Commercial Energy 100%

2021 IECC Commercial Provisions

Lesson 14: Inspections, Tests, and Course Review

IECC C105, C402.5, C403.12, C408 and course review · 20 practice questions

0:00 / --:--

Reading

Thirteen lessons have taught what the 2021 IECC commercial provisions require. Two things prove that a finished building meets them. Inspections say who looks, at what point, and what must stay uncovered until they do. Tests and verifications say how a tight envelope, tight ducts, working controls and commissioned equipment are shown rather than assumed. Section C105 sets the inspections, and Sections C402.5, C403.12, C408 and C401.3 set the tests, verifications and paperwork. Local adoption governs: Lesson 1's dated check found that Houston enforces the 2021 IECC with Houston amendments, so confirm the adopted edition and any local test rule before you write a correction. This lesson teaches the inspections and tests, then reviews the whole course.

Timeline of the six energy inspections listed in Section C105.2 A six-step vertical timeline in the usual field order. One, footing and foundation insulation (C105.2.1): R-value, location, thickness, depth of burial and protection of the insulation. Two, thermal envelope (C105.2.2): insulation type, R-values and location, fenestration U-factor, SHGC and VT, and air leakage controls properly installed. Three, plumbing (C105.2.3): pipe insulation type, R-values, protection, controls and heat traps. Four, mechanical (C105.2.4): equipment type and size, controls, insulation and R-values, system and damper air leakage, fan efficiency, energy recovery and economizer. Five, electrical (C105.2.5): lighting system controls, components and meters. Six, final (C105.2.6): proper operation of all required building controls and documentation that Section C408 commissioning was carried out. A note box lists the tests and reports that feed these inspections: air barrier verification or fan testing, leak testing of duct designed for 3 inches w.g. or more, the Preliminary Commissioning Report before final, and lighting controls testing before final. 1 Footing and foundation insulation C105.2.1 R-value, location, thickness, depth of burial and protection of the insulation, against the approved plans and specifications 2 Thermal envelope C105.2.2 Insulation type, R-values and location; fenestration U-factor, SHGC and VT; air leakage controls properly installed 3 Plumbing C105.2.3 Type of insulation, R-values, protection required, controls and heat traps 4 Mechanical C105.2.4 Equipment type and size, controls, insulation and R-values, system and damper air leakage, fan efficiency, energy recovery, economizer 5 Electrical C105.2.5 Lighting system controls, components and meters 6 Final C105.2.6 Proper operation of all required building controls, and documentation that Section C408 commissioning activities have been carried out Tests and reports that feed these inspections Air barrier: verified during construction, or fan tested (C402.5.1.5, C402.5.2, C402.5.3) Duct designed for 3 in. w.g. or more: leak test, CL 4.0 or less, 25 percent of duct area (C403.12.2.3) Preliminary Commissioning Report before final (C408.2.4.1); lighting controls tested before final (C408.3.1)
The code lists six inspections and sets no calendar order; this is the usual order in the field. Each item is checked while it can still be seen and fixed.

The six inspections (C105.2)

Section C105.2 names six inspections, made by the code official, a designated agent or an approved agency once the permit holder gives notice. Footing and foundation insulation (C105.2.1) checks the insulation's R-value, location, thickness, depth of burial and protection. Thermal envelope (C105.2.2) checks insulation type, R-values and location, fenestration U-factor, SHGC and VT, and that air leakage controls are properly installed. Plumbing (C105.2.3) checks pipe insulation and its protection, controls and heat traps. Mechanical (C105.2.4) checks equipment type and size, controls, insulation and R-values, system and damper air leakage, fan efficiency, energy recovery and the economizer. Electrical (C105.2.5) checks lighting controls, components and meters. The final inspection (C105.2.6) confirms that all required building controls work and that documentation shows the commissioning of Section C408 was done. The code lists the six but does not set a calendar order. The figure shows the order they usually fall in the field, and the reason is practical: an item is inspected while it can still be seen and fixed.

Keeping work open, and what a failure means (C105.1, C105.3 to C105.6)

Permitted work stays visible and accessible until it is approved, and keeping it that way is the permit applicant's duty (C105.1). Neither the code official nor the jurisdiction is liable for the cost of removing or replacing material to allow inspection, so the cost of opening a closed wall lands on the project. Approval after an inspection is never approval of a violation. The permit holder tells the code official when work is ready and provides access and means for inspection (C105.5). Work that fails is corrected and resubmitted for inspection and testing (C105.6), and a building is reinspected wherever the code official finds it necessary (C105.3). The code official may accept reports from third-party agencies that are not affiliated with the design or construction and are approved for qualifications and reliability (C105.4).

