Lesson 7: The plan review process and report format
TDLR RAS Procedures · 14 practice questions
0:00 / --:--
Reading
Lessons 3 through 6 covered what a RAS checks. This lesson covers how a
RAS actually conducts a plan review and what the resulting report has to
contain, drawn from TDLR's own RAS Procedures document (effective
December 3, 2018, still the version TDLR links on its RAS page). This is
the paperwork side of the job. The Procedures set required content,
format, and deadlines, and TDLR can audit a RAS's work, so a correct
finding delivered in the wrong format, or late, is still a procedural
problem.
Before the review starts
Plan review is tied to construction. Under Government Code Section
469.101, plans for a subject building with an estimated construction cost
of at least $50,000 must be submitted for review, and under Rule 68.50 the
design professional with overall responsibility submits them to a RAS not
later than the 20th day after issuing them, not counting weekends and
legal holidays. Before conducting the review, the RAS must have in hand
the AB Project Registration Form (when the RAS registers the project), a
Designated Agent Form signed by the owner if the owner has named one, a
Proof of Submission Form signed by the design professional if one applies,
and the construction documents to be used for construction. A RAS who
starts reviewing drawings without these in the file is working outside the
procedure before the technical review has even begun.
What the report must contain
The plan review report has to be typewritten and must include: a
heading identifying it as a "Plan Review Report" or "Plan Revision
Report," the RAS's name and license number, the report date, the TABS
project number, the facility name, the project name and address, and a
detailed listing of deficiencies, each one referencing the specific TAS
reference number, its location in the building, and the possible
violation. A completed Attachment "A" is also required. Attachment "A"
is TDLR's prescribed transmittal letter, "Plan Review/Revision Completed."
If the review finds no deficiencies at all, the procedures (Section
3.9.1) allow that transmittal letter to be used instead of a full
deficiency report, but that shortcut only applies when there is genuinely
nothing to report. Under RAS Bulletin 2023-05 (effective September 1,
2023, citing Rule 68.53(b)), TDLR also prescribes the results, action, and
disclaimer paragraphs that transmittal letters carry, so use TDLR's
current wording rather than writing your own.
Submission timeframes
The RAS must issue the report to the owner or designated agent within
30 days of the report's completion date, and must upload it to the TABS
system, TDLR's online project tracking system, within 30 days of the
report date as well. These two 30-day clocks run in parallel from
essentially the same date, not one after the other, so a RAS working
toward the deadline should be treating both delivery to the owner and the
TABS upload as due at the same time, not sequential steps with 30 days
each.
Why the deficiency listing has to be this specific
A deficiency entry that just says "restroom noncompliant" is not
useful to an owner trying to fix it, and it is not what the procedure
requires. Each deficiency has to name the TAS section the drawing fails,
where in the building it occurs, and what the potential violation is.
Lessons 3 through 6 gave you the actual technical vocabulary, the section
numbers and dimensions, that a properly written deficiency entry draws
on. "Section 604.5.1: side-wall grab bar shown at 36 inches, 6 inches
short of the 42-inch minimum, men's restroom, first floor" is the kind of
entry the procedure is asking for.
How this connects forward to the inspection lesson
A plan review happens before construction, checking the design. Lesson
8 covers the inspection process, which happens after construction is
complete, checking what was actually built against the same TAS
technical chapters. The two processes share the same underlying technical
standard and much of the same report structure, but they happen at
different points in a project's life and use different report
attachments, which lesson 8 covers directly.
The plan review sequence runs from gathering required forms through the technical review to a report issued and uploaded within 30 days.
Practice questions
1. What must a RAS have in hand before starting a plan review?
The registration form if the RAS registers the project, applicable agent and submission forms, and the construction documents
Nothing; a RAS may begin as soon as the owner verbally asks for a review of the drawings
Only the construction documents, since the forms are collected after the review is finished
A signed contract with the owner's attorney and a copy of the building permit
Answer: a. TDLR's procedures (Section 4.2.1) require the AB Project Registration Form when the RAS registers the project, the Designated Agent Form and Proof of Submission Form if applicable, and the construction documents before the review begins.
2. What heading must the plan review report carry?
No specific heading is required as long as the RAS signs and dates the report
"Compliance Certificate" issued under the Texas Accessibility Standards
"Plan Review Report" or "Plan Revision Report"
"Preliminary Findings Memo" followed by the RAS license number
Answer: c. The report must be headed "Plan Review Report" or "Plan Revision Report."
