3 hiring, environmental review, waste diversion reportingLoss of funding eligibility, reporting failure, reputational harm

Finding requirements before they find you

Compliance identification is a planning activity, not a discovery you make during an inspection. The PM should:

  • Review the contract, grant agreement, and charter for stated obligations, reporting duties, and audit rights.
  • Consult subject matter experts: legal counsel, the compliance officer, the safety manager, the funder's program representative. PMI expects the PM to consult experts rather than interpret regulation alone.
  • Research applicable jurisdictional rules: the same rehab scope carries different requirements in a coastal windstorm zone than inland.
  • Record requirements in the requirements documentation and traceability matrix so each one traces to a deliverable and a verification method.
  • Analyze the consequences of non-compliance and record the exposure in the risk register, with owners and responses.
  • Build compliance into the plan: schedule activities, budget cost, assign responsibility, and define quality metrics and audits.
Key points

Compliance costs belong in the budget and compliance activities belong in the schedule. An answer choice that treats a required inspection, certification, training, or report as unplanned overhead is almost always the wrong answer. Planned compliance is cheap; discovered non-compliance is expensive.

Verifying compliance: audits, inspections, and metrics

Planning alone proves nothing. Verification methods include:

  • Quality audits: structured, independent reviews confirming the project follows policies and processes. Audits examine process; inspections examine product.
  • Inspections and testing: third-party or authority-having-jurisdiction verification of the deliverable itself.
  • Checklists and compliance registers: a running list of requirements with status and evidence.
  • Compliance metrics and thresholds: for example, percent of subcontractors with current insurance certificates, or number of open safety observations. A threshold that is crossed should trigger a defined response, not a debate.
  • Documentation and records retention: for funded programs, the file is the compliance. If the required work was performed but not documented, an auditor will treat it as not performed.

When non-compliance happens

This is the highest-yield exam scenario in the domain. The general sequence:

  • Stop the unsafe or non-compliant activity if there is any risk of harm or of worsening the violation. Safety first, always.
  • Determine the facts and the root cause: what happened, what requirement it breached, how far it extends.
  • Notify the required parties: compliance officer, legal, sponsor, and where the rule requires it, the regulator or funder. Some violations carry a legally mandated reporting deadline.
  • Contain and correct: remediate the specific instance, then apply corrective action to stop recurrence.
  • Update the risk register, issue log, and lessons learned, and adjust the plan or process that allowed it.
Escalation is correct here

PMI usually rewards acting over escalating. Compliance is a well-known exception. If a violation is a legal breach, a safety hazard, a fraud indicator, or an ethics violation, the correct exam answer is to stop the activity and report it through the proper channel immediately, even if a stakeholder, a sponsor, or a customer asks you not to. You do not negotiate a legal requirement, and you do not conceal a violation to protect a schedule.

Watch also for the ethics dimension. PMI's Code of Ethics and Professional Conduct requires responsibility, respect, fairness, and honesty. Accepting a gift from a bidder, allowing an undisclosed conflict of interest, or signing off on work that was not done are all compliance failures the exam will test through realistic-sounding scenarios.

Data privacy and AI-era compliance

Housing programs collect deeply personal information: income, disability status, medical need, household composition. The compliance obligations that follow are practical:

  • Collect only the data the program actually requires, and keep it only as long as required.
  • Restrict access to those who need it; do not email client documentation to the whole crew thread.
  • Get consent before using client photos, names, or stories in reporting or promotion.
  • Do not enter personal data into unapproved tools, including AI assistants. Vendor terms may allow the tool to retain or train on submitted content, which can itself be the breach.
  • Know your breach notification duties in advance, because notification deadlines are set by law or contract and can be short.

Compliance across delivery approaches

Agile teams carry the same obligations. The differences are mechanical, not substantive:

  • Compliance requirements can be written as backlog items or as constraints in the definition of done, so no increment is "done" until it satisfies them.
  • Regulated work often uses a hybrid model: iterate on design, but pass mandated gates for permitting, environmental review, and inspection.
  • Some agile environments maintain a compliance backlog or a standing non-functional requirement set reviewed each iteration.
  • Continuous compliance, verifying a little every iteration, beats a single audit scramble at the end, which is the point of building it into the definition of done.

Practice Questions

1. A crew member reports that a subcontractor removed painted trim from a 1958 home without lead-safe containment. What should the project manager do FIRST?

  1. Ask the subcontractor to be more careful next time
  2. Note it in the lessons learned register
  3. Stop the work immediately and secure the area
  4. Finish the day and address it at the weekly meeting

2. Which of the following BEST distinguishes a quality audit from an inspection?

  1. There is no meaningful difference
  2. An audit measures cost performance against the budget; an inspection measures schedule performance against the baseline
  3. An audit is done by the project team on itself; an inspection is done by the customer at final acceptance
  4. An audit examines the process; an inspection examines the product

3. A grant agreement between GCHS and a private foundation requires quarterly outcome reports and photo documentation of each finished unit. Which compliance category is this?