Air barrier: verify it or test it (C402.5)

Section C402.5 lets the envelope comply by meeting the air barrier provisions or by passing a test, and a building that complies by testing must still meet the damper, loading dock and vestibule sections (C402.5.7 to C402.5.9). Inside the air barrier path, C402.5.1.2 decides who tests. Group R and I buildings go to enclosure testing of units (C402.5.2), with exceptions only for Zones 2B, 3C and 5C. Other groups go to a whole-building test (C402.5.3), with exceptions for Zones 2B, 3B, 3C and 5C, for buildings larger than 5,000 square feet in Zones 0B, 1, 2A, 4B and 4C, and for buildings from 5,000 to 50,000 square feet in Zones 0A, 3A and 5B. In Houston (Zone 2A) that means a building outside Group R and I that is larger than 5,000 square feet is excepted, and one of 5,000 square feet or less is tested. A building or portion that does not complete testing meets the materials path (0.004 cfm per square foot or less at 75 Pa, C402.5.1.3) or the assemblies path (0.04 or less, C402.5.1.4), and also the verification in C402.5.1.5. There the code official, a registered design professional or an approved agency reviews the drawings and inspects the air barrier during construction while it can still be reached and repaired. If a design professional or agency did the inspecting, a final commissioning report listing deficiencies and corrections goes to the owner and the code official. These exceptions interlock, so ask the code official which path a project is using.

Air leakage test numbers (C402.5.2 and C402.5.3)

A dwelling or sleeping unit is tested separately with an unguarded blower door at 50 Pa (0.2 inch water gauge) and may leak no more than 0.30 cfm per square foot of unit enclosure area. The building result is the average of the unit results weighted by enclosure area. With fewer than eight units, every unit is tested. With eight or more, the greater of seven units or 20 percent is tested, including a top-floor unit, a ground-floor unit and the unit with the largest enclosure, and each tested unit over the limit adds two more units of mixed type and location (C402.5.2). A whole-building test is limited to 0.40 cfm per square foot of envelope area at 75 Pa (0.3 inch water gauge). A designer may instead test portions and area-weight the results, but the portions must include every story with any space directly under a roof, every story with an entrance, exposed floor or loading dock or that is below grade, and representative above-grade sections totaling at least 25 percent of the wall area around the remaining conditioned space. A result over 0.40 and not over 0.60 is handled by a diagnostic evaluation with smoke tracer or infrared imaging while the building is pressurized, a visual inspection, sealing of the leaks that can be sealed without destroying existing components, and an extra report to the code official and owner. That is deemed to comply (C402.5.3). Window and door leakage is a different kind of check: a lab tests it and the maker labels it (Table C402.5.4), so in the field it is read from the label.

Worked example. A Group B clinic in Houston (Zone 2A) is 4,200 square feet, which is not larger than 5,000, so it is tested unless it takes the materials or assemblies path. Its envelope area is 11,500 square feet, so the limit is 0.40 x 11,500 = 4,600 cfm at 75 Pa. A reading of 4,000 cfm is 0.35 and passes. A reading of 5,750 cfm is 0.50, over 0.40 but not over 0.60, so the diagnostic route applies. A reading of 7,200 cfm is 0.63, over 0.60, so the leaks are sealed and the building is retested. For a four-story R-2 building, 30 units means 20 percent is 6, which is less than 7, so 7 units are tested. With 45 units, 20 percent is 9, so 9 are tested.

