Lesson 14: Section 504, Section 3 and fair housing
24 CFR Part 8 and 24 CFR Part 75 · 14 practice questions
Content current as of September 22, 2026, per the 2026 TxCDBG Project Implementation Manual (effective September 1, 2026) and the current eCFR.
0:00 / --:--
Reading
Two separate obligations sit under this lesson. Section 3 asks who does
the work, and tries to route CDBG-funded jobs and contracts toward the
low-income people the program is meant to help. Section 504 asks who can use
the housing once it is built or rehabilitated, and requires that people with
disabilities are not shut out of it. They come from different statutes and
different CFR parts, but a grant administrator has to track both on the same
project file.
Section 3 economic-opportunity requirements, Section 504 accessibility, and general fair housing obligations are cross-cutting: they apply on top of, not instead of, everything else in this course.
Section 3, 24 CFR Part 75
Section 3 applies once total housing and community development financial
assistance to a project exceeds $300,000. Below that
threshold, Section 3 does not attach to the project. HUD raised the figure
from $200,000 in a Federal Register notice of February 13, 2026, effective
March 16, 2026 (the threshold for Lead Hazard Control and Healthy Homes
grants moved from $100,000 to $150,000), and 24 CFR 75.3 has HUD update the
thresholds at least every five years. Once a project is covered, the rules
apply to the entire project, whatever mix of funds pays for it.
Once a project is over the threshold, the regulation measures performance
against two safe harbor benchmarks, calculated as a share of total labor
hours on the project, with professional services labor hours
excluded from the calculation entirely:
25 percent or more of total labor hours performed by
Section 3 workers.
5 percent or more of total labor hours performed by
Targeted Section 3 workers.
A caution worth teaching directly: 24 CFR 75.23 does not
itself write the 25 percent and 5 percent figures into the regulatory text.
The regulation says HUD sets the benchmarks in a Federal Register document
and updates them at least every three years. The two percentages above were
set in HUD's Federal Register notice of September 29, 2020 (85 FR 60907), and
HUD's Section 3 Guidebook repeats them. Know the numbers, but know where they
actually live, and check for a newer HUD notice rather than assuming the
figures have not moved.
A Section 3 worker is someone who meets at least one of
three tests: income below the HUD-established limit, employment by a
Section 3 business concern, or participation in YouthBuild.
A Targeted Section 3 worker, for CDBG purposes, is a
Section 3 worker who also meets at least one further condition: working for
a Section 3 business concern, living within one mile of the project site
(with the area widened until it holds 5,000 people if the immediate area is
too small), or participating in YouthBuild.
The reason Section 3 is structured this way is worth explaining to a
learner, not just naming. CDBG money is meant to benefit low- and
moderate-income people directly, and eligible activities alone do not
guarantee that. A project can meet a national objective on paper while every
paycheck it generates goes to workers who live nowhere near the community
being helped. Section 3 closes that gap by asking who is actually hired and
paid, on top of asking who benefits from the finished work. That is also why
the calculation is tracked in labor hours rather than dollars or headcount:
hours are what a payroll record actually proves.
Section 504 of the Rehabilitation Act, 24 CFR Part 8
Section 504 is a civil rights statute. It prohibits disability
discrimination in any program or activity receiving federal financial
assistance, and 24 CFR Part 8 is HUD's implementing rule for housing and
community development programs, including CDBG.
The most demanding standard applies only above a specific size and scope
trigger, called substantial alteration: a project of
15 or more units where the cost of the alterations is
75 percent or more of the replacement cost of the
completed project. Crossing that line pulls the project into the new
construction accessibility standards:
5 percent of total units, or at least one unit,
whichever is greater, must be accessible for persons with mobility
impairments.
An additional 2 percent, but not less than one unit,
must be accessible for persons with hearing or vision impairments.
Below the substantial alteration threshold, a different and lighter
standard applies to other alterations in a multifamily housing project (five
or more units): units must be made accessible
to the maximum extent feasible, which does not require action
that would impose undue financial and administrative burdens. That duty caps
itself once 5 percent of the units in a project are readily accessible to
people with mobility impairments, at which point no further dwelling unit
elements are required. These unit rules (8.22 and 8.23) are written for
multifamily projects, so a scattered site single family job does not run
through them.