  1. Regulatory
  2. Voluntary best practice
  3. Internal policy
  4. Contractual

4. When should compliance requirements be identified on a project?

  1. Only if a stakeholder or funder representative raises them in writing
  2. During planning, before execution begins
  3. When an inspector arrives on site and cites the first violation
  4. At project closure, when the compliance file is assembled for audit

5. A sponsor asks the project manager not to report a documented safety violation because it would delay the funding draw. What should the PM do?

  1. Ask the team to vote on it
  2. Follow the sponsor's direction since the sponsor has authority
  3. Report the violation through the required channel and document the request
  4. Delay reporting until after the draw clears

6. Which of the following is NOT a typical consequence of non-compliance with a regulatory requirement?

  1. Automatic scope increase approval
  2. Loss of license or of eligibility for future funding
  3. Fines and penalties assessed by the regulator
  4. Stop-work orders issued by the authority having jurisdiction

7. A GCHS estimator skips the organization's own three-bid rule to save time on a small purchase. Which compliance category does this violate?

  1. Internal policy, since GCHS's own procurement rule created the obligation
  2. Regulatory, since it comes from a government statute that sets competitive bidding thresholds for nonprofits
  3. Contractual, since it comes from a signed agreement
  4. Health and safety

8. When identifying which compliance requirements apply to a new GCHS rehab, what does PMI expect the project manager to do?

  1. Delegate the entire question to the crew lead
  2. Interpret the applicable regulations directly, without outside input
  3. Consult subject matter experts such as legal counsel, the compliance officer, the safety manager, or the funder's program representative
  4. Wait for an inspector to identify the requirements during a site visit

9. Why does a project manager record compliance requirements in the requirements documentation and traceability matrix?

  1. To assign blame after a violation occurs
  2. So each requirement traces to a specific deliverable and a verification method
  3. To replace the risk register entirely once each requirement has a planned verification method
  4. To track only the project budget

10. A compliance metric, such as percent of subcontractors with current insurance certificates, crosses a defined threshold. What should happen?

  1. The threshold is quietly lowered so it is no longer crossed
  2. The threshold triggers the defined response already specified for it
  3. The team debates whether the threshold is fair before acting
  4. The finding is set aside until the next scheduled audit

11. Lead-safe work practices were actually followed on a unit, but the required compliance records were never filed. How will an auditor treat this?

  1. As acceptable, as long as no auditor or funder representative specifically asks about it
  2. As satisfied by the crew lead's verbal confirmation that the work was done correctly
  3. As if the lead-safe work practices were not performed at all
  4. As fully compliant, since the work itself was completed

12. A bidder on a GCHS procurement offers the project manager a personal gift during vendor selection. What should the project manager do?

  1. Accept the gift but tell no one about it
  2. Ask the bidder to offer something smaller instead
  3. Accept the gift quietly since it is a minor gesture
  4. Decline the gift and disclose the offer, consistent with PMI's Code of Ethics requirement of honesty and fairness

13. How do agile teams typically build compliance requirements into their delivery process?

  1. Compliance requirements become backlog items or part of the definition of done, so no increment is complete without them
  2. Compliance requirements are handled entirely by a separate compliance team outside the backlog, which reviews the product after release
  3. Agile teams are exempt from compliance requirements
  4. Compliance is addressed only in a single audit at the very end of the release

14. Before including a homeowner's photo in a funder progress report, what must the project manager obtain?

  1. Nothing, since it documents a successful project outcome and the funder already owns the program records
  2. Consent only if the homeowner is a minor
  3. No formal step is needed unless the homeowner objects afterward
  4. The homeowner's consent before using their photo, name, or story in reporting or promotion

Glossary

Compliance
Following every rule that applies to a project: laws, regulations, contract terms, funder conditions, internal policy, safety codes, and privacy obligations.
Quality audit
A structured, independent review confirming a project follows its policies and processes.
Inspection
Third-party or authority-having-jurisdiction verification of the deliverable itself.
Compliance threshold
A defined variance or metric level that, once crossed, triggers a specified response rather than a debate.
Requirements traceability matrix
A record linking each requirement to the deliverable it affects and the method used to verify it.
Code of Ethics and Professional Conduct
PMI's standard requiring responsibility, respect, fairness, and honesty in professional conduct.
Definition of done
The agreed conditions, which can include compliance requirements, that an increment must satisfy before it counts as complete.
Breach notification duty
A legally mandated deadline for disclosing a data privacy or security incident to affected parties or regulators.