Key numbers: tests and inspections
  • Six inspections: footing and foundation insulation, thermal envelope, plumbing, mechanical, electrical, final (C105.2.1 to C105.2.6). Work stays open until approved (C105.1)
  • Unit test: 0.30 cfm per square foot of unit enclosure at 50 Pa; 8 or more units test the greater of 7 or 20 percent (C402.5.2)
  • Whole-building test: 0.40 cfm per square foot of envelope at 75 Pa; over 0.40 up to 0.60 takes the diagnostic route (C402.5.3)
  • Zone 2A: a building outside Group R and I larger than 5,000 square feet is excepted from the whole-building test (C402.5.1.2)
  • Duct at 3 in. w.g. or more: leak test to CL 4.0 or less on sections totaling at least 25 percent of duct area (C403.12.2.3)
  • Commissioning exempt under 480,000 Btu/h cooling and under 600,000 Btu/h combined heating; Preliminary Commissioning Report before final; final documents within 90 days of the certificate of occupancy (C408.2)
  • Occupant sensors: 7 or fewer test each; more test at least 10 percent of each combination, never fewer than one; 30 percent failing means test all remaining (C408.3.1.1)

Duct leakage tests (C403.12.2)

Ducts are built as the International Mechanical Code says, and what must be sealed or tested depends on the design static pressure, which the drawings must show. At 2 inches w.g. or less, joints and seams are fastened and sealed with welds, gaskets, mastics, mastic-plus-fabric systems or tapes used as the maker directs (C403.12.2.1). Above 2 and below 3 inches, ducts are insulated and sealed as C403.12.1 requires (C403.12.2.2). At 3 inches w.g. or more, the duct is also leak tested with the SMACNA duct leakage manual and must show a leakage class CL of 4.0 or less, worked out from the measured leakage and the test pressure. Documentation must show that representative sections totaling at least 25 percent of the duct area were tested and that every tested section passed (C403.12.2.3). The mechanical inspection also verifies system and damper air leakage (C105.2.4). Most duct in small commercial buildings is low pressure, so the usual field check is a sealed joint, and a test is expected on the high-pressure part of a large system. Example: a Group B building has 4,800 square feet of duct designed for 3.5 inches w.g. At 25 percent, sections totaling 1,200 square feet are tested, and each must reach CL 4.0 or less.

Commissioning and functional tests (C408.2)

Before the final mechanical and plumbing inspections, a registered design professional or approved agency provides evidence that mechanical and service water-heating systems were commissioned (C408.2). Two exceptions apply: buildings whose total capacity is under 480,000 Btu/h of cooling and under 600,000 Btu/h of combined service water and space heating, and economizer systems that serve individual dwelling or sleeping units. Both totals must be under their limits, so a clinic with 300,000 Btu/h of cooling and 400,000 Btu/h of heating is exempt, and adding 200,000 Btu/h of cooling removes the exemption. A commissioning plan comes first (C408.2.1). Air systems and hydronic coils are balanced, and discharge dampers may not be used to balance constant-volume fans or variable-volume fans with motors of 10 hp and larger (C408.2.2.1). Functional performance tests then show that equipment works in every mode of the sequence of operation, at full and part load, in backup mode, in its alarms and on loss and restoration of power (C408.2.3.1). One exception covers unitary or packaged equipment in the Section C403.3.2 tables that does not need a supply air economizer. Controls and their sequences are tested (C408.2.3.2), and air economizers get their own functional test (C408.2.3.3).

The results go in a certified Preliminary Commissioning Report with mechanical and water heating findings in separate sections. It carries the completed checklist, any deficiencies not yet corrected, the tests deferred for climate and the conditions they need, the results, and the procedures with measurable pass criteria (C408.2.4). A building is not acceptable for final inspection until the code official has received that report (C408.2.4.1). The balancing report and the Final Commissioning Report reach the owner within 90 days of the certificate of occupancy, and deferred climate tests are the one exception to the final report's content (C408.2.5).

Lighting controls functional tests (C408.3)

Before a building passes final inspection, evidence must show that the automatic lighting controls were tested and are calibrated, adjusted and programmed (C408.3.1). For occupant sensors, the tester certifies location and aim. With seven or fewer sensors each is tested. With more, each unique combination of sensor type and space geometry is tested at not less than 10 percent, never fewer than one, and if 30 percent or more of the tested sensors fail, all the remaining identical sensors are tested (C408.3.1.1). Time switches are checked for correct weekday, weekend and holiday schedules, the date and time, battery backup, an override limit of no more than 2 hours, and occupied and unoccupied behavior (C408.3.1.2). Daylight controls are checked for location, calibration, response to daylight, and calibration access limited to authorized people (C408.3.1.3). Example: 60 sensors in three combinations of 30, 20 and 10 means at least 3 + 2 + 1 = 6 are tested. If 1 of the 3 tested in the group of 30 fails, that is 33 percent, so the other 27 in that group are tested. Lighting drawings, an operation and maintenance manual and the test report reach the owner within 90 days of the certificate of occupancy (C408.3.2).

