Lesson 8: The inspection process and report format
TDLR RAS Procedures · 14 practice questions
0:00 / --:--
Reading
Inspection happens after construction is finished, verifying what was
actually built against the same TAS technical chapters a plan review
checks in the design. The process, the report contents, and the
follow-through on violations are all more involved than plan review,
because an inspection that finds violations starts a 270-day correction
window and, if problems are not fixed, a mandatory transfer of the file.
Before the inspection
The owner of a subject building is responsible for having it inspected
not later than the first anniversary of the completion of construction
(Government Code Section 469.105 and Rule 68.52(a)). Completion of
construction is the date the project results in occupancy or a certificate
of occupancy is issued (Rule 68.10). TDLR's plan review transmittal letter
also tells the owner to request the inspection no later than 30 days after
completion, so treat 30 days as the working target and one year as the
outer limit. The request can be in any written format from the owner or
designated agent. Before inspecting, a RAS must obtain access to the
project file, either through a file transfer request or through the TABS
Sharing System, must confirm that a written inspection request from the
owner or designated agent is already in the file, and must obtain a copy
of the Designated Agent Form if one applies. A TDLR "Notice of Inspection
Overdue" is not treated as a request for inspection.
At the inspection
The RAS must obtain a signed proof of inspection form at the time of
the inspection itself. This is a contemporaneous record that the
inspection actually took place on a specific date, separate from the
report that follows.
What the inspection report must contain
Like the plan review report, the inspection report must be typewritten
and headed, in this case "Inspection Report." It must include the RAS's
name and license number, the report date and the actual date the
inspection occurred, the TABS project number, the facility name, the
project name and address, and a detailed listing of deficiencies with TAS
reference numbers, locations, and violations. Instead of Attachment "A,"
the inspection report is completed with Attachment "B" (Inspection
Completed, Violations Pending) or Attachment "C" (Inspection Completed,
No Violations). These attachments are TDLR's prescribed transmittal
letters, and the letter date must match the report date. Where there are
no violations at all, transmittal letter "C" may be used instead of a full
report. TDLR's procedures also make one point explicit: photographs and
other documents are not permitted to take the place of a written
description of a violation. A photo can support the written finding; it
cannot substitute for it.
Submission timeframes
The RAS must issue the inspection report to the owner or designated
agent within 30 days of the inspection date, and upload the results and the
proof of inspection to TABS within 30 days of the report date, the same
two-track 30-day pattern as plan review. The RAS may retain the project
file for up to 270 days from the inspection report date, or until
verification of corrective modifications is received, whichever comes
first.
What happens when violations are found
Where an inspection finds violations, the Attachment "B" letter gives the
owner 270 calendar days from the date of the letter, which matches the
inspection report date, to furnish written verification that every
violation has been corrected. RAS Bulletin 2023-06 (effective September 1,
2023, citing Rule 68.40(d)) adds a first step: the owner must respond in
writing on TDLR's Inspection Response Form (EAB-229N) no later than 30
days after the date of the inspection report, stating that corrections are
complete, asking for an extension, or saying that a variance application
will be submitted. Once the RAS receives written corrective documentation,
the RAS has 30 days to issue either Attachment "D," Corrective
Modifications with Violations Pending, if items are still uncorrected, or
Attachment "E," Corrective Modifications with No Violations, if everything
has been fixed. The RAS then uploads that result to TABS within 30 days of
receiving the owner's documentation.
Escalation when correction does not happen
If full compliance is not achieved within the 270-day window, the RAS
is required to transfer the project file, uploading it to the TABS
Transfer System within 30 days of the 270th day, or by the 300th day at
the latest. This is not discretionary on the RAS's part. If the file is
not transferred, the procedures say it is transferred to TDLR
automatically after 301 days. A stalled correction does not just sit in
the RAS's file indefinitely; the procedure forces it back into TDLR's
system within a fixed window.
Why this two-report structure matters to GCHS
A GCHS-employed RAS working a project from design through completion
would produce two separate, differently structured reports on the same
building, a plan review report before construction and an inspection
report after, each with its own attachment letters and its own
deadlines. Treating them as one continuous "accessibility check" rather
than two distinct regulated deliverables, each with its own required
content and clock, is the kind of procedural mistake TDLR's rules are
built to catch.
The inspection timeline runs from construction completion through a 270-day correction window to mandatory escalation if compliance is not achieved.
Practice questions
1. By when must the owner obtain an inspection after construction is complete?
There is no deadline as long as the certificate of occupancy has been issued
Not later than the first anniversary of the completion of construction
Within 7 days of the plan review report being issued to the owner
Within 270 days of the completion of construction, the same window used for corrections
Answer: b. Government Code Section 469.105 and Rule 68.52(a) require the owner to obtain an inspection not later than the first anniversary of the completion of construction. TDLR's plan review transmittal letter also tells the owner to request it within 30 days after completion, so request it promptly.
2. What must a RAS obtain at the time of the inspection itself?
A building permit copy
A notarized affidavit from the contractor
Nothing beyond the report
A signed proof of inspection form
Answer: d. A signed proof of inspection form is required at the time of the inspection, a contemporaneous record separate from the later report.
