Lesson 3: Selecting a project, building the charter, and proving the payoff
IASSC Body of Knowledge 1.3, Selecting Lean Six Sigma Projects · 14 practice questions
0:00 / --:--
Reading
Not every problem worth grumbling about is worth a Lean Six Sigma project.
This lesson covers how a project actually gets selected and started: the
business case that justifies spending time on it, the charter that defines
it, and the financial case that proves, in a way leadership can verify, that
it was worth doing.
A project charter's core pieces: problem, goal, and scope, supported by a business case, and made measurable by a baseline and target metric that feed the financial evaluation.
Building a business case and project charter
A business case answers one question before any team time is spent: why
does this problem matter enough to fix now? It typically states the problem
in terms of business impact, cost, risk, customer dissatisfaction, missed
deadlines, and ties it to organizational priorities rather than describing
it as an abstract inconvenience.
Once a business case justifies starting a project, the project
charter is the document that actually defines it, and typically
includes:
Problem statement: a specific, factual, measurable
description of what is wrong, with no assumed cause and no proposed
solution baked in.
Goal statement: what improvement the project is aiming
for, ideally with a specific, measurable target.
Scope: the boundaries of what the project will and will
not touch, which prevents the common failure mode of a project quietly
expanding until it can never finish.
Project team and roles: who is on the team, who
sponsors it, and who the process owner is.
Timeline: target dates for each DMAIC phase.
A charter is a living agreement between the team and its sponsor, not
paperwork filed away once signed. When a project's scope or goal changes
mid-stream, the charter should be revised and re-approved, not silently
ignored.
Developing project metrics
A charter's goal statement is only useful if it is tied to a metric that
can actually be measured before and after the project. Project metrics
typically separate into primary metrics, the Y in Y = f(x), directly tied to
the CTQ the project is meant to improve, and secondary or consequential
metrics, which track whether fixing the primary metric accidentally made
something else worse. A project that improves cycle time by 30 percent while
quietly doubling the defect rate has not actually succeeded; the consequential
metric caught what the primary metric alone would have missed.
Financial evaluation and benefits capture
A Lean Six Sigma project has to translate its result into terms the
organization's leadership can verify and trust, which almost always means
dollars. Financial evaluation typically separates benefits into two
categories:
Hard savings: a direct, verifiable reduction in
spending or increase in revenue, such as reduced material waste, reduced
overtime, or fewer returns processed. Hard savings show up in the budget.
Soft savings: real but less directly verifiable
benefits, such as improved employee morale, avoided future cost, or
improved customer satisfaction that has not yet been tied to a specific
dollar figure. Soft savings matter but typically carry less weight with a
financial sponsor than hard savings do.
Benefits capture is the discipline of actually confirming, after a
project closes, that the projected savings materialized and held, usually
through a follow-up review some months after the control plan takes effect.
A project whose savings were never verified after the fact is, in Six Sigma
terms, an unproven project no matter how good the improvement felt at the
time.
Writing a SMART goal statement
A charter's goal statement is only as useful as it is specific. The
widely used test for a well-written goal, in Six Sigma and well beyond it, is
the SMART framework, a mnemonic traced to a 1981
management article by George T. Doran, whose exact wording has shifted over the
years. In its commonly taught form, a goal should be Specific
(naming exactly what will change, not a vague direction), Measurable
(tied to a metric the team can actually collect), Achievable
(a real stretch, but not a target the team has no realistic path to), Relevant
(tied to the business case and the CTQ the project is meant to improve), and
Time-bound (with a target date, not an open-ended aspiration).
"Improve permit turnaround" is a direction, not a goal. "Reduce the average
number of days between GCHS submitting a rehab permit application and county
approval, from 21 days to 12 days, by the end of the third quarter" is a
SMART goal: it names the metric, the current baseline, the target, and the
deadline, all in one sentence. A goal statement missing any of the five
elements tends to produce exactly the kind of dispute a charter is supposed
to prevent, usually surfacing months into the project when someone asks
whether the team actually met its target and nobody can agree on what the
target was.
Practice questions
1. What question does a business case answer before a project team spends any time on a problem?
Why this problem matters enough to fix now
What statistical software the team should use
How many Black Belts are available that quarter
Who will be blamed if the project fails
Answer: a. A business case answers why a problem matters enough to justify a project now, tying it to business impact such as cost, risk, or customer dissatisfaction.
2. A well-written problem statement in a project charter should avoid which of the following?
An assumed root cause or a baked-in proposed solution
Any reference to the process affected
A specific description of what is wrong
Measurable facts about current performance
Answer: a. A problem statement should be specific, factual, and measurable, with no assumed cause and no proposed solution baked in, so the team's later analysis is not biased toward a predetermined answer.
3. What does the "scope" section of a project charter prevent?
The team from collecting baseline data on the process it is improving
Financial evaluation of the project after it is closed out by the sponsor
A project quietly growing past its boundaries until it never finishes
The need for a goal statement
Answer: c. Scope defines the boundaries of what a project will and will not touch, preventing the common failure mode of a project's boundaries silently expanding until it never finishes.
