Module 7 - Risk Management

Day 23: Contractual Risk Transfer, Force Majeure, and Module Mini-Exam

9% of the exam - about 2 hours - 14 practice questions

0:00 / --:--

Reading

Contractual Risk Allocation

The sound principle, and the one the exam endorses, is that risk should be allocated to the party best able to control, absorb, or price it. Allocating a risk to a party that cannot control it does not eliminate the risk; it prices it into the bid, usually inefficiently, or produces a dispute when it occurs.

An owner who disclaims all responsibility for subsurface conditions does not make rock disappear. Contractors either add contingency they may not need, which the owner pays for on every project, or they bid thin and fight when rock appears. Either way the owner pays, and the second way costs more.

Differing Site Conditions Clauses

A DSC clause is the standard mechanism for allocating subsurface risk sensibly. Type I covers conditions materially differing from those indicated in the contract documents. Type II covers unknown physical conditions of an unusual nature differing materially from those ordinarily encountered in work of that character.

The clause requires prompt notice before the conditions are disturbed, precisely so the owner can observe and verify. A contractor who excavates through the condition and claims later has usually destroyed the evidence and weakened the claim. The CM's role when notice arrives is to go look immediately, document conditions with photographs and measurements, and preserve the ability to evaluate.

Indemnity Clauses

These shift liability for claims, and the exam tests the three forms. Broad form indemnity makes the indemnitor responsible even for the indemnitee's sole negligence. Many states prohibit this by anti-indemnity statutes as against public policy. Intermediate form covers the indemnitee's partial negligence. Limited form covers only the indemnitor's own negligence and is generally enforceable.

The CM's practical duty is not to draft indemnity language, which is legal work, but to recognize when a proposed clause reaches further than the local statute allows, and to flag it for the owner's counsel rather than assume it will hold.

Additional insured status works alongside indemnity. Requiring the contractor to name the owner and CM as additional insureds on the CGL policy means the contractor's insurer defends and indemnifies them directly. The endorsement form and its edition date matter greatly, because forms differ in whether they cover completed operations and whether they cover the additional insured's own negligence. Specifying the form by number rather than saying "name us as additional insured" is the competent practice.

Waiver of subrogation prevents an insurer that pays a loss from stepping into its insured's shoes and suing another project party. Mutual waivers of subrogation among owner, contractor, and designer for risks covered by property insurance reduce circular litigation and are standard in most contract families.

Limitation of Liability and Consequential Damages Waivers

Many contracts include a mutual waiver of consequential damages, meaning neither party can recover indirect losses such as lost profits, lost rental income, or loss of use. This matters enormously to owners, because delay damages on a revenue-generating facility are often consequential. An owner who signs a mutual waiver and then suffers a long delay may find its actual loss unrecoverable, which is exactly why liquidated damages provisions exist as the negotiated substitute.

Force Majeure

A force majeure clause excuses performance for events beyond the parties' control. What counts is defined by the clause, not by intuition, and post-2020 contracts often address epidemics and government orders explicitly where older forms did not. Typical treatment grants time but not money, consistent with the excusable non-compensable classification from Module 3. The CM should read the actual clause before advising on entitlement, because the list is negotiated and varies.

Risk in Delivery Method Selection

Delivery method is itself a risk decision, tying back to Module 1. Design-Bid-Build with a complete design and lump sum pricing transfers the most cost risk to the contractor but requires complete documents and offers the least flexibility. CM at Risk with a GMP gives cost certainty earlier at the price of setting that certainty against incomplete design. Design-Build consolidates responsibility, reducing the owner's exposure to design-construction coordination gaps but reducing owner control. IPD shares risk deliberately. The CM advising on delivery method is performing risk management, and the exam frames it that way.

Delivery methods arranged along a spectrum of owner control versus contractor cost-risk transfer Design-Bid-Build with lump sum pricing transfers the most cost risk to the contractor but requires complete documents and offers the least flexibility. CM at Risk with a GMP trades some cost certainty against incomplete design. Design-Build consolidates responsibility and reduces coordination-gap exposure but reduces owner control. Integrated Project Delivery shares risk deliberately among all parties. Design-Bid-BuildMost cost risk tocontractor; least flexible CM at Risk / GMPEarlier cost certaintyvs. incomplete design Design-BuildConsolidated responsibility;less owner control IPDRisk shareddeliberately, by design Owner controls cost risk Risk shared or transferred away
Choosing a delivery method is a risk allocation decision made before the first contract is even drafted, not something layered on afterward.

