Content current as of September 22, 2026, per the 2026 TxCDBG Project Implementation Manual (effective September 1, 2026) and the current eCFR.
0:00 / --:--
Reading
Lead-based paint rules exist because dust and paint chips from disturbed
old paint poison children, and the poisoning is permanent. For a grantee doing
single family rehabilitation, this is not a side compliance topic. It is one
of the two or three rules that will actually change what work you scope, what
it costs, and how long it takes. Get the tier wrong and you either under
protect an occupant or blow your budget on abatement you never needed.
Lead-based paint obligations rise in three cumulative tiers under 35.930, driven by the lesser of federal assistance or hard rehab cost per assisted unit.
Does the rule apply at all: 24 CFR 35.115
The trigger is the construction date. Housing built on or after
January 1, 1978 is exempt from Part 35, because that is when lead
paint for residential use was banned nationally. Some jurisdictions banned it
earlier, and a local ban date controls if it is earlier than 1978.
Beyond the date test, several other categories are exempt: zero-bedroom
units, including single room occupancy; property where an inspection found no
lead-based paint; property where all lead-based paint was removed and
clearance was achieved; unoccupied property scheduled for demolition;
non-residential portions of a property, other than common passageways;
rehabilitation that does not disturb any painted surface; emergency action
taken to prevent imminent danger; property seized by federal law enforcement
and held under 270 days; emergency or foreclosure prevention
rental assistance expiring within 100 days; exterior work
delayed by unsuitable weather; and, when the State Historic Preservation
Office asks, historic properties doing interim controls in place of abatement.
One exemption is easy to misread, and GCHS will run into it constantly.
Part 35 exempts housing for the elderly, or a residential
property designated exclusively for persons with disabilities, unless a child
under 6 lives there or is expected to live there. But "housing for the
elderly" is a defined term in 35.110: retirement communities or similar housing
reserved for households with one or more persons 62 or older at the time of
initial occupancy. An ordinary house that happens to belong to an elderly
person is not exempt on that basis, and neither is a house
where someone with a disability lives. GCHS serves elderly and disabled
homeowners in older Gulf Coast housing stock, so do not assume an owner
occupied elderly household is out of scope. Even inside a qualifying age
restricted property, the exemption ends when a child under 6 lives there or is
expected to reside there, which the rule defines as actual knowledge that a
child will live in the unit (a resident known to be pregnant counts). Ask the
question at intake.
The three tiers: 24 CFR 35.930
Once you know Part 35 applies, everything else turns on one number: the
amount of federal rehabilitation assistance per unit. The obligations are
built up in layers: testing or presumption and safe work practices run
through every tier, and each higher tier adds duties.
Assistance per unit
What is required
Up to $5,000
Paint testing or presumption;
safe work practices under 35.1350; repair of any disturbed paint; and
clearance after the work. No risk assessment, no interim
controls, no abatement.
Over $5,000 up to $25,000
Paint testing or
presumption; a risk assessment of the units, common areas
and exterior before work starts; interim controls on every
hazard the risk assessment identifies; safe work practices; repair of
disturbed paint.
Over $25,000
Paint testing or presumption;
risk assessment; abatement of all identified hazards; safe
work practices; repair of disturbed paint.
Two narrow exceptions sit inside that table. At the lowest tier, clearance
is not required if the work disturbed no more painted surface area than the
de minimis threshold set in 35.1350(d). At the top tier,
interim controls are acceptable in place of abatement on exterior surfaces
the rehabilitation did not disturb, and on paint-lead hazards that fall below
the de minimis limits. Those limits, in 35.1350(d), are painted surface totals
of no more than 20 square feet on exterior surfaces,
2 square feet in any one interior room or space, or
10 percent of the total surface area of a small component
type such as window sills, baseboards or trim. Also at the lowest tier, if paint
testing shows the disturbed surfaces are not lead-based paint, safe work
practices and clearance are not required.
The pattern to carry into the field: more federal money per unit
means more obligation. Testing or presumption happens at every
tier, no exception. Risk assessment and interim controls start at the
$5,000 line. Full abatement is reserved for the $25,000 line and above.
Calculating assistance per unit: 24 CFR 35.915
This is where programs get the tier wrong, so work through it carefully.
The figure that decides your tier is the lesser of two
numbers: the average federal assistance per assisted unit, or the average
per unit hard costs of rehabilitation.