Approval and closeout (C106, C401.3, C103.6)

When the prescribed tests and inspections show that the work complies in all respects, the code official issues a notice of approval (C106.1). It can be suspended or revoked in writing if it was issued in error or on incorrect information (C106.2). A permanent thermal envelope certificate is posted in the equipment space, a utility room or another approved place, and it lists insulation R-values, fenestration U-factors and SHGC, and the results of any envelope air leakage testing (C401.3). Within 90 days of the certificate of occupancy the owner also receives record documents and one compliance document that names the code edition used and the lighting compliance path (C103.6).

In the field

A GCHS inspector arrives for the final inspection of a new community clinic in Houston. The cooling capacity is 540,000 Btu/h, so commissioning applies, but the mechanical contractor hands over only start-up sheets. The lighting contractor tested 6 of 60 identical occupant sensors and 2 failed, and the envelope test result is missing from the posted certificate. Three things stop the final: no Preliminary Commissioning Report (C408.2.4.1), two failures in six is over 30 percent, so all 54 remaining identical sensors must be tested (C408.3.1.1), and a certificate that lacks the air leakage result (C401.3). Under C105.6 the corrections are made and the work is resubmitted.

Course review

The review walks the five modules in order and repeats the numbers used most often. It teaches nothing new, and every value carries the hedges of its lesson. Where a lesson said to check the adopted code, do the same here.

Module 1: Administration and Compliance (Lessons 1 and 2)

Every job starts with which code binds and which route the design takes. Lesson 1's dated check (September 29, 2026) found that the Texas statewide commercial energy code is the 2015 IECC, effective November 1, 2016, with rulemaking on the 2024 IECC expected in 2026, and that Houston enforces the 2021 IECC with Houston amendments from early January 2024. The amendments were not read, so request them. Lesson 2 supplied the zone, the definitions and the labels.

Key numbers: Lessons 1 and 2
  • Residential building: one- and two-family dwellings, townhouses and Groups R-2, R-3 and R-4 up to 3 stories above grade plane. A four-story R-2 is commercial (C202)
  • Paths: prescriptive Sections C402 through C406 and C408; total building performance at most 85 percent of the reference cost (C407.2); ASHRAE 90.1 named only as the alternative (C401.2)
  • New buildings earn 10 credits (C406.1). Closeout documents to the owner within 90 days of the certificate of occupancy (C103.6). The code official keeps a set 180 days (C103.5)
  • Zone 2A* in Table C301.1: Harris, Galveston, Brazoria, Fort Bend, Montgomery, Jefferson. Contrast: Cameron 1A*, El Paso 3B
  • Design temperatures: at most 72 F heating, at least 75 F cooling (C302.1)
  • R-value mark on insulation 12 inches or wider; attic depth markers one per 300 square feet, figures 1 inch high; cover for exposed foundation insulation 6 inches below grade (C303)

Module 2: Building Envelope (Lessons 3 to 5)

Lesson 3 gave the Zone 2 insulation values, Lesson 4 limited and rated the glass, and Lesson 5 sealed the shell. Which buildings must test for air leakage in Zone 2A depends on the interlocking exceptions above, so ask the code official which path is in use.

Key numbers: Lessons 3 to 5
  • Zone 2 (Table C402.1.3): roof with insulation above the deck R-25ci, attic roof R-38, metal building roof R-19 + R-11 LS; wood-framed wall R-13 + R-3.8ci or R-20; mass wall R-5.7ci (R-7.6ci Group R); floor over unconditioned space R-30; heated slab R-7.5 for 12 inches plus R-5; unheated slab and below-grade wall NR
  • Glass: 30 percent of gross above-grade wall and 3 percent of roof; 40 and 6 percent with daylight controls (C402.4.1)
  • Zone 2 fenestration: U 0.45 fixed, 0.60 operable, 0.77 entrance doors; fixed SHGC 0.25, 0.30, 0.40 by projection factor (under 0.2, 0.2 to under 0.5, 0.5 or more); PF = A / B; skylights U 0.65 and SHGC 0.30
  • Air barrier: material 0.004 and assembly 0.04 cfm per square foot at 75 Pa; whole-building 0.40 at 75 Pa; units 0.30 at 50 Pa; storefront and curtain wall 0.06, windows and doors 0.20 (C402.5)
  • Vestibules not required in Zones 0 to 2. Recessed lights IC-rated, 2.0 cfm or less at 75 Pa. Operable openings over 40 square feet reset setpoints to 90 F and 55 F within 10 minutes

