Commercial Electrical 100%

2023 NEC Article 240

Lesson 6: Overcurrent Protection

NEC 240 · 14 practice questions

0:00 / --:--

Reading

Overcurrent protection does two jobs. It protects each conductor at a rating tied to that conductor's ampacity, and it sits at the point where the conductor receives its supply. Article 240 sets both rules and then lists the exceptions, and the exceptions are where inspectors spend their time: the next-size-up rule, the small-conductor limits, and the tap rules. This lesson covers all three, plus where the devices may be mounted. Ampacity itself is Lesson 8, feeder sizing is Lesson 4, and the service overcurrent device is Lesson 5. Local adoption governs which NEC edition applies (see Lesson 1).

Feeder tap rules for a 400 ampere feeder: the 10 foot tap and the 25 foot tap A 400 ampere feeder overcurrent device supplies a feeder. A 10 foot tap runs in a raceway to a panelboard; its ampacity must cover the load and the panel device rating, and at least one-tenth of 400 amperes, which is 40 amperes, if it leaves the enclosure. A 25 foot tap must have ampacity of at least one-third of 400 amperes, which is 133 amperes, so 1/0 AWG copper at 150 amperes, and must end at a single 150 ampere breaker with the conductors protected from physical damage. The next-size-up rule of 240.4(B) may not be used for taps, so a 130 ampere tap cannot use a 150 ampere breaker. 10 ft tap (240.21(B)(1)) 25 ft tap (240.21(B)(2)) Feeder 400 A 10 ft or less, in a raceway Panel or switchboard Ampacity at least the calculated load, and the panel device rating. If it leaves the enclosure: 400 / 10 = 40 A minimum. Does not extend beyond the equipment it supplies. 25 ft or less 150 A Panel loads Ampacity at least one-third of 400 A 400 / 3 = 133 A, so 1/0 AWG copper (150 A at 75 C). 1 AWG is only 130 A. Ends at one breaker, 150 A or less. Protected from physical damage. That breaker may feed any number of devices. Next-size-up rule (240.4(B)): feeders yes, taps no Feeder: 130 A conductor (1 AWG) may use a 150 A breaker. Tap: the device may not exceed the tap ampacity, so 115 A conductors take 110 A, never 125 A. Not to scale. A tap may start at any point on the load side of the feeder overcurrent device.
Both feeder tap rules drawn for a 400 A feeder, with the minimum tap ampacity worked out for each. The next-size-up rule stops at the tap.

Protect the conductor at its ampacity

The starting rule is that conductors, other than flexible cords, flexible cables, and fixture wires, are protected against overcurrent at their ampacity from Section 310.14, unless 240.4(A) through (H) say otherwise (2023 NEC 240.4). One exception is a circuit where opening would create a hazard, such as a fire pump circuit, which needs short-circuit protection but not overload protection (240.4(A)). Tap conductors follow 240.21 (240.4(E)), and the transformer secondary rule is covered below (240.4(F)).

Standard ampere ratings

Fuses and inverse time circuit breakers come in the standard ratings of Table 240.6(A): 10, 15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, 100, 110, 125, 150, 175, 200, 225, 250, 300, 350, 400, 450, 500, 600, 700, 800, 1000, 1200, 1600, and 2000 A, continuing upward. Fuses also come in 1, 3, 6, and 601 A. Notice what is not on the list: 65 A and 75 A. A conductor whose ampacity is 65 A does not line up with any device, and that gap is exactly what the next-size-up rule fills.

The next-size-up rule

Where the overcurrent device is rated 800 A or less, the next higher standard rating above the conductor ampacity may be used if all three conditions are met (240.4(B)). First, the conductors are not part of a branch circuit supplying more than one receptacle for cord-and-plug portable loads. Second, the conductor ampacity does not match a standard rating. Third, the next standard rating does not exceed 800 A. Ampacity here is the value after the adjustments covered in Lesson 8.

Copper conductor at 75 CAmpacityLargest device permitted by 240.4(B)
6 AWG65 A70 A
4 AWG85 A90 A
3 AWG100 A100 A (already standard)
2 AWG115 A125 A
1 AWG130 A150 A

The rule is a permission, not a requirement, and it does not lift other limits. A 65 A conductor on a row of receptacles for bench tools may not go on a 70 A device, because that circuit supplies more than one receptacle for portable loads, and without the round-up the device may not exceed the 65 A conductor ampacity, so the largest standard rating is 60 A. Above 800 A, there is no round-up: the conductor ampacity must be at least the device rating (240.4(C)). A 1,000 A breaker needs conductors that carry 1,000 A, not 920 A.