Federal assistance for this calculation means all federal funds
assisting the project, regardless of what they are used for. That
includes acquisition, construction, permits and fees, not just the line item
you think of as the rehab budget. If more than one federal source touches
the project, all of it counts.
Hard costs, by contrast, exclude the lead work itself:
evaluation, remediation, site preparation, occupant protection, relocation,
interim controls, abatement, clearance and lead waste handling are all left
out of the hard costs figure. The reason is straightforward. If the cost of
complying with Part 35 counted toward the number that decides how much
compliance you owe, a program could get pushed into abatement purely because
abatement itself is expensive. The rule keeps the compliance cost out of the
number that triggers compliance.
Where a project mixes assisted and unassisted units, only the assisted
units go in the numerator for unit-specific costs, and shared costs are
spread across every unit, assisted or not:
per unit hard costs = (unit specific costs divided by number of assisted
units) plus (common area and exterior costs divided by total units in the
project)
Run both the federal assistance figure and the hard costs figure, then use
whichever is lower. That lower number is what you compare against the
$5,000 and $25,000 lines in 35.930.
Notification: 24 CFR 35.125 and 35.130
Three items travel with a job that falls under Part 35 once evaluation or
hazard reduction is done:
A lead hazard information pamphlet (35.130), EPA approved,
unless it has already been delivered to the occupant under the disclosure rule
or the renovation hazard education rule.
A notice of evaluation or presumption, delivered within
15 calendar days of receiving the evaluation report or making
the presumption. It states the nature, dates, scope and results of the
evaluation (or the nature and scope of the presumption), a contact, and the
date.
A notice of hazard reduction, delivered within
15 calendar days of completing the work. It summarizes what
was done, the clearance results, where any lead-based paint remains in the
unit, a contact, and the date. It is not required when no clearance
examination is required.
Both 15 day clocks run from an event, not from the start of the job, so
track them separately from your rehabilitation schedule.
In practice for single family rehabilitation
For a small grantee running owner-occupied rehab, Part 35 shows up on
almost every pre-1978 house you touch. Build the workflow around three
questions, asked in order. First, does an exemption apply, and if the house
is elderly or disability occupied, is a child under 6 present or expected.
Second, once you know Part 35 applies, what is the federal assistance per
unit, calculated as the lesser of total federal assistance and hard costs,
with the lead work itself stripped out of the hard costs side. Third, does
that number land in the $5,000, the $25,000, or above the $25,000 tier,
because that answer tells your contractor whether they are doing clearance
work, interim controls, or abatement, and tells your file what notices are
due and when. Get this sequence wrong and you either expose an occupant to a
hazard you were supposed to fix, or you pay for abatement the file never
required.
Why this matters
The number that decides the tier is the lesser of federal assistance per unit or per unit hard costs, and hard costs deliberately exclude the lead work itself. An exam question that includes lead abatement costs in the hard-cost figure is testing whether you know to leave them out.
Practice questions
1. A GCHS rehab project is scoped for a house built in 1975. What determines whether 24 CFR Part 35 applies?
Whether the house was built before the applicable lead paint ban date, generally January 1, 1978
Whether the homeowner is over 62 years old, because Part 35 protects only elderly occupants and their households
Whether the county has an active TxCDBG contract
Whether the rehabilitation budget exceeds 25,000 dollars
Answer: a. The Part 35 applicability test in 24 CFR 35.115 turns on the construction date. Housing built on or after January 1, 1978 is exempt, or an earlier date if the local jurisdiction banned lead paint sooner. A 1975 house is not exempt on that basis.
2. GCHS is rehabbing a unit in a retirement community reserved for households aged 62 and older, which would ordinarily be exempt under 35.115 as housing for the elderly. Staff learn a resident's 4 year old grandson is expected to move in. Does the exemption still apply?
Yes, because the property is age restricted and that controls regardless of who else lives there
No, the exemption does not apply once a child under 6 lives there or is expected to live there
Yes, as long as the grandson is not yet living there at the time of the site visit
No, but only if the child is under 3 rather than under 6
Answer: b. 24 CFR 35.115 exempts housing for the elderly, which 35.110 defines as retirement communities or similar housing reserved for households with a person 62 or older, unless a child under 6 lives there or is expected to live there. A grandson under 6 who is expected to move in ends the exemption. An ordinary house owned by an elderly person is not covered by this exemption at all.
3. A rehab project provides 4,200 dollars in federal assistance per unit. Which set of requirements applies under 24 CFR 35.930?