Module 3: Mechanical and Water Heating (Lessons 6 to 8)

Lessons 6 and 7 sized, controlled and sealed the HVAC system, and Lesson 8 kept hot water from wasting energy. Equipment efficiencies are pointers to Tables C403.3.2 and C404.2, so compare the nameplate with the schedule. Water temperature at a public lavatory is a plumbing code matter, so check the adopted plumbing code.

Key numbers: Lessons 6 to 8
  • Capacity no more than the smallest available size above the load (C403.3.1). Deadband at least 5 F. Setback holds 55 F heating and 85 F cooling. Time clock: 7 schedules, 10-hour memory, 2-hour override. Automatic stop at least 2 F
  • Fault detection for HVAC serving 100,000 square feet or more, sampling every 15 minutes. Zone isolation for zones over 25,000 square feet or spanning floors
  • Economizer at 54,000 Btu/h (non-Group R) and 270,000 Btu/h (Group R); Zone 2A is not exempt; fixed dry-bulb high limit 65 F. Energy recovery ratio 50 percent
  • Fan power over 5 hp: constant volume CFMs x 0.0011, variable volume CFMs x 0.0015. Ducts R-6 in unconditioned space, R-8 outside in Zones 0 to 4
  • Gas plant of 1,000,000 Btu/h or more in a new building: 92 percent single unit, 90 percent weighted average. Insulate to the heat trap or the first 8 feet. Service hot water 105 to 140 F: 1.0 inch under 1.5 inch pipe, 1.5 inches for 1.5 to under 4 inches
  • Length method, other fixtures: 1/2 inch 43 feet, 3/4 inch 21 feet, 1 inch 13 feet. Volume: 2 ounces to a public lavatory, 64 ounces to others. Loop pump off at temperature, 104 F into cold piping

Module 4: Lighting and Electrical Power (Lessons 9 to 11)

Lesson 9 controlled the lights, Lesson 10 capped their power and Lesson 11 covered the rest of the electrical rules and the credit tables. Every count starts from the drawings and the luminaire schedule, and a claim with no paper trail is not a credit.

Key numbers: Lessons 9 to 11
  • Occupant sensor: lights off within 20 minutes, automatic on at no more than 50 percent power. Open plan zones 600 square feet or less, idle zones 20 percent or less. Time switch: 7 days, 24-hour holiday shutoff, 10-hour backup, override 2 hours and 5,000 square feet
  • Daylight controls: over 150 W primary sidelit, 300 W sidelit or 150 W toplit; dim to 15 percent or lower. Primary sidelit zone 1.0 x head height deep and 0.5 beyond the window edges; window at least 24 square feet, VT at least 0.20
  • Connected power not greater than the allowance; track at least 8 W per linear foot; office 0.64, retail 0.84, religious building 0.67 W per square foot. Space-by-Space for partial buildings and unfinished spaces (0.2 W per square foot at most). Exterior base site allowance 350, 400, 500 and 900 W for Zones 1 to 4
  • R-2 dwelling unit meters; voltage drop 5 percent; receptacle control 50 percent; energy monitoring at 25,000 square feet; elevator cab lights 35 lumens per watt
  • 10 credits for new buildings, 5 for tenant spaces; lighting credit under 90 percent of the allowance; renewables 0.25 W per square foot; envelope UA 15 percent under the reference; infiltration 0.25 cfm per square foot at 75 Pa, third-party tested

Module 5: Performance, Commissioning, Existing Buildings, and Review (Lessons 12 to 14)

Lesson 12 covered the simulation path and commissioning, Lesson 13 the rules for work on buildings that already stand, and this lesson gathered the inspections and tests that prove all of it. Chapter 5 is the part most used on GCHS rehab jobs: sort the work into an addition, alteration, repair or change of occupancy first.

