Commercial Electrical 100%

2023 NEC Article 230

Lesson 5: Services and Service Disconnects

NEC 230 · 14 practice questions

0:00 / --:--

Reading

The service is where the utility's power becomes the building's power, and every later rule in the installation depends on getting it right. Article 230 covers how many services a building may have, how the conductors are run and how high they must be, where the disconnect goes, how it is rated and protected, and when the service needs ground-fault protection. This lesson walks the service from the pole to the main disconnect. Load calculations are Lesson 4, overcurrent devices are Lesson 6, and grounding of the service is Lesson 7. Local adoption governs which NEC edition applies (see Lesson 1), and the serving utility sets its own metering and meter-base requirements.

Overhead service to a commercial building with clearances, disconnect location, and the ground-fault protection test An elevation shows a utility pole, overhead service conductors, and a commercial building with a meter and a service disconnect on the outside wall. Horizontal reference lines mark 10 feet for walkways and the service entrance, 12 feet for commercial areas without truck traffic at 300 volts or less to ground, and 18 feet for driveways, streets, and truck-traffic parking. Notes say the service disconnect goes outside or inside nearest the point of entrance, never in a bathroom, and must be marked. A three-question box shows that ground-fault protection of equipment is required only when the service is a solidly grounded wye, is over 150 volts to ground, and has a disconnect rated 1,000 amperes or more. The setting may not exceed 1,200 amperes and the delay may not exceed one second at 3,000 amperes or more. Overhead service, not to scale kWh SVC DISC 18 ft: driveways, streets, truck parking 12 ft: commercial, no trucks, 300 V or less 10 ft: walkways, service entrance Service disconnect (230.70) Outdoors, or indoors nearest where the service enters. Readily accessible. Never in a bathroom. Permanently marked. Also: 3 ft from operable windows, doors, stairs (230.9(A)). Over a roof: 8 ft 6 in, held 3 ft from the edge (230.24(A)). Ground-fault protection (230.95) 1. Solidly grounded wye? Such as 208Y/120 V or 480Y/277 V 2. Over 150 V to ground? 208Y/120: 120 V, no. 480Y/277: 277 V, yes 3. Disconnect 1,000 A or more? Rating of the largest fuse or trip setting Three yeses: required Setting no higher than 1,200 A. Opens within 1 second at 3,000 A+. Any single no: not required at the service by this section.
Clearances above grade, where the service disconnect goes, and the three-question test for ground-fault protection. The dashed lines mark minimum heights for the conductors, not the height of the building.

One building, one service

A building or structure is supplied by only one service, unless one of the exceptions in Section 230.2 applies (2023 NEC 230.2). The additional services allowed as special conditions are for fire pumps, emergency systems, legally required standby, optional standby, interconnected power production sources, and systems designed for multiple sources for reliability (230.2(A)). Additional services may be allowed by special permission in a multiple-occupancy building with no room for common service equipment, or in a building large enough to need two or more (230.2(B)). Capacity can also justify another service where the requirement exceeds 2000 A at 1000 V or less (230.2(C)), and different voltages, frequencies, phases, or rate schedules allow additional services (230.2(D)). Where more than one service, feeder, or branch circuit supplies a building, a permanent plaque or directory at each service disconnect location must show the others and the area each serves (230.2(E)).

Each service drop or lateral supplies only one set of service-entrance conductors (230.40), and service conductors may not pass through the interior of another building (230.3).

Overhead conductor clearances

Overhead service conductors may not be readily accessible, and the minimum clearances depend on what is underneath (230.24). Heights are measured from final grade or another accessible surface.

Area under the conductorsMinimum clearance
Service entrance, drip loop, and pedestrian-only areas (cabled on a grounded bare messenger, 150 V or less to ground)10 ft
Residential property and driveways, and commercial areas with no truck traffic, 300 V or less to ground12 ft
The same areas where the voltage to ground exceeds 300 V15 ft
Public streets, alleys, roads, parking areas with truck traffic, and driveways on other than residential property18 ft
Above a roof surface8 ft 6 in, kept 3 ft out from the roof edge

Notice how the commercial lot changes the answer. The same 208Y/120 V service drop over a clinic's customer parking needs 12 ft, and over the delivery lane behind the building it needs 18 ft. A roof over which pedestrians or vehicles travel uses the ground clearances instead of the roof clearance. There are reductions above roofs at 300 V or less between conductors for steeper roofs (4 in 12 or more) and for roof overhangs under stated limits (230.24(A)). Open service conductors and cable without an outer jacket must stay 3 ft from operable windows, doors, porches, balconies, ladders, stairs, and fire escapes (230.9(A)), and overhead conductors may not run beneath openings through which materials are moved, which matters at loading docks (230.9(C)). A service mast may support only the power conductors and must be strong enough or braced (230.28).