Paint testing, a full risk assessment, and interim controls on every identified hazard
Abatement of all identified lead hazards
Paint testing or presumption, safe work practices, repair of disturbed paint, and clearance, with no risk assessment or interim controls required
No lead-based paint requirements apply below 5,000 dollars
Answer: c. 24 CFR 35.930 sets the lowest tier at up to 5,000 dollars in assistance per unit: paint testing or presumption, safe work practices under 35.1350, repair of disturbed paint, and clearance after the work. Risk assessment, interim controls and abatement are not required at this tier.
4. A project provides 15,000 dollars in federal rehabilitation assistance per unit. Under 24 CFR 35.930, what must happen before work starts, in addition to testing and safe work practices?
Full abatement of every identified lead hazard by a certified abatement contractor, with a clearance examination afterward
Nothing beyond what the up to 5,000 dollar tier requires
A risk assessment only, with no requirement to act on what it finds
A risk assessment of the units, common areas and exterior, with interim controls required on every hazard it identifies
Answer: d. 15,000 dollars falls in the over 5,000 to 25,000 dollar tier of 24 CFR 35.930, which requires a pre-work risk assessment of units, common areas and exterior, and interim controls on every hazard the assessment identifies, on top of testing, safe work practices and repair of disturbed paint.
5. A project provides 30,000 dollars in federal rehabilitation assistance per unit. Under 24 CFR 35.930, what does this tier require for identified hazards?
Abatement of all identified lead hazards, along with testing, risk assessment, safe work practices and repair of disturbed paint
Interim controls only, since abatement is reserved for HUD-owned property
Clearance only, since a project above 5,000 dollars has already met its testing threshold and needs no separate evaluation or hazard work
The same requirements as the 5,000 to 25,000 dollar tier, with no additional obligation
Answer: a. 24 CFR 35.930 sets abatement of all identified hazards as the requirement above 25,000 dollars in assistance per unit, layered on top of testing or presumption, risk assessment, safe work practices and repair of disturbed paint.
6. At the up to 5,000 dollar tier, is clearance always required after the work?
Yes, clearance is required at this tier with no exceptions, whatever the amount of painted surface disturbed or the result of paint testing
No, clearance is not required if the work disturbed no more painted surface area than the de minimis threshold in 35.1350(d)
No, clearance is never required below the 25,000 dollar tier
Clearance is optional at every tier and left to grantee discretion
Answer: b. 24 CFR 35.930 carries a narrow exception at the lowest tier: clearance is not required if the work disturbed no more painted surface than the de minimis amount set in 35.1350(d). Outside that exception, clearance is required at the lowest tier.
7. At the over 25,000 dollar tier, is interim controls ever an acceptable substitute for abatement?
Yes, but only if the grantee obtains a written HUD waiver before the rehabilitation work begins
No, abatement of every hazard is required with no exceptions at this tier
Yes, on undisturbed exterior surfaces and on paint-lead hazards below the de minimis limits
Yes, on any surface the contractor chooses, at the grantee's discretion
Answer: c. 24 CFR 35.930 allows interim controls in place of abatement at the top tier only for undisturbed exterior surfaces and for paint-lead hazards below the de minimis limits. All other identified hazards at this tier still require abatement.
8. A single unit project has 22,000 dollars in total federal assistance and 27,000 dollars in hard costs of rehabilitation, after excluding lead work. Under 24 CFR 35.915, which figure decides the tier, and what tier does it fall in?
The greater of the two figures controls, so 27,000 dollars applies, placing the project in the over 25,000 dollar tier
The two figures are averaged, placing the project at 24,500 dollars in the over 25,000 dollar tier
Hard costs are irrelevant to the calculation, so only the 22,000 dollar assistance figure matters
The lesser of the two figures controls, so 22,000 dollars applies, placing the project in the over 5,000 to 25,000 dollar tier
Answer: d. 24 CFR 35.915 defines assistance per unit as the lesser of average federal assistance per unit or average hard costs of rehabilitation per unit. Here that is 22,000 dollars, which falls in the over 5,000 to 25,000 dollar tier under 35.930.
9. A rehab project is funded partly by CDBG and partly by a separate federal home repair grant. For the 35.915 assistance per unit calculation, which costs count as federal assistance?
All federal funds assisting the project, regardless of use, including acquisition, construction, permits and fees
Only the CDBG funds specifically labeled for rehabilitation work in the grant budget, not acquisition, permits or fees
Only funds spent on lead hazard evaluation and remediation
Only the larger of the two federal funding sources
Answer: a. 24 CFR 35.915 defines federal assistance for this calculation as all federal funds assisting the project, regardless of what the funds are used for, not just the amount labeled as the rehabilitation line item. Both federal sources count.