Practice Questions

1. Risk should be allocated to:

  1. The party best able to control, absorb, or price it
  2. The contractor in all cases
  3. The party with the deepest pockets
  4. Whoever will accept it

2. Rock encountered that differs materially from the borings shown in the contract documents is:

  1. Contractor risk regardless
  2. Type II differing site condition
  3. Force majeure
  4. Type I differing site condition

3. An unknown physical condition of an unusual nature, not ordinarily encountered in work of that character, is:

  1. Type I
  2. A constructive change
  3. An issue
  4. Type II

4. A contractor excavates through a differing condition before giving notice. The likely effect is:

  1. Automatic entitlement
  2. Weakened claim, since the evidence was destroyed and the owner could not verify it
  3. Strengthened claim, because the contractor can show its own photographs of the excavation
  4. No effect

5. Indemnity requiring the indemnitor to cover the indemnitee's sole negligence is:

  1. Broad form, prohibited by anti-indemnity statutes in many states
  2. Limited form, the version most states prohibit because it protects the indemnitee the most
  3. Intermediate form
  4. Standard and universally enforceable

6. Specifying the additional insured endorsement by form number rather than generally is important because:

  1. Forms differ on completed operations and on the additional insured's own negligence
  2. It waives subrogation
  3. It is required by OSHA
  4. It reduces the premium, since the insurer then treats the contractor as a lower hazard class

7. A mutual waiver of consequential damages means an owner generally cannot recover:

  1. Direct repair costs
  2. Liquidated damages
  3. Lost profits, lost rent, and loss of use
  4. Retainage

8. Waiver of subrogation prevents:

  1. The contractor from suing the owner over unpaid change orders and delay claims
  2. An insurer that paid a loss from suing another project party
  3. Claims for delay
  4. Liquidated damages

9. Under a typical force majeure clause, entitlement is generally:

  1. Time and money
  2. Time only
  3. Money only
  4. Termination

10. An owner disclaims all subsurface responsibility on a project with limited borings. The probable result is:

  1. Faster schedule
  2. Elimination of subsurface risk, because the contractor now controls every site condition
  3. Contractors pricing contingency into every bid or bidding thin and disputing later
  4. Lower cost

11. Indemnity limited to the indemnitor's own negligence is:

  1. Limited form, generally enforceable
  2. Prohibited in most states
  3. Broad form
  4. Intermediate form

12. Design-Bid-Build with a lump sum price, compared to CM at Risk with a GMP, generally:

  1. Eliminates the need for a design
  2. Guarantees cost certainty earlier
  3. Transfers more cost risk to the contractor but needs complete documents first
  4. Transfers less cost risk to the contractor because the owner holds the design and the price

13. A CM advising an owner on which delivery method to select is, functionally, performing:

  1. A purely administrative task with no risk content, since the owner's counsel selects the method
  2. Risk management, since delivery method allocates risk before any contract is signed
  3. Quality assurance
  4. Insurance procurement

14. A force majeure clause drafted before 2020 does not mention epidemics or government-ordered shutdowns. A contractor claims entitlement for a pandemic-related shutdown anyway. The CM's correct first step is:

  1. Refer the question to OSHA
  2. Assume entitlement applies, since force majeure clauses are generic and courts read them broadly to cover any disruption
  3. Deny automatically since epidemics were not contemplated
  4. Read the clause to see what events and mechanisms it defines before advising on entitlement

Glossary

Differing Site Condition (Type I / Type II)
Type I: a condition materially differing from that indicated in the contract documents. Type II: an unknown physical condition of an unusual nature, not ordinarily encountered.
Broad / Intermediate / Limited Form Indemnity
Broad covers the indemnitee's sole negligence (barred in many states); intermediate covers partial negligence; limited covers only the indemnitor's own negligence.
Additional Insured
Status naming another party on a policy so that party's insurer defends and indemnifies directly; coverage depends on the specific endorsement form.
Waiver of Subrogation
Prevents an insurer that paid a loss from suing another project party in its insured's place.
Consequential Damages Waiver
Mutual waiver of indirect losses such as lost profits, lost rent, or loss of use.
Force Majeure
Clause excusing performance for defined events beyond the parties' control; typically grants time, not money.
Anti-Indemnity Statute
State law voiding indemnity provisions that reach beyond a defined limit, most commonly broad-form indemnity.
Risk Allocation Principle
Allocating a given risk to the party best positioned to control, absorb, or price it.