Small conductors

For small conductors, the overcurrent protection may not exceed the limits in 240.4(D), after any correction and adjustment factors have been applied. For copper: 18 AWG at 7 A, 16 AWG at 10 A, 14 AWG at 15 A, 12 AWG at 20 A, and 10 AWG at 30 A. For aluminum and copper-clad aluminum: 12 AWG at 15 A and 10 AWG at 25 A. The 18 and 16 AWG limits carry extra conditions on continuous load and on the listing of the device. These limits explain why a 12 AWG copper branch circuit tops out at a 20 A breaker even where its table ampacity at 90 C is higher.

Location in the circuit and taps

Overcurrent protection goes in each ungrounded conductor at the point where the conductors receive their supply, except in the cases 240.21(A) through (H) list (240.21). A tap is a conductor connected to a feeder without its own overcurrent device at the connection. Taps are allowed only in specific forms, and 240.4(B) may not be used for tap conductors (240.21(B)).

The 10 ft tap: if the tap is 10 ft or less, its ampacity must be at least the calculated load it serves and at least the rating of the equipment or device it ends in. It must not extend beyond the equipment it supplies. It must be enclosed in a raceway from the tap to the enclosure. If it leaves the enclosure or vault where the tap is made, its ampacity must be at least one-tenth of the rating of the feeder overcurrent device (240.21(B)(1)).

The 25 ft tap: if the tap is 25 ft or less, its ampacity must be at least one-third of the rating of the feeder overcurrent device. It must end in a single circuit breaker or set of fuses that limits the load to the ampacity of the tap conductors, and that device may feed any number of other devices. The conductors must be protected from physical damage (240.21(B)(2)). A transformer tap allows one primary plus one secondary conductor of up to 25 ft combined (not counting any primary portion protected at its ampacity), with a primary ampacity of one-third and a secondary of at least the voltage ratio times one-third of the feeder device (240.21(B)(3)). Outside taps of unlimited length must end in a single device at a disconnect that is readily accessible outdoors or nearest the entrance (240.21(B)(5)). Taps longer than 25 ft indoors are limited to high-bay manufacturing buildings over 35 ft high (240.21(B)(4)).

Worked example: taps from a 400 A feeder

A 400 A feeder passes a new 125 A panelboard 8 ft away in the same electrical room. A 10 ft tap can feed it. The tap must carry the 125 A load and the 125 A rating of the panel's main, so 1 AWG copper at 75 C (130 A) works. If the tap leaves the enclosure where it is made, the one-tenth test gives 400 / 10 = 40 A, which 130 A easily exceeds. Now a second panelboard is 22 ft away, so only a 25 ft tap can reach it, and the one-third test gives 400 / 3 = 133 A. The same 1 AWG conductor at 130 A now falls short, so the smallest choice is 1/0 AWG copper at 150 A. That tap ends at a single 150 A breaker ahead of the panel. A designer who keeps 1 AWG and adds a 150 A breaker cites 240.4(B), but taps may not use the next-size-up rule, and 130 A is below the one-third minimum in any case.

Transformer secondaries and where devices go

Secondary conductors of a transformer, other than single-phase 2-wire secondaries and 3-wire delta-delta secondaries, are not protected by the primary device (240.4(F)). The 10 ft secondary rule in 240.21(C)(2) has the same style of conditions as the 10 ft tap, and 240.4(B) may not be used there either. Industrial 25 ft secondaries are limited to switchgear or switchboards in industrial installations (240.21(C)(3)). Under Section 240.24, breakers and fused switches must be readily accessible with the center of the operating handle grip, in its highest position, not over 6 ft 7 in above the floor or working platform (240.24(A)). Each occupant needs ready access to the devices protecting that occupancy, with limited management exceptions (240.24(B)). Devices must not be exposed to physical damage (240.24(C)), must not be near easily ignitible material such as in clothes closets (240.24(D)), may not be in bathrooms, showering facilities, or locker rooms with showers (240.24(E)), and may not be over steps of a stairway (240.24(F)).