Service-entrance conductors

Service conductors must carry the load calculated in Article 220 and have enough mechanical strength (230.23(A)). The overhead minimum size is 8 AWG copper or 6 AWG aluminum or copper-clad aluminum. A smaller conductor, down to 12 AWG hard-drawn copper, is allowed only for limited loads on a single branch circuit, such as a controlled water heater (230.23(B)). Conductor sizing itself is covered in Lesson 8.

Where the service disconnect goes

The building needs a means to disconnect all ungrounded conductors from the service conductors (230.70). It must be at a readily accessible location, either outside the building or inside, nearest the point where the service conductors enter (230.70(A)(1)). It may not be in a bathroom (230.70(A)(2)). Where a remote control device operates the disconnect, the disconnect itself still has to follow the same location rule (230.70(A)(3)). Each service disconnect is permanently marked to identify it as a service disconnect (230.70(B)). The equipment must be marked as suitable for use as service equipment and be listed or field evaluated (230.66(A)). A meter socket is not service equipment, but it must be listed and rated for the service voltage and current (230.66(B)).

How many disconnects

Each service has one disconnecting means, unless the two-to-six rule applies (230.71). Two to six disconnects are allowed for a service. They may be separate enclosures with a main in each, panelboards with a main, metering centers, and similar arrangements (230.71(B)). They must be grouped, and each is marked to show the load it serves (230.72(A)). Disconnects for fire pumps, emergency, and standby services are placed remote from the normal group so one event cannot interrupt both (230.72(B)). In multiple-occupancy buildings each tenant must be able to reach the tenant's own disconnect, except where building management provides service and maintenance under continuous supervision (230.72(C)). Equipment disconnects built into listed equipment for power monitoring, surge protection, and the ground-fault control circuit do not count toward the six (230.71(A)). Where several disconnects are used, their combined rating may not be less than the rating 230.79 requires (230.80).

Rating and protection of the service

The disconnect rating may not be less than the calculated load, and never less than 60 A for an ordinary installation (15 A for one branch circuit, 30 A for two circuits, and 100 A for a one-family dwelling) (230.79). Each ungrounded service conductor needs overload protection at a rating not above the conductor ampacity, where the next-size-up rule of 240.4(B) and the standard ratings of 240.6 may be used (230.90(A)). The service overcurrent device must be built into the disconnect or immediately adjacent to it, and where fuses are used, the disconnect sits ahead of them on the supply side (230.91).

Ground-fault protection of equipment

A solidly grounded wye service of more than 150 V to ground and not over 1000 V phase-to-phase must have ground-fault protection of equipment for each service disconnect rated 1000 A or more (230.95). The rating means the largest fuse that can be installed or the highest continuous trip setting the installed breaker can be adjusted to. It does not apply to a disconnect for a continuous industrial process where an unplanned shutdown creates added hazards. The protection must open all ungrounded conductors of the faulted circuit, with a maximum setting of 1200 A and a maximum delay of one second at ground-fault currents of 3000 A or more (230.95(A)). It must be tested on site by primary current injection, with a written record for the authority having jurisdiction (230.95(C)). It only protects the load side of the sensor, so downstream selectivity should be reviewed.

Worked example: a small community hospital annex has a calculated load of 700 kVA on a 480Y/277 V three-phase service. The current is 700,000 / (1.732 x 480) = 842 A. The disconnect may not be rated below 842 A, and 800 A is the last standard rating below it, so the next standard device is 1,000 A (Table 240.6(A)). The service is a solidly grounded wye at 277 V to ground, which is over 150 V, and the disconnect is 1,000 A, so ground-fault protection is required. Above 800 A the next-size-up rule does not apply, so the conductors must carry at least the device rating (240.4(C)). The same 700 kVA on 208Y/120 V would be 1,943 A. That service is only 120 V to ground, so 230.95 does not apply, but the disconnect would be about 2,000 A, the top of what a single service is normally allowed (230.2(C)(1)).

