Module 7 - Risk Management

Day 22: Risk Response, Insurance, and Surety

9% of the exam - about 2 hours - 14 practice questions

0:00 / --:--

Reading

Threat Response Strategies

Four classic strategies, and the exam tests the distinctions precisely.

Avoid eliminates the threat by changing the plan. Relocating a structure off a contaminated parcel avoids the contamination risk entirely. Avoidance removes the risk rather than managing it.

Transfer shifts the financial consequence to a third party. Insurance, bonding, and indemnity clauses are transfers. Note what transfer does and does not do: it moves the financial impact, it does not make the event less likely, and it is never free.

Mitigate reduces probability, impact, or both. Additional geotechnical borings mitigate the unknown-conditions risk by reducing its probability. Staging critical materials early mitigates the supply risk.

Accept takes the risk knowingly. Active acceptance establishes a contingency reserve against it. Passive acceptance does nothing and deals with it if it occurs. Acceptance is the correct answer for low-probability, low-impact risks where response cost exceeds expected value.

Opportunity response strategies mirror them: exploit ensures the opportunity is realized, share partners with someone better able to capture it, enhance increases probability or impact, and accept takes it if it comes.

Escalate is a fifth strategy in current practice for risks outside the project's authority, raised to the program or portfolio level. Know it by name.

Risk response strategies grouped into threats, opportunities and either Three groups. Threat responses: avoid, transfer, mitigate. Opportunity responses that mirror them: exploit, share, enhance. Responses that apply to either: accept, which can be active or passive, and escalate, used when a risk is outside the project's own authority and is raised to the program or portfolio level. Threats Opportunities Either Avoid Exploit Transfer Share Mitigate Enhance AcceptActive or passive; applies tothreats and opportunities EscalateOutside project authority; raisedto program or portfolio level
Threat and opportunity strategies mirror each other row by row (avoid and exploit, transfer and share, mitigate and enhance); accept and escalate apply to either, so they sit outside the pairing.

Secondary and Residual Risk

Two terms the exam likes. Residual risk is what remains after a response is implemented; mitigation rarely reduces risk to zero. Secondary risk is a new risk created by the response itself. Transferring work to a lower-cost subcontractor to mitigate cost risk may create a quality or solvency risk that did not exist before. A complete response plan names both.

Insurance

The core construction products and what they actually cover:

Commercial General Liability covers third-party bodily injury and property damage arising from operations. It does not cover the insured's own defective work, though it may cover resulting damage to other property caused by that defective work, a distinction that generates enormous litigation.

Workers' Compensation covers employee injury on a no-fault basis and is the exclusive remedy against the employer in most jurisdictions. Employer's Liability fills gaps around that exclusivity.

Builder's Risk is first-party property insurance covering the work in progress against physical loss, typically written on the project rather than a party. Key issues are who is named, whether it covers materials in transit and stored off site, the deductible and who bears it, and whether it includes soft costs and delay in start-up.

Professional Liability covers negligent acts, errors, or omissions in professional services. A CM providing professional services needs it, and an owner should require it. It is claims-made, meaning coverage responds to claims made during the policy period, which is why tail coverage after project completion matters.

Umbrella or Excess sits above the primary limits.

Pollution Liability covers pollution conditions generally excluded from CGL.

Wrap-ups consolidate coverage for all enrolled parties under one program: an OCIP is owner-controlled, a CCIP is contractor-controlled. Advantages include consistent limits, potential cost savings, and reduced litigation among enrolled parties. Disadvantages include administrative burden and the need to strip insurance cost from bids so the owner does not pay twice.

Surety Bonds

A bond is not insurance. Insurance is a two-party risk transfer in which losses are expected and priced. A bond is a three-party instrument among the principal (contractor), the obligee (owner), and the surety, in which the surety guarantees the principal's performance and expects no losses, because the surety underwrites to the contractor's capacity and requires indemnity from the principal. When a surety pays, it generally seeks recovery from the contractor.

Bid bonds guarantee that a successful bidder will enter the contract and furnish required bonds. Performance bonds guarantee completion per the contract. Payment bonds guarantee payment to subcontractors and suppliers. On private work that protects the owner from liens. On public work, where liens generally cannot attach to public property, the payment bond is the claimants' substitute remedy, and it is required on most public work. Maintenance bonds cover defects during a stated warranty period.