Two duties reach every program regardless of project size, and these are
the ones a small grantee actually lives with day to day:
Program accessibility (24 CFR 8.24). Each existing housing
program or activity that receives federal assistance must, viewed in its
entirety, be readily accessible to and usable by individuals with handicaps. This is a
program-level test, not a building-level test. A single rehabilitated house
does not have to be independently accessible in every respect as long as the
program as a whole meets people's needs, but the program cannot functionally
exclude people with disabilities from participating. The duty stops short of
a fundamental alteration of the program or undue financial and administrative
burdens, but then the grantee must find another way to get the benefits to
people with disabilities.
Reasonable accommodation. Part 8 states the duty at 8.11
for applicants and employees with disabilities: reasonable accommodation of
known physical or mental limitations, unless it would impose an undue hardship
on the operation of the program. For homeowners seeking assistance, HUD treats
disability related requests as part of Section 504 and Fair Housing Act
compliance, with the program accessibility limits above. Confirm the current
HUD guidance and the TxCDBG manual for how a request is documented.
Fair housing and affirmatively furthering fair housing
Section 3 and Section 504 sit inside a broader fair housing framework. The
State CDBG rules at 24 CFR 570.487(b) require the State, and each unit of
local government, to certify that it will affirmatively further fair housing
(AFFH), consistent with 24 CFR 5.150 and 5.151.
Those two sections were revised on March 3, 2025 (90 FR 11023). "Fair
housing" now means housing that is affordable, safe, decent, free of unlawful
discrimination, and accessible as required under civil rights laws. To
"affirmatively further" it means to take any action rationally related
to promoting any attribute of fair housing, and a certification is
sufficient if the participant takes such an action in the relevant period. The
older assessment of fair housing process from the 2015 rule is no longer in
the regulation (sections 5.152 through 5.180 are reserved). None of this
relieves a grantee of the Fair Housing Act and other civil rights duties.
In practice for single family rehabilitation
Most GCHS rehab work is scattered site and single family, far below the
five unit line where the Part 8 unit rules (8.22 and 8.23) start to apply and
the 15 unit threshold that triggers the substantial alteration standard. That
trigger will rarely fire on this organization's projects. It does not mean
Section 504 is irrelevant. Program accessibility, nondiscrimination and
reasonable accommodation of known limitations reach every file regardless of
size. If a homeowner discloses a mobility limitation during intake, treat the
request as a Section 504 accommodation question even on a single unit, modest
budget job. On
the Section 3 side, track the $300,000 threshold at whatever project level
your grant agreement defines, and if a project crosses it, be ready to
document labor hours by worker category from the start of construction, not
reconstructed after the fact. Both rules are easiest to satisfy when they
are asked about at intake and bid, not discovered at closeout.
Practice questions
1. A CDBG-funded rehabilitation project has total housing and community development financial assistance of 250,000 dollars. Does Section 3 apply to the project?
No, because Section 3 applies only once total assistance to the project exceeds 300,000 dollars
Yes, Section 3 applies to every CDBG-funded project regardless of dollar amount, as long as any construction labor is involved
Yes, because 250,000 dollars exceeds the 100,000 dollar contract threshold
No, Section 3 only applies to entitlement grantees, never to State CDBG projects
Answer: a. 24 CFR Part 75 sets the Section 3 applicability threshold at total project assistance exceeding 300,000 dollars. At 250,000 dollars, the project falls below that threshold.
2. On a Section 3 covered project, what share of total labor hours must be performed by Section 3 workers to meet the safe harbor benchmark?
10 percent or more of total labor hours
25 percent or more of total labor hours
50 percent or more of total labor hours
5 percent or more of total labor hours
Answer: b. The Section 3 safe harbor benchmark for Section 3 workers is 25 percent or more of total labor hours on the project, as set in HUD's Federal Register benchmark notice under 24 CFR 75.23 (85 FR 60907).
3. What share of total labor hours on a Section 3 covered project must be performed by Targeted Section 3 workers specifically, under the safe harbor benchmark?
25 percent or more of total labor hours
15 percent or more of total labor hours
5 percent or more of total labor hours
1 percent or more of total labor hours
Answer: c. The Targeted Section 3 worker safe harbor benchmark is 5 percent or more of total labor hours, a narrower subset of the broader 25 percent Section 3 worker benchmark.
4. When calculating the Section 3 labor hour benchmarks, how are professional services labor hours treated?
They automatically count toward the Targeted Section 3 worker benchmark
They are counted double because they are higher skilled work
They are included only if performed by a Section 3 business concern
They are excluded from the labor hour calculation
Answer: d. Professional services labor hours are excluded from the Section 3 benchmark calculation, so the 25 percent and 5 percent figures are measured against non-professional labor hours on the project.