Surge protection and emergency disconnects

Surge-protective devices are required at services supplying dwelling units, dormitory units, guest rooms and suites of hotels and motels, and patient sleeping areas of nursing homes and limited-care facilities (230.67(A)). They must be part of the service equipment or adjacent, be Type 1 or Type 2, and have a nominal discharge current of at least 10 kA (230.67(B), (C), (E)). An ordinary office or retail building is not on that list. The emergency disconnect in 230.85 is for one- and two-family dwelling units only, so it does not apply to a commercial service.

Key numbers
  • One service per building, with listed exceptions (230.2). Additional services above 2000 A
  • Clearances: 10 ft entrance and pedestrian areas, 12 ft commercial no trucks, 15 ft over 300 V to ground, 18 ft trucks and streets (230.24(B))
  • 8 ft 6 in above roofs, kept 3 ft from the edge. 3 ft from operable windows and doors (230.24(A), 230.9(A))
  • Minimum service conductor: 8 AWG copper or 6 AWG aluminum (230.23(B))
  • Disconnect: outside, or inside nearest the entrance, never in a bathroom, marked (230.70)
  • Up to six disconnects per service, grouped (230.71, 230.72)
  • Ground-fault protection: grounded wye over 150 V to ground, disconnect 1000 A or more. Maximum 1200 A setting, 1 second at 3000 A (230.95)

In the field

A GCHS crew is converting an old warehouse into a small community clinic and rehab office. The utility will feed it overhead from a pole across the rear delivery lane. The inspector stands in the lane and measures the lowest point of the drop against the 18 ft truck-lane line, not the 12 ft line used in the front lot. The main disconnect has been mounted inside a janitor closet that also holds the restroom water heater, so the inspector checks that it is nearest the point of entrance, readily accessible, not in a bathroom, and marked as a service disconnect. The gear nameplate shows 480Y/277 V and a 1,200 A frame with an adjustable trip, so the inspector asks for the ground-fault settings and the written primary-injection test record.

Practice questions

1. A community center with a single-service building adds a fire pump. Under 2023 NEC 230.2(A), is a separate service for the fire pump allowed?

  1. No, a building may never have more than one service under any condition of use
  2. Only if the building's total capacity is more than 2000 amperes
  3. Yes, fire pumps are one of the special conditions in 230.2(A) that allow an additional service
  4. Only if the fire pump sits in a separate detached building

2. A multi-tenant commercial building has no available space for common service equipment for all tenants. Under 230.2(B), how may an additional service be allowed?

  1. Automatically, because every multiple-occupancy building may have one service per tenant
  2. By special permission, because no space exists for common service equipment
  3. Only if each tenant's load exceeds 2000 amperes
  4. Only if all the tenants agree in writing to share one utility meter

3. Overhead 208Y/120 V service conductors cross the rear delivery lane of a commercial building that is used by trucks. What minimum clearance from final grade does 230.24(B) require at the lowest point?

  1. 18 ft
  2. 10 ft, because the voltage to ground is only 120 V
  3. 12 ft, as for commercial areas not subject to truck traffic
  4. 15 ft, as for areas where the voltage to ground exceeds 300 V

4. Overhead 208Y/120 V service conductors pass over the customer parking lot of a small clinic. No trucks use the lot. What minimum clearance applies under 230.24(B)?

  1. 10 ft, as for a pedestrian sidewalk or the service entrance itself
  2. 12 ft, commercial area without trucks at 300 V or less
  3. 15 ft, because a parking lot always needs more clearance than a driveway
  4. 18 ft, because every parking area of any kind needs the public street value

5. A 208Y/120 V service drop cabled with a grounded bare messenger passes over a walkway used only by pedestrians. What minimum clearance from the walkway surface is required?

  1. 8 ft, because pedestrians are shorter than vehicles
  2. 12 ft, which is the residential driveway value
  3. 18 ft, which applies to every walkway near a street
  4. 10 ft

6. Overhead service conductors cross a flat commercial roof that is not used by pedestrians or vehicles. What minimum vertical clearance above the roof surface does 230.24(A) require, and how far from the roof edge is it kept?