Key numbers: Lessons 12 to 14
  • Performance path: annual energy cost at most 85 percent of the reference; software models 8,760 hours and at least ten thermal zones (C407)
  • Commissioning exempt under 480,000 Btu/h cooling and under 600,000 Btu/h combined heating; test at winter and summer design and full outside air; no discharge dampers on fans of 10 hp and larger (C408.2)
  • Alterations meet the code as new construction and may not leave the building less conforming; six exceptions apply while energy use does not increase (C503.1)
  • Roof replacement with insulation entirely above the deck: Zone 2 R-25ci, and never reduce the R-value. Replacement windows: fixed U-0.45, operable U-0.60, entrance doors U-0.77, averaged only within one category
  • Replacing less than 10 percent of the luminaires in a space with no added power is excepted, counted per space (C503.5). Conditioning-change and occupancy-change tradeoffs are capped at 110 percent (C502.2, C505.1)
  • Tests and inspections: this lesson. Nothing is covered until approved, and the final needs working controls and commissioning documents

The practice exam

The practice exam is the next step. It draws 60 questions, weighted by each topic area's share of the question bank, with a 120-minute time limit. It is a practice tool GCHS built for its own staff development. On an actual project, the locally adopted code, not this course, governs.

Practice questions

1. A four-story Group R-2 apartment building in Houston (Climate Zone 2A) has 30 dwelling units and complies by enclosure testing under IECC Section C402.5.2. At the least, how many units are blower-door tested before any failures are counted?

  1. 6 units, because 20 percent of 30 units is 6 and the percentage alone governs, with no top-floor or ground-floor unit required
  2. All 30 units, because every unit is tested in an apartment building above three stories
  3. 7 units, including a top-floor unit, a ground-floor unit and the unit with the largest enclosure area
  4. 3 units, one each on the top floor, the ground floor and the largest unit only

2. A Group B clinic in Zone 2A has 11,500 square feet of building thermal envelope and complies by a whole-building test under C402.5.3. The fan test measures 5,750 cfm at 75 Pa. What follows?

  1. The result is 0.50 cfm per square foot, over 0.40 but within 0.60, so the diagnostic evaluation, sealing and extra report apply
  2. The result is 0.50 cfm per square foot, which fails outright because the limit is 0.40 and no diagnostic route exists for Group B buildings
  3. The result is 0.50 cfm per square foot, which passes because only a reading over 0.60 must be corrected
  4. The result is 0.50 cfm per square foot, which fails because Group B buildings must meet 0.30 at 50 Pa

3. A new 8,000 square foot Group B office in Houston (Zone 2A) is being permitted. What does C402.5.1.2 require for its air barrier?

  1. A whole-building test at 0.40 cfm per square foot at 75 Pa, because every building over 5,000 square feet in Zone 2A must be tested and the result reported
  2. A blower door test of at least 7 units, because Zone 2A applies the Group R unit test to every occupancy
  3. No continuous air barrier at all, because Zone 2A is exempt from the air barrier requirement
  4. It is excepted from whole-building testing, so it meets the materials or assemblies path and the verification in C402.5.1.5

4. A Group B building has a supply duct system designed for 3.5 inches w.g. static pressure with 4,800 square feet of duct surface. Under C403.12.2.3, what must the leakage testing show?

  1. All 4,800 square feet pass at a leakage class CL of 4.0 or less, because high-pressure duct is tested completely
  2. Representative sections totaling at least 1,200 square feet pass, at a leakage class CL of 4.0 or less
  3. Sections totaling at least 480 square feet pass, at a leakage class CL of 4.0 or less
  4. Representative sections totaling at least 1,200 square feet pass, at a leakage class CL of 12.0 or less

5. A Group E school has 30 occupant sensors, all the same sensor type in the same room geometry. Under C408.3.1.1, at least how many are tested, and what happens if one of the tested sensors fails?

  1. 3 sensors are tested, and a failure only requires that the failed sensor be corrected and retested
  2. 3 sensors are tested, and one failure is over 30 percent of them, so all 27 remaining sensors are tested
  3. 1 sensor is tested, and its failure means all 29 remaining sensors are tested
  4. 6 sensors are tested, and one failure means the other 24 sensors are tested

6. A new Group B clinic in Houston has 540,000 Btu/h of cooling capacity and 450,000 Btu/h of combined space and water heating. At final inspection the contractor offers only equipment start-up sheets. What does C408.2.4.1 say?