3. What identifying information must the report include, beyond the deficiency list?
The building owner's Social Security number and the contractor's license number
RAS name and license number, report date, TABS number, and facility and project name and address
Only the RAS's name and signature, along with a notarized statement from the building owner about the project
Only the project address, the estimated construction cost, and the contractor name and telephone number
Answer: b. The report needs the RAS's name and license number, the report date, the TABS project number, and the facility name and the project name and address.
4. What must each deficiency entry in the report reference?
Only a general description of the problem, with no code citation
The contractor's bid amount and the estimated cost of the correction
Only a photograph or marked-up sketch of the condition, with the owner's initials on it
The TAS section, its location in the building, and the potential violation
Answer: d. Each deficiency must cite the TAS reference number, where it occurs in the building, and the possible violation, not a vague general description.
5. Which attachment must accompany a plan review report?
Attachment "D"
Attachment "E"
No attachment is required for plan review
Attachment "A"
Answer: d. A completed Attachment "A" is required with the plan review report.
6. What shortcut does the procedure allow when a plan review finds no deficiencies at all?
A transmittal letter may substitute for the full report
The RAS may skip the technical review entirely on the next project
The owner may waive the review fee
No report of any kind is needed
Answer: a. When no deficiencies are found, a transmittal letter (Attachment "A") may be used instead of the full deficiency report, per Section 3.9.1 of TDLR's procedures.
7. Within how many days of report completion must the RAS issue the plan review report to the owner or designated agent?
90 days
7 days
15 days
30 days
Answer: d. The report must be issued to the owner or designated agent within 30 days of the report's completion date.
8. Within how many days of the report date must the RAS upload the report to TABS?
30 days
60 days
There is no upload deadline
10 days
Answer: a. The TABS upload is also due within 30 days of the report date, running in parallel with the owner-delivery deadline.
9. Do the owner-delivery and TABS-upload deadlines run sequentially or in parallel?
They are the same single deadline with no separate tracking
In parallel, both measured from essentially the same date
Sequentially, TABS upload only after the owner has responded
The TABS upload deadline only starts after 60 days
Answer: b. Both 30-day clocks run in parallel from essentially the same date, not one after the other.
10. What is wrong with a deficiency entry that just reads "restroom noncompliant"?
It is too long, and the Procedures ask for a one-word summary of each finding
It fails to cite the specific TAS section, location, and potential violation the procedure requires
It should cite ADA Title III and DOJ regulations rather than TAS for any restroom deficiency
Nothing; the Procedures prefer short general descriptions when the owner is a public entity
Answer: b. A vague entry like that skips the section citation, location, and violation detail the procedure specifically requires.
11. What is TABS, as used in RAS reporting?
The vendor that develops and administers the RAS licensing exam for TDLR
A private accreditation body for accessibility consultants and design firms
A federal court system that hears appeals of TDLR variance decisions
TDLR's online project tracking system where reports are uploaded
Answer: d. TABS, the Texas Architectural Barriers online System, is TDLR's system for tracking RAS project files, where plan review and inspection reports are uploaded.
12. Does a plan review happen before or after construction?
Plan review and inspection happen at the same time
Plan review only happens for renovation projects
Before construction, reviewing the design
After construction, reviewing what was built
Answer: c. Plan review happens before construction, checking the design against TAS. Inspection, covered next lesson, happens after construction.
13. A RAS finds a side-wall grab bar shown at 36 inches on the drawings. What TAS section from lesson 4 does this deficiency reference?
Section 404.2.3
Section 304.3
Section 604.5.1
Section 208.2
Answer: c. Section 604.5.1 sets the side-wall grab bar at 42 inches minimum, so a 36-inch bar is a deficiency against that section.
14. Why does TDLR treat the report format itself as part of the regulated function, not just paperwork?
Because TDLR only reviews reports at renewal time, when the license is up for renewal
Because the format is optional and left to each RAS's preference and the owner's approval
Because the Procedures set required content, format, and deadlines, and TDLR can audit them
Because report format has no bearing on how TDLR or the owner treats the finding
Answer: c. The RAS Procedures set report content, format, and timing as required parts of the job, and Section 3.10 lets TDLR audit RAS work, with administrative penalties, sanctions, or both possible if unsatisfactory findings are not addressed.
Glossary
AB Project Registration Form
Form required in the project file before a RAS begins plan review, when the RAS registers the project.
Attachment "A"
TDLR's prescribed transmittal letter, "Plan Review/Revision Completed," required with every plan review report.
TABS
TDLR's online system for tracking RAS project files and report uploads.
Transmittal letter
A shortened alternative to the full report, permitted only when no deficiencies are found.