5. A construction worker on a Section 3 covered project has household income below the HUD-established limit for the area but does not work for a Section 3 business concern and is not a YouthBuild participant. Does this worker qualify as a Section 3 worker?
Yes, meeting the income test alone is sufficient, since a Section 3 worker needs to meet only one of the three qualifying tests
No, a worker must meet all three tests at once (income, Section 3 business employment and YouthBuild participation) to qualify as a Section 3 worker
No, income alone never qualifies a worker; employment by a Section 3 business concern is required
Yes, but only if the worker also lives within one mile of the project site
Answer: a. A Section 3 worker qualifies by meeting at least one of three tests: income below the HUD-established limit, employment by a Section 3 business concern, or YouthBuild participation. Meeting the income test alone is enough.
6. A worker qualifies as a Section 3 worker and also lives within one mile of a CDBG project site. Does that alone make the worker a Targeted Section 3 worker for CDBG purposes?
No, only employment by a Section 3 business concern can make a worker a Targeted Section 3 worker, no matter where the worker lives
Yes, living within one mile of the site is one of the added conditions that make a Section 3 worker a Targeted Section 3 worker
No, only YouthBuild participants can be Targeted Section 3 workers
Yes, but only if the worker's income also falls below 30 percent of area median income
Answer: b. For CDBG, a Targeted Section 3 worker is a Section 3 worker who also works for a Section 3 business concern, lives within one mile of the project site (widened if needed to reach 5,000 people), or is a YouthBuild participant. Living within one mile satisfies that additional condition.
7. Where do the 25 percent and 5 percent Section 3 safe harbor benchmark figures actually come from?
24 CFR 75.23 itself, which states both percentages directly in the regulatory text and fixes them until Congress changes them
The TxCDBG Implementation Manual, which sets figures that differ from the federal benchmarks for State-funded projects
A HUD Federal Register benchmark notice (85 FR 60907), since 75.23 lets HUD set the figures by notice
Each grantee sets its own benchmark percentages in its citizen participation plan, subject to State approval
Answer: c. 24 CFR 75.23 does not itself contain the 25 and 5 percent figures. It has HUD set benchmarks in a Federal Register document and update them at least every three years. The current figures come from HUD's notice of September 29, 2020 (85 FR 60907), which HUD's Section 3 Guidebook repeats, rather than from the CFR text.
8. A CDBG-assisted rehabilitation project involves 20 units, and the cost of the alterations equals 60 percent of the replacement cost of the completed project. Does the substantial alteration standard under 24 CFR Part 8 apply?
Yes, because the project has 15 or more units, which is enough by itself
Yes, because 60 percent alteration cost exceeds the ordinary maintenance threshold
No, because Section 504 never applies to alterations, only to new construction
No, because substantial alteration requires both 15 or more units and alteration costs of 75 percent or more of replacement cost, and this project is below the 75 percent cost threshold
Answer: d. 24 CFR Part 8 defines substantial alteration as a project of 15 or more units where alteration costs reach 75 percent or more of replacement cost. Both conditions must be met; at 60 percent, this 20 unit project does not cross the substantial alteration line.
9. A project of 40 units triggers the Section 504 substantial alteration standard. Under 24 CFR Part 8, how many units must be accessible for mobility impairments, and how many more for hearing or vision impairments?
At least 2 units accessible for mobility impairments (5 percent of 40), plus at least 1 more unit accessible for hearing or vision impairments (2 percent of 40, rounded up to the 1 unit minimum)
At least 1 unit total, covering both mobility and hearing or vision impairments combined
At least 4 units accessible for mobility impairments and 4 more for hearing or vision impairments
All 40 units must be fully accessible once the substantial alteration threshold is triggered
Answer: a. 24 CFR Part 8's new construction standard requires 5 percent of units, or at least one unit, whichever is greater, accessible for mobility impairments, which is 2 units on a 40 unit project, plus an additional 2 percent, but not less than one unit, accessible for hearing or vision impairments, which rounds up to 1 unit here.
10. A multifamily rehabilitation project of five or more units falls below the Section 504 substantial alteration threshold. What accessibility standard applies instead?
No accessibility standard applies below the substantial alteration threshold, because Part 8 covers only new construction and substantial alterations
Units must be made accessible to the maximum extent feasible, with the duty capping once 5 percent of units in the project are readily accessible
The same 5 percent mobility and 2 percent hearing or vision standard applies regardless of project size
Accessibility becomes optional and is left entirely to grantee discretion
Answer: b. 24 CFR 8.23(b) requires other alterations to multifamily housing, below the substantial alteration threshold, to be made accessible to the maximum extent feasible, and that duty stops once 5 percent of the units in the project are readily accessible to people with mobility impairments.