  1. Final inspection may proceed, because the Final Commissioning Report is not due until 90 days after occupancy
  2. The clinic is exempt from commissioning, because its heating capacity is under 600,000 Btu/h
  3. The code official may waive the report if the owner accepts the building in writing
  4. The building is not acceptable for final inspection until the code official receives the Preliminary Commissioning Report

7. A new four-story Group R-2 apartment building with 40 units is planned in Houston. Which provisions of the 2021 IECC govern its energy compliance (Lesson 1)?

  1. The commercial provisions, because an R-2 building more than three stories above grade plane is a commercial building
  2. The residential provisions, because apartments are dwellings and dwellings of every height use the residential energy code
  3. The residential provisions, because every Group R-2 building follows Section R406 for the whole building
  4. Either set, at the designer's choice, because Group R-2 is classed as both commercial and residential

8. A GCHS estimator is pricing a new Group B clinic in Houston. According to the dated check in Lesson 1, which energy code does the City of Houston enforce for commercial buildings?

  1. The 2015 IECC, the statewide minimum, with no city amendments and no local change of edition
  2. The 2018 IECC with Houston amendments, effective in 2019
  3. The 2021 IECC with Houston amendments, effective in early January 2024
  4. The 2024 IECC, adopted by the city after the statewide rulemaking

9. A Group B clinic's attic holds 3,000 square feet of blown-in cellulose. Under C303.1.1.1 (Lesson 2), at least how many depth markers must be installed?

  1. 3 markers, one for every 1,000 square feet, placed near the access opening or the attic hatch
  2. 6 markers, one for every 500 square feet, with figures at least 2 inches high, fixed to the ceiling joists
  3. 30 markers, one for every 100 square feet, with figures at least 1 inch high
  4. 10 markers, one for every 300 square feet, with figures at least 1 inch high facing the access opening

10. A Group B clinic in Climate Zone 2A has roof insulation entirely above the deck, and the designer uses the R-value method of Table C402.1.3. Which layup meets it (Lesson 3)?

  1. Two layers of continuous board labeled R-10 each, joints staggered
  2. Two layers of continuous board labeled R-13 each, joints staggered
  3. One layer of continuous R-13 board plus R-13 batts in the roof cavity below the deck
  4. One layer of continuous R-13 board plus one layer labeled R-10, joints staggered

11. An overhang projects 4 feet from a Group B clinic's fixed window, and its underside is 8 feet above the bottom of the glass. In Zone 2, what is the highest SHGC allowed for that fixed glass under Table C402.4 (Lesson 4)?

  1. 0.25
  2. 0.30
  3. 0.40
  4. 0.37

12. A 6,000 square foot Group M shop in Houston has a public entrance door directly to the outdoors. Under C402.5.9, is a vestibule required (Lesson 5)?

  1. No, because vestibules are not required in Climate Zones 0 through 2, and Houston is Zone 2A
  2. Yes, because the space is over 3,000 square feet and the public uses the entrance every day
  3. Yes, unless a revolving door is installed beside the swinging door, since a revolving door replaces the vestibule
  4. No, but only if an air curtain of at least 6.56 feet per second at the floor is installed

13. A Group A-3 fellowship hall in Houston has a calculated cooling load of 46,000 Btu/h. Available rooftop sizes are 36,000, 48,000, 60,000 and 72,000 Btu/h. Under C403.3.1, what is the largest size allowed (Lesson 6)?

  1. 36,000 Btu/h, the nearest size below the load
  2. 48,000 Btu/h
  3. 60,000 Btu/h, one size above the smallest that exceeds the load
  4. 72,000 Btu/h, the largest size in the manufacturer's line

14. A Group B office in Houston (Zone 2A) will have one packaged rooftop unit with 60,000 Btu/h of cooling. The design uses none of the C403.5 exceptions and none of the allowance for a limited capacity of fan units without economizers. What does C403.5 require (Lesson 7)?

  1. No economizer, because humid Zone 2A exempts individual fan systems from economizers
  2. An economizer only at 270,000 Btu/h or more, which is the trigger for a non-Group R individual fan system
  3. No economizer, because economizers apply only to buildings of 100,000 square feet or more
  4. An economizer, because the trigger for a non-Group R individual fan system is 54,000 Btu/h and Zone 2A is not exempt

15. A community kitchen sink in a Group R-2 building is 30 feet from a recirculation loop by a 3/4 inch branch. What is the result under the length method of Table C404.5.1 (Lesson 8)?