3. What heading must the inspection report carry?
"Compliance Certificate"
No specific heading is required
"Inspection Report"
"Plan Review Report"
Answer: c. The inspection report is headed "Inspection Report," distinct from the plan review report's heading.
4. Which attachment accompanies an inspection report when violations are pending?
Attachment "E"
Attachment "A"
Attachment "B"
Attachment "C"
Answer: c. Attachment "B" is used when violations are pending. Attachment "C" is used when there are none.
5. Can photographs replace a written description of a violation in an inspection report?
Yes, but only for restroom violations and other findings that involve fixtures or clearances
Only if the owner agrees in writing to accept photographs
Yes, photographs are sufficient on their own when they are dated, labeled, and attached to the report
No, photographs and other documents cannot take the place of a written description
Answer: d. TDLR's procedures explicitly state photographs and other documents cannot substitute for a written violation description; they can only support it.
6. Within how many days of the inspection date must the report be issued to the owner or designated agent?
10 days
15 days
30 days
60 days
Answer: c. 30 days from the inspection date, the same pattern as the report-to-owner deadline in plan review.
7. For how long may a RAS retain the project file to verify corrective modifications?
180 days from the inspection, with an extension available on the owner's request
Up to 270 days, or until corrections are verified, whichever comes first
Thirty days from the date the report was uploaded to TABS, unless the owner objects
Ninety days, with one 90-day extension allowed if the owner asks in writing
Answer: b. The RAS may retain the file up to 270 days from the inspection report date, or until verification of corrective modifications is received, whichever comes first.
8. What written verification must the owner furnish if an inspection found violations?
Nothing; the RAS closes the file automatically after 30 days if the owner does not respond
Written verification that every violation is corrected, within 270 days of the report date
A verbal confirmation to the RAS, followed by a new construction permit
A new construction permit and a second inspection request within 30 days
Answer: b. The owner must furnish written verification that every violation is corrected within the 270-day window. Since September 1, 2023, the owner must also return TDLR's Inspection Response Form within 30 days of the report date (RAS Bulletin 2023-06).
9. Once the RAS receives the owner's corrective documentation, how long does the RAS have to respond?
30 days, issuing Attachment "D" or Attachment "E"
90 days, issuing a single closing letter to the owner and TDLR
There is no deadline for the RAS's response, since the file stays open
7 days, with the results uploaded to TABS on the same day
Answer: a. The RAS has 30 days to issue Attachment "D" (violations still pending) or Attachment "E" (no violations remaining).
10. What does Attachment "E" specifically indicate?
Corrective Modifications, No Violations: everything cited has been fixed
The project file has been transferred through the TABS Transfer System after day 300
Violations are still pending after the owner's correction attempts
The inspection has not yet occurred and the request is on file
Answer: a. Attachment "E," Corrective Modifications, No Violations, confirms every violation has been corrected.
11. What happens if full compliance is not achieved within the 270-day window?
The 270-day window automatically extends indefinitely while the owner keeps working
The RAS license of the person who inspected the building is revoked
The RAS must transfer the file through the TABS Transfer System by day 300
The file is simply closed with no further action by the RAS or TDLR
Answer: c. Escalation is mandatory: the file must be transferred via the TABS Transfer System within 30 days of day 270, no later than day 300. After 301 days the procedures say the file is transferred to TDLR automatically.
12. Is escalation at day 270-300 discretionary for the RAS?
Yes, but only with TDLR's written permission to keep the file open
Escalation does not apply to inspections, only to plan review files
Yes, the RAS may choose to keep the file open longer if the owner is cooperating
No, the transfer requirement is mandatory under the procedure
Answer: d. The transfer requirement at day 270-300 is mandatory, not left to the RAS's discretion.
13. How does an inspection report's attachment lettering differ from a plan review report's?
Plan review uses "A"; inspection uses "B" or "C," with "D" or "E" for the later correction cycle
Both use the same attachment letters, with the type of report shown only in the heading
Plan review has no attachments; only inspection reports use attachment letters and forms
Inspection reports never use attachment letters and rely only on the written heading
Answer: a. Each report type and stage of the process has its own attachment letter, from "A" at plan review through "E" at final correction verification.
14. Why is it a mistake to treat plan review and inspection as one continuous "accessibility check"?
Because they use identical report headings, attachments, and deadlines in every case
Because they are two separate deliverables, each with its own content, attachments, and deadlines
Because inspection replaces the need for plan review entirely on subject projects
Because only one of the two is actually required by TDLR for a subject project
Answer: b. Plan review and inspection are separate regulated deliverables with their own headings, attachments, and deadlines, not one combined check.
Glossary
Proof of inspection form
Signed at the time of inspection, a contemporaneous record distinct from the later written report.
Attachment "B" / "C"
Accompanies the inspection report: "B" for violations pending, "C" for none found.
Attachment "D" / "E"
Issued after the owner's corrective documentation: "D" if violations remain, "E" if all are corrected.
270-day correction window
The period from the inspection report date within which the owner must document full correction.
TABS Transfer System
Where a RAS must transfer an uncorrected project file by day 300 at the latest.