4. When a project's scope or goal changes significantly mid-stream, what should happen to the charter?
The team should simply proceed without telling the sponsor
It should be revised and re-approved with the sponsor
It should be discarded and never referenced again
Nothing; charters are fixed once signed and cannot change
Answer: b. A charter is a living agreement; when scope or goal changes materially, it should be revised and re-approved with the sponsor, not silently ignored.
5. What is a secondary, or consequential, metric used to track?
Only the project's budget
Whether fixing the primary metric made something else worse
The number of team members and sponsor meetings assigned to the project
The exact same thing as the primary metric, measured twice
Answer: b. A secondary or consequential metric tracks whether improving the primary metric accidentally degraded something else, such as quality dropping while speed improves.
6. A project improves cycle time by 30 percent but the defect rate doubles in the process. What does this scenario illustrate?
That Pareto analysis was not needed for this project
That the project should be counted as a full success because cycle time fell 30 percent
Why a consequential metric is needed alongside the primary metric
That defect rate and cycle time can never be related
Answer: c. This illustrates why a consequential metric matters: the primary metric alone shows a win, while the consequential metric reveals the project actually made overall performance worse.
7. Which of these is an example of a hard savings benefit?
Improved employee morale that has not been tied to a specific dollar figure
A general sense that customers seem happier
Avoided future cost that has not been quantified
A verifiable cut in material waste that shows up in the budget
Answer: d. Hard savings are a direct, verifiable reduction in spending or increase in revenue, such as reduced material waste, that actually shows up in the budget.
8. Soft savings typically carry less weight with a financial sponsor than hard savings because of what?
Soft savings are real but harder to verify in dollar terms
Soft savings are always fabricated
Soft savings only apply to manufacturing processes
Sponsors are never interested in morale or satisfaction, only in the final budget line
Answer: a. Soft savings, such as morale or avoided future cost, are real but less directly verifiable than hard savings, so they typically carry less weight in a financial case.
9. What is "benefits capture"?
A synonym for Cost of Poor Quality
The step where a team brainstorms and ranks possible root causes on a fishbone
The process of writing the original project charter
Confirming after closure that projected savings materialized and held
Answer: d. Benefits capture is confirming, typically through a follow-up review some months after the control plan takes effect, that the projected savings actually materialized and held.
10. A project's savings were never verified after the project closed. In Six Sigma terms, how is that project best described?
Automatically a failed project regardless of results
An unproven project, however good the improvement felt
Exempt from any further financial evaluation since the project already closed
A textbook example of proper benefits capture
Answer: b. Without a follow-up review confirming the savings materialized and held, a project is unproven in Six Sigma terms, regardless of how good the improvement felt at the time.
11. In the SMART framework for a project's goal statement, what does the "M" stand for?
Manageable
Measurable
Motivational
Mandatory
Answer: b. The M in SMART stands for Measurable, tied to a metric the team can actually collect, alongside Specific, Achievable, Relevant, and Time-bound.
12. GCHS is chartering a project to speed up accessibility modifications after a home visit assessment. The team writes the problem statement: "Some homes take too long to modify." What is missing from this statement?
A list of team members
Nothing; it is already specific and factual
A proposed root cause
Specific, measurable, factual detail about actual current performance
Answer: d. A problem statement needs specific, factual, measurable detail about what is wrong today. "Some homes take too long" names no baseline, no metric, and no scope.
13. A well-built business case for a Lean Six Sigma project typically ties the problem to what?
Organizational priorities such as cost, risk, and customer impact
The personal preferences of the project team
The number of Black Belts and Green Belts available for staffing that quarter
The color scheme of the final report
Answer: a. A business case states the problem in terms of business impact, cost, risk, or customer dissatisfaction, and ties it to organizational priorities rather than describing an abstract inconvenience.
14. A GCHS rehab project reduces the number of return trips a contractor must make to finish punch-list items, directly cutting the mileage reimbursement GCHS pays out. This benefit is best classified as what?
A secondary metric only
A soft saving, because morale improved
A hard saving, because it is a direct, verifiable reduction in spending
Benefits capture
Answer: c. A direct, verifiable reduction in spending, here lower mileage reimbursement, is a hard saving; it shows up in the budget rather than remaining an unquantified benefit.
Glossary
Business Case
The justification for why a problem matters enough to fix now, tied to business impact such as cost, risk, or customer dissatisfaction.
Project Charter
The document that defines a project: problem statement, goal statement, scope, team and roles, and timeline.
Problem Statement
A specific, factual, measurable description of what is wrong, with no assumed cause and no proposed solution baked in.
Scope
The boundaries of what a project will and will not touch.
SMART Goal
A goal statement that is Specific, Measurable, Achievable, Relevant, and Time-bound.
Primary Metric
The Y in Y = f(x), directly tied to the CTQ a project is meant to improve.
Hard Savings
A direct, verifiable reduction in spending or increase in revenue that shows up in the budget.
Benefits Capture
Confirming, after a project closes, that its projected savings actually materialized and held.