11. A GCHS rehab program serves scattered single family homes, none individually accessible in every respect. Under the Section 504 program accessibility standard, what is actually being tested?
Whether every single rehabilitated house meets full new construction accessibility standards
Whether the grantee's administrative office building is wheelchair accessible
Whether the program, viewed in its entirety, is readily accessible to and usable by individuals with handicaps, not whether each individual building is independently accessible
Whether the program spent at least 5 percent of its budget on accessibility features
Answer: c. 24 CFR Part 8 states the program accessibility standard as a program-level test: the program or activity, viewed in its entirety, must be readily accessible to and usable by individuals with handicaps. It is not a requirement that every individual unit independently meet full accessibility standards.
12. During intake, a homeowner applying for CDBG-funded rehab discloses a known mobility limitation and asks for a specific accommodation in how the work is scoped. What does Section 504, as HUD implements it in 24 CFR Part 8, expect of the grantee?
No obligation, since reasonable accommodation only applies to projects of 15 units or more
The grantee must grant every requested accommodation exactly as asked, regardless of cost, feasibility or effect on the rest of the program and its other participants
The grantee may deny the request unless the homeowner provides medical documentation
Consider and provide reasonable accommodation for the known limitation, unless it would fundamentally alter the program or impose undue burdens
Answer: d. Part 8 bars disability discrimination in HUD assisted programs (8.4), requires each housing program to be readily accessible to and usable by people with disabilities when viewed in its entirety (8.24), and states the reasonable accommodation duty at 8.11 with an undue hardship limit. Applied to a homeowner's request, the grantee accommodates unless doing so would fundamentally alter the program or impose undue financial and administrative burdens. None of this depends on project size, so it applies to a single unit job too.
13. Under 24 CFR 5.151, as revised in 2025, when is a grantee's certification that it will affirmatively further fair housing sufficient?
Only when the grantee has completed an Assessment of Fair Housing under the 2015 rule and HUD has formally accepted it for the current program year
When the grantee takes, in the relevant period, any action rationally related to promoting one or more attributes of fair housing
Only when the grantee builds new affordable units in a high opportunity area within the program year
Never on its own, because a complaint process in the citizen participation plan replaces the certification
Answer: b. 24 CFR 5.150 and 5.151 (revised March 3, 2025, 90 FR 11023) define fair housing as housing that is affordable, safe, decent, free of unlawful discrimination and accessible as required under civil rights laws, and treat a certification as sufficient if the participant takes any action rationally related to promoting one or more of those attributes. It does not relieve the grantee of other civil rights and fair housing duties.
14. What does Section 504 of the Rehabilitation Act prohibit, and what is HUD's implementing rule for housing and community development programs including CDBG?
Disability discrimination in any program or activity receiving federal financial assistance, implemented at 24 CFR Part 8
Discrimination based on income in the award of CDBG contracts, implemented by HUD at 24 CFR Part 75 and enforced through Section 3 reporting
Discrimination in employment only, with no application to housing programs
Discrimination in citizen participation hearings, implemented at 24 CFR Part 570 Subpart J
Answer: a. Section 504 is a civil rights statute prohibiting disability discrimination in any program or activity receiving federal financial assistance, and 24 CFR Part 8 is HUD's implementing rule for housing and community development programs, including CDBG.
Glossary
Section 3
The 24 CFR Part 75 requirement directing economic opportunities from covered CDBG projects over $300,000 toward low- and very low-income persons.
Section 3 worker
A worker who meets at least one of three tests: income below the HUD-established limit, employment by a Section 3 business concern, or YouthBuild participation.
Targeted Section 3 worker
A Section 3 worker who also works for a Section 3 business concern, lives within one mile of the project site (widened to 5,000 people if needed), or participates in YouthBuild.
Section 504
The civil rights statute, implemented at 24 CFR Part 8, prohibiting disability discrimination in any program or activity receiving federal financial assistance.
Substantial alteration
A project of 15 or more units where alteration costs reach 75 percent or more of replacement cost, triggering new construction accessibility quotas.
Program accessibility
The Section 504 standard requiring a program, viewed in its entirety, to be readily accessible to and usable by individuals with handicaps, without requiring every unit to be independently accessible.
Reasonable accommodation
The Section 504 duty to accommodate known physical or mental limitations (stated at 24 CFR 8.11 for applicants and employees), unless doing so would impose an undue hardship on the program.