10. When calculating average hard costs of rehabilitation per unit under 24 CFR 35.915, which costs are excluded from the figure?
Permit and inspection fees, contractor overhead, and other hard costs unrelated to lead hazards, whether paid with federal or non-federal funds
Evaluation, remediation, site preparation, occupant protection, relocation, interim controls, abatement, clearance and lead waste handling
General contractor overhead and profit
Nothing is excluded; all rehabilitation costs count toward hard costs
Answer: b. 24 CFR 35.915 excludes the lead work itself from hard costs: evaluation and remediation, site preparation, occupant protection, relocation, interim controls, abatement, clearance and lead waste handling. This keeps compliance costs from pushing a project into a higher compliance tier.
11. A project has three units, only two of which receive federal rehab assistance. Common area and exterior costs total 6,000 dollars. Under the mixed unit formula in 24 CFR 35.915, how are those common costs applied?
Divided only across the two assisted units, ignoring the unassisted unit entirely because it receives no federal funds
Excluded from the per unit hard costs calculation altogether
Divided across all three units in the project, assisted and unassisted alike, and added to the per unit figure
Assigned entirely to whichever single unit had the most rehabilitation work
Answer: c. 24 CFR 35.915 spreads common area and exterior costs across all units in the project, assisted or not, while unit specific costs are counted only for assisted units in the numerator. The formula is unit costs divided by assisted units, plus common and exterior costs divided by total units.
12. After completing a required risk assessment on a GCHS rehab unit, when must the notice of evaluation or presumption go out under 24 CFR 35.125?
Within 30 calendar days of the start of construction
Before construction begins, with no fixed deadline once the contractor has been given the risk assessment report
At closeout, along with the final program file documentation
Within 15 calendar days of receiving the evaluation report or making the presumption
Answer: d. 24 CFR 35.125 requires the notice of evaluation or presumption, with the nature, dates, scope and results, a contact and the date, within 15 calendar days of the date the designated party receives the report or makes the presumption.
13. Under 24 CFR 35.130, what must a grantee deliver to an occupant unless it has already been provided under the disclosure rule or the renovation hazard education rule?
A signed waiver releasing the grantee from further lead-based paint obligations
A copy of the contractor's lead abatement license
An EPA approved lead hazard information pamphlet
A notarized statement of the property's construction date
Answer: c. 24 CFR 35.130 requires delivery of the EPA approved lead hazard information pamphlet, unless the designated party can show it was already provided under the disclosure rule or the renovation hazard education rule. Section 35.910 applies that requirement to federally funded rehabilitation.
14. Under 24 CFR 35.125, when must the notice of hazard reduction go out, and what must it cover?
Within 30 calendar days of the notice of evaluation, summarizing only the contractor's invoice
At closeout only, listing the total project budget
Within 15 calendar days of starting the work, listing the scope of the planned evaluation
Within 15 calendar days of completing the work, summarizing what was done, the clearance results, where any lead-based paint remains, a contact, and the date
Answer: d. The notice of hazard reduction is due within 15 calendar days of completing the work and must summarize what was done, the clearance results, where any lead-based paint remains in the unit, a contact, and the date, a separate 15-day clock from the notice of evaluation or presumption.
Glossary
Clearance
The post-work check confirming a unit is safe for occupancy after lead-based paint work; required at every tier except at the lowest tier when the work stays under the de minimis limits or paint testing shows no lead-based paint.
Risk assessment
An evaluation of units, common areas and the exterior for lead hazards, required before work starts at the over $5,000 tier and above.
Interim controls
Measures that address identified lead hazards without full abatement; required at the middle tier and allowed as a substitute for abatement in narrow circumstances at the top tier.
Abatement
Permanent elimination of identified lead-based paint hazards, required at the over $25,000 tier.
De minimis threshold
The surface-area limit in 35.1350(d) (20 square feet exterior, 2 square feet per interior room, or 10 percent of a small component) below which disturbed paint does not trigger the clearance requirement at the lowest tier.
Paint testing or presumption
The applicability step, required at every tier, of either testing painted surfaces or presuming lead-based paint is present.
Hard costs
Per unit rehabilitation costs used in the 35.915 tier calculation, deliberately excluding the lead work itself so compliance costs cannot push a project into a higher tier.