Interrupting rating and arc energy

A device must have an interrupting rating at least equal to the available fault current at its line terminals (110.9), and Lesson 2 covers the required marking of that current. Series-rated combinations must be selected by a licensed professional engineer, documented, and field marked in existing installations (240.86(A)), or be a tested combination marked on the equipment (240.86(B)). Where a circuit breaker's highest continuous trip setting can be 1200 A or higher, 240.87 requires documentation of the breaker locations and a method to reduce clearing time, such as zone-selective interlocking or an arc-energy reduction maintenance switch.

Key numbers
  • Standard ratings include 60, 70, 80, 90, 100, 110, 125, 150, 175, 200 A. There is no 65 A or 75 A (Table 240.6(A))
  • Next-size-up: 800 A or less, not for a circuit with more than one receptacle for portable loads (240.4(B))
  • Over 800 A: conductor ampacity at least the device rating (240.4(C))
  • Copper small conductors: 14 AWG 15 A, 12 AWG 20 A, 10 AWG 30 A (240.4(D))
  • Tap 10 ft or less: one-tenth of the feeder device if it leaves the enclosure (240.21(B)(1))
  • Tap 25 ft or less: one-third of the feeder device, single device at the end (240.21(B)(2))
  • No next-size-up for taps or transformer secondary conductors (240.21(B), (C))
  • Breaker handle no higher than 6 ft 7 in (240.24(A)). Arc energy reduction at 1200 A and up (240.87)

In the field

A GCHS inspector walks a small church's fellowship hall addition. A 400 A feeder panel is on the wall, and a new sub-panel sits about 20 ft away, fed by conductors spliced into the feeder lugs with no breaker at the splice. That is a tap, so the inspector asks for the tap length, the ampacity of the conductors, and what protects them at the far end. Conductors that are shorter than 25 ft but carry only 115 A fail the one-third rule of 133 A. The same visit turns up a panel in a coat closet and a breaker whose handle is 7 ft off the floor, both violations of 240.24.

Practice questions

1. A feeder to a panelboard in a Group B building uses 6 AWG copper conductors with a 65 A ampacity at 75 C. It is not a branch circuit. What is the largest standard overcurrent device 240.4(B) allows?

  1. 65 A, because devices may be rated at the exact ampacity of the conductor
  2. 80 A, which is two standard sizes above the ampacity
  3. 75 A, which is the next rating that is a multiple of 5
  4. 70 A, the next standard rating above the 65 A conductor ampacity

2. A feeder uses 1 AWG copper conductors with a 130 A ampacity at 75 C, and the ampacity does not match a standard device rating. What is the largest overcurrent device the next-size-up rule allows?

  1. 150 A, the next standard rating above 130 A
  2. 125 A, because the device may never be above the conductor ampacity
  3. 175 A, because two sizes up is allowed above 100 A
  4. 130 A, because a device may be set at any nonstandard value

3. An electrician wires a row of receptacle outlets for bench tools with 6 AWG copper (65 A) and protects it with a 70 A breaker. Under 240.4(B)(1), what is the problem?

  1. No problem at all, because 70 A is the next standard size above the 65 A ampacity
  2. More than one receptacle for portable loads, so the largest standard device is 60 A
  3. The breaker must be 100 A, because receptacle circuits need an extra margin above ampacity
  4. The circuit must have a 125 A breaker so that it can carry the whole receptacle load

4. 12 AWG aluminum conductors are used for a 120 V branch circuit in a small office. What is the maximum overcurrent protection under 240.4(D)?

  1. 20 A, the same as 12 AWG copper
  2. 25 A, the same as 10 AWG aluminum
  3. 15 A, the limit for 12 AWG aluminum and copper-clad aluminum
  4. 30 A, the same as 10 AWG copper

5. A circuit in a community center kitchen uses 10 AWG copper conductors, with no correction or adjustment factors needed. What is the maximum overcurrent protection under 240.4(D)?

  1. 30 A
  2. 25 A, the 10 AWG aluminum limit
  3. 35 A, the next size above the 30 A table ampacity
  4. 40 A, the 90 C table ampacity of 10 AWG copper

6. A 1,000 A overcurrent device on a commercial feeder is proposed with two parallel sets that together have a 920 A ampacity. What does 240.4(C) say?

  1. It is permitted, because the next-size-up rule applies at any rating of overcurrent device
  2. Not permitted, since above 800 A the ampacity must be at least the device rating
  3. It is permitted, because 920 A is over 90 percent of the 1,000 A device rating
  4. It is permitted, because parallel conductors are exempt from 240.4 entirely

7. A 400 A feeder has a 10 ft tap to a panel, and the tap conductors leave the enclosure where the tap is made. What minimum ampacity does the one-tenth rule of 240.21(B)(1) set for the tap, apart from the load?