  1. It passes, because 3/4 inch pipe is allowed 43 feet to a fixture other than a public lavatory, and the run is only 30 feet
  2. It fails, because the limit for 3/4 inch pipe is 13 feet to a fixture other than a public lavatory
  3. It fails, because the limit for 3/4 inch pipe is 21 feet, while a 1/2 inch branch with a 43 foot limit would pass by length
  4. It passes, because the volume method allows 0.5 gallon and the length method is optional

16. A Group B open plan office of 3,000 square feet is being lit. Under C405.2.1.3, into at least how many control zones must the lighting be divided (Lesson 9)?

  1. 5 zones, of no more than 600 square feet each
  2. 3 zones, of no more than 1,000 square feet each
  3. 4 zones, of no more than 750 square feet each
  4. 10 zones, of no more than 300 square feet each

17. A 5,000 square foot Group B office uses the Building Area Method at 0.64 W per square foot. Its schedule shows 3,060 W of fixtures counted at rated input watts, plus 20 feet of track holding 100 W of actual lamps. What is the result under C405.3 (Lesson 10)?

  1. Connected power is 3,160 W against 3,200 W allowed, so it passes with 40 W to spare
  2. Connected power is 3,060 W against 3,200 W allowed, because track is excluded, so it passes with 140 W to spare
  3. Connected power is 3,220 W, and it passes because the office allowance is 4,200 W
  4. Connected power is 3,220 W against 3,200 W allowed, so it fails by 20 W

18. A new 5,000 square foot Group B building in Zone 2A has an interior lighting allowance of 3,200 W and a connected interior lighting power of 2,950 W. Does it earn the base reduced lighting power credit under C406.3.1 (Lesson 11)?

  1. Yes, because connected power is below the allowance
  2. No, because 2,950 W is 92 percent of the allowance and the base credit needs under 90 percent, or 2,880 W
  3. No, because the base credit needs connected power under 85 percent of the allowance, which would be 2,720 W
  4. Yes, because 2,950 W is under 95 percent of the allowance

19. A Group B clinic on the total building performance path has a standard reference design that costs $140,000 a year in energy. What is the highest annual energy cost the proposed design may have under C407.2 (Lesson 12)?

  1. $119,000
  2. $126,000
  3. $133,000
  4. $112,000

20. A Group A-3 fellowship hall has 30 luminaires in one space. Under the C503.5 exception for alterations, what is the largest number that can be replaced with no added installed power and no new lighting compliance (Lesson 13)?

  1. 3 luminaires, because 10 percent of 30 is 3 and the exception allows up to 10 percent
  2. 4 luminaires, because the exception allows up to 15 percent when installed power does not increase
  3. 2 luminaires, because the exception is for less than 10 percent and 3 of 30 is exactly 10 percent
  4. All 30 luminaires, because only a lamp or ballast swap ever triggers the lighting rules

Glossary

Blower door test
A fan test that pressurizes or depressurizes a building or unit to measure air leakage. Units are tested at 50 Pa and whole buildings at 75 Pa (IECC C402.5.2, C402.5.3).
Envelope performance verification
The review of drawings and the inspection of the continuous air barrier during construction, while it can still be repaired, used where the building does not test (C402.5.1.5).
Diagnostic evaluation
A smoke tracer or infrared check of a pressurized building, with sealing and an extra report, allowed when a whole-building result is over 0.40 and not over 0.60 cfm per square foot (C402.5.3).
Leakage class (CL)
The rating that a leak test of high-pressure duct must reach, 4.0 or less, on sections totaling at least 25 percent of the duct area (C403.12.2.3).
Functional performance test
A test that shows equipment and controls operate in every mode of the sequence of operation, at full and part load, as the plans say (C408.2.3).
Preliminary Commissioning Report
The certified report of commissioning results that the code official must receive before a building is acceptable for final inspection (C408.2.4, C408.2.4.1).
Thermal envelope certificate
The permanent certificate posted in the equipment space or another approved place. It lists R-values, fenestration ratings and any air leakage test results (C401.3).
Notice of approval
The approval a code official issues after the prescribed tests and inspections show the work complies. It can be revoked in writing if issued in error (C106.1, C106.2).