  1. 8 ft 6 in above the roof, maintained 3 ft in all directions from the roof edge
  2. 3 ft above the roof surface, maintained 8 ft 6 in out from the roof edge in every direction
  3. 10 ft above the roof, with no separate distance from the roof edge being required
  4. 12 ft above the roof surface, maintained 3 ft away from any roof opening or vent

7. An inspector finds open service conductors installed 18 inches from an operable window on the side of a commercial building. What does 230.9(A) require?

  1. At least 12 inches, so the 18 inch spacing found is acceptable as installed
  2. At least 6 ft, but only for windows located on the upper floors of a building
  3. At least 3 ft from windows that open, so the installation must be moved
  4. Nothing, because clearance to windows applies only to dwelling occupancies

8. A commercial building's service enters on the north wall. Where does 230.70(A)(1) allow the service disconnect to be installed?

  1. Anywhere in the building, as long as it is on the same floor as the panelboards it feeds
  2. At a readily accessible location, either outside the building or inside nearest the point of entrance
  3. Only outdoors on the exterior wall, and never anywhere inside the building at all
  4. Inside the building, but only at the far end of the main corridor from the entrance

9. During a rehab of a two-story office, the electrician proposes mounting the main disconnect inside the first-floor restroom, since it is nearest where the conduit comes in. What does 230.70(A)(2) say?

  1. It is allowed if the restroom has a lockable door
  2. It is allowed if the disconnect is more than 3 ft from a sink
  3. It is allowed if the disconnect is listed as wet-location equipment
  4. Service disconnecting means may not be installed in bathrooms

10. A main breaker in a new office building has no label at all. Which requirement of 230.70(B) is not met?

  1. It must carry a label that names the electrical contractor who installed it and the date
  2. It must show the date it was installed and the name of the contractor or inspector
  3. It must be permanently marked to identify it as a service disconnect
  4. It must be painted red so the fire department can find it from the street

11. A strip center owner wants seven separate tenant service disconnects grouped on one service. What does 230.71(B) allow?

  1. Two to six per service, so seven is over the limit
  2. Any number of disconnects, as long as they are grouped and each one is marked
  3. Up to twelve, provided that each tenant has its own utility meter installed
  4. Up to eight, as long as the service is rated over 800 amperes in total

12. A 480Y/277 V three-phase service has a main breaker that is adjustable up to 1,200 A. Does 230.95 require ground-fault protection of equipment?

  1. No, ground-fault protection is required only for services larger than 2000 amperes
  2. Yes, a grounded wye over 150 V to ground with a disconnect rated 1000 A or more
  3. No, because every commercial service is exempt from ground-fault protection rules
  4. Yes, but only if the service uses a delta secondary instead of a grounded wye

13. A hotel laundry building has a 208Y/120 V three-phase service with a 2,000 A main disconnect. Does 230.95 require ground-fault protection of equipment at the service?

  1. Yes, because any disconnect of 1000 A or more needs it
  2. Yes, because the service is a solidly grounded wye
  3. No, because ground-fault protection is required only for delta services
  4. No, because the voltage to ground is 120 V, which is not over 150 V

14. Which ground-fault protection setting complies with 230.95(A) on a 480Y/277 V, 1,200 A service disconnect?

  1. A pickup of 1,000 A with a delay that opens within 1 second at 3,000 A or more
  2. A pickup of 1,400 A with no intentional delay at any level of ground-fault current
  3. A pickup of 1,200 A with a delay of up to 2 seconds at 3,000 A of fault current
  4. A pickup of 1,500 A with a delay of 1 second at ground-fault current of 3,000 A

Glossary

Service
The conductors and equipment that deliver electric energy from the utility to the wiring system of the premises.
Service drop
The overhead conductors between the serving utility and the service point.
Service disconnecting means
The device or group of devices used to disconnect all ungrounded conductors of the building from the service conductors.
Drip loop
A downward loop in service conductors just outside the weatherhead so water drips off before entering the raceway.
Solidly grounded wye
A three-phase system, such as 208Y/120 V or 480Y/277 V, whose neutral point is connected directly to ground.
Ground-fault protection of equipment
A system that opens the service disconnect on a ground-fault current, required on certain high-current wye services (230.95).
Primary current injection
The field test that sends real current through the sensing equipment to prove the ground-fault system trips as set.
Surge-protective device
A device that limits transient voltage; required at the service for dwellings, dormitories, hotel guest rooms, and nursing home sleeping areas.