  1. 133 A, which is one-third of the 400 A feeder device rating
  2. 80 A, which is one-fifth of the 400 A feeder device rating
  3. 40 A, which is one-tenth of the 400 A feeder device
  4. 400 A, the same as the full rating of the feeder device itself

8. A 25 ft tap is made from a 400 A feeder. What is the smallest copper conductor, using the 75 C column, that meets the one-third rule of 240.21(B)(2)?

  1. 1 AWG, at 130 A
  2. 1/0 AWG copper, which carries 150 A at 75 C
  3. 2 AWG, at 115 A
  4. 3/0 AWG, at 200 A

9. An electrician wants to tap a 400 A feeder with conductors 30 ft long inside an office building and end them at a panelboard. Does 240.21(B) allow it?

  1. No, indoor taps over 25 ft are limited to high-bay manufacturing buildings
  2. Yes, any tap up to 50 ft is allowed as long as it is installed in conduit
  3. Yes, provided the tap conductors are the same size as the feeder conductors
  4. Yes, provided the panelboard has a main breaker of any ampere size at the end

10. A 300 A feeder has a 25 ft tap of 2 AWG copper (115 A), which meets the one-third minimum of 100 A. The designer ends the tap in a 125 A breaker, citing 240.4(B). What is the problem?

  1. There is no problem, because 125 A is the next standard size above the 115 A ampacity
  2. Taps may not use next-size-up, so the largest standard breaker is 110 A
  3. The breaker must be exactly 100 A, which is the one-third minimum figure itself
  4. The breaker must be 150 A so that it matches the rating of the feeder device

11. Which condition is required for an outside tap of unlimited length under 240.21(B)(5)?

  1. The tap may be no longer than 100 ft, measured from the feeder connection point
  2. The tap must be protected by the primary device of an upstream transformer
  3. The tap must be located in a high-bay building over 35 ft high at the walls
  4. It ends at a single device limiting the load to the tap ampacity

12. An inspector finds the center of the grip of a circuit breaker handle, in its highest position, at 7 ft 2 in above the floor of a commercial kitchen panelboard. Which rule is violated?

  1. 240.24(A), since the grip center may not exceed 6 ft 7 in above the floor
  2. 240.24(E), because panelboards may never be installed in commercial kitchens
  3. 240.4(B), because the breaker installed there is not a standard rating
  4. None, because 7 ft 2 in is within the normal reach range for an electrician

13. During a rehab of a community center, an electrician mounts a new panelboard inside the coat closet of the front office. Which rule does this conflict with?

  1. 240.24(A), which limits an office building to one panelboard on each floor of the building
  2. 240.6(A), which limits the ampere rating of any panelboard installed in an office space
  3. 240.24(D), which keeps devices away from easily ignitible material such as clothes closets
  4. 240.87, which requires a separate room for every panelboard installed in a building

14. A panelboard in a church annex has 22,000 A of available fault current at its line terminals, and its breakers are marked 10,000 A interrupting rating. What do 110.9 and 240.86 require?

  1. Nothing further, since 10,000 A is the standard interrupting rating for every branch circuit breaker in use
  2. Nothing further, provided the panelboard has a main breaker of any ampere size ahead of the branch breakers
  3. Only a label showing the available fault current, because a label satisfies the interrupting rating rule
  4. Devices rated at least 22,000 A, or a properly selected series-rated combination

Glossary

Ampacity
The maximum current a conductor can carry continuously under the conditions of use without exceeding its temperature rating.
Overcurrent device
A fuse or circuit breaker that opens the circuit when current exceeds its rating.
Standard ampere rating
A rating listed in Table 240.6(A), such as 60, 70, 100, 125, or 150 A. Ratings like 65 A and 75 A are not on the list.
Next-size-up rule
The 240.4(B) permission to use the next higher standard device above a conductor's ampacity, for devices of 800 A or less, with conditions.
Feeder tap
A conductor connected to a feeder without its own overcurrent device at the connection, allowed only in the forms of 240.21(B).
Interrupting rating
The highest fault current a device can safely open at its rated voltage; it must equal or exceed the available fault current (110.9).
Series rating
A tested pairing of an upstream and downstream device that lets the downstream breaker be used above its own interrupting rating (240.86).
Arc energy reduction
The 240.87 requirement for a method to shorten clearing time on breakers with a trip setting of 1200 A or higher.