On federal work, the Miller Act requires performance and payment bonds above a statutory threshold, and state Little Miller Acts impose similar requirements on state and local public work. The CM should know these exist and that thresholds vary.

When a contractor defaults, the surety's options under a performance bond typically include financing the existing contractor to completion, tendering a replacement contractor, taking over and completing, or paying the obligee. The surety chooses, not the owner, and the CM's role is to document the default carefully and preserve the owner's rights, since a defective default declaration can jeopardize the bond claim.

Practice Questions

1. Relocating a building to avoid a contaminated parcel is:

  1. Transfer
  2. Accept
  3. Mitigate
  4. Avoid

2. Purchasing insurance against a risk is:

  1. Exploitation
  2. Transfer
  3. Avoidance
  4. Mitigation

3. Additional geotechnical borings to reduce the likelihood of unknown conditions is:

  1. Transfer
  2. Accept
  3. Avoid
  4. Mitigate

4. Establishing a contingency reserve for a known risk without other action is:

  1. Transfer
  2. Active acceptance
  3. Passive acceptance
  4. Mitigation

5. A new risk created by implementing a risk response is:

  1. An opportunity
  2. Residual risk
  3. Secondary risk
  4. An issue

6. Risk remaining after a response is implemented is:

  1. Residual risk
  2. A trigger
  3. Secondary risk
  4. An issue

7. A surety bond differs from insurance because it is:

  1. Cheaper
  2. First-party coverage
  3. Required by OSHA on every construction project above a stated contract value, whatever the delivery method
  4. A three-party instrument in which the surety expects no loss and seeks indemnity

8. Payment bonds primarily protect the owner by:

  1. Guaranteeing completion of the work by the contractor or a replacement contractor
  2. Guaranteeing payment to subcontractors and suppliers, protecting against liens
  3. Covering defects
  4. Insuring the work in progress

9. Builder's risk insurance covers:

  1. The work in progress against physical loss
  2. Third-party bodily injury
  3. Employee injury
  4. Professional errors

10. Professional liability policies are typically claims-made, which means:

  1. Coverage responds to claims made during the policy period, so tail coverage matters after completion
  2. No deductible applies
  3. Coverage follows the occurrence date regardless of when the claim is made, and no tail coverage is ever needed
  4. Coverage is unlimited

11. Upon contractor default under a performance bond, the choice of remedy typically belongs to:

  1. The owner
  2. The court
  3. The CM
  4. The surety

12. A CM partners with a specialty subcontractor who is better positioned to capture a value-engineering opportunity. This is:

  1. Transfer
  2. Mitigate
  3. Share
  4. Avoid

13. A risk sits outside the project's own authority to resolve, such as a policy decision only the owner's board can make. The appropriate strategy is:

  1. Passive acceptance
  2. Mitigate
  3. Escalate
  4. Avoid

14. CGL insurance's coverage of the insured's own defective work is best described as:

  1. Covered only under a wrap-up
  2. Fully covered without exception, including the cost to repair or replace the defective work
  3. Generally excluded, though resulting damage to other property may be covered
  4. Covered only under builder's risk

Micro-Assignment

Take the top five risks from your Day 21 register. For each, select a response strategy, state specifically what the response is, estimate its cost, and identify both the residual risk that remains and any secondary risk the response creates. Then write two sentences identifying which of the five you would recommend simply accepting, and why the response cost is not justified.

Glossary

Avoid / Transfer / Mitigate / Accept
The four threat response strategies.
Exploit / Share / Enhance / Accept
The four opportunity response strategies.
Escalate
Raising a risk outside the project's authority to the program or portfolio level.
Residual Risk
Risk remaining after response.
Secondary Risk
New risk created by a response.
OCIP / CCIP
Owner-controlled and contractor-controlled insurance programs.
Miller Act
Federal statute requiring performance and payment bonds above a threshold.
Claims-Made Policy
Coverage responding to claims made during the policy period regardless of when the underlying act occurred; tail coverage extends this after the policy ends.

Progress

Previous: Day 21 Next: Day 23