Day 16: Plan and Manage Schedule

about 4.1% of the exam content - about 90 minutes - 14 practice questions

0:00 / --:--

Reading

A schedule is a model of how work will unfold, not a wish. Building one means four things in order: define the activities, sequence them, estimate how long each takes, then develop the schedule model that falls out of those decisions. Everything else (compression, leveling, forecasting) is manipulation of that model. On the exam, schedule questions are heavy on network logic and float arithmetic, so the mechanics below are worth knowing cold.

Critical path network for a GCHS accessibility retrofit A network diagram from Start through activity A (5 days), then splitting into two parallel paths to activity D (6 days): the top path through B (8 days) and the bottom path through C (12 days), before rejoining at Finish. The bottom path, Start-A-C-D-Finish, totals 23 days and is the critical path, drawn with a solid heavy line. The top path, Start-A-B-D-Finish, totals 19 days and is not critical, drawn dashed, with a label showing that activity B carries 4 days of total float. Start A 5 days B 8 days C 12 days D 6 days Finish Path A-B-D = 19 days, total float on B = 4 days Path A-C-D = 23 days: critical path (heavy line)
Two parallel paths connect activity A to activity D. The lower path through C is longer, so it sets the 23-day project duration and carries zero float; the upper path through B has 4 days of total float and can slip that much without delaying the finish.

Sequencing: dependency types and modifiers

TypeMeaningGCHS example
Finish-to-start (FS)Predecessor must finish before successor starts. By far the most common.Demolition must finish before framing starts.
Start-to-start (SS)Successor cannot start until predecessor starts. Debris hauling starts two days after demolition starts (SS + 2).
Finish-to-finish (FF)Successor cannot finish until predecessor finishes.Final punch cannot finish until final cleaning finishes.
Start-to-finish (SF)Successor cannot finish until predecessor starts. Rare, usually a shift-handover pattern.The temporary heater stays running until the new HVAC system starts up.

Two modifiers adjust the relationship. A lag is required waiting time: concrete must cure five days before framing, so that is FS with a 5-day lag. A lead is overlap, allowing a successor to begin before the predecessor is complete: starting trim work three days before painting finishes is FS with a 3-day lead. Leads compress; lags stretch.

Dependencies are also classified by where they come from. Mandatory (hard logic) is physically or contractually unavoidable: you cannot drywall before rough-in inspection. Discretionary (preferred or soft logic) reflects best practice and can be changed: painting before flooring because the crew prefers it that way. External dependencies sit outside the project team's control, such as a county permit. Internal ones are inside the team's control. Only discretionary logic is safely available for fast-tracking.

Critical path method: the arithmetic

The critical path is the longest path through the network, and therefore the shortest possible project duration. Suppose the network runs Start → A(5) → B(8) → D(6) → Finish, and also Start → A(5) → C(12) → D(6) → Finish. Path A-B-D is 19 days; path A-C-D is 23 days. The critical path is A-C-D at 23 days, and B carries 23 − 19 = 4 days of total float.

The forward pass moves left to right and computes early start (ES) and early finish (EF): the earliest each activity can happen. The backward pass moves right to left and computes late start (LS) and late finish (LF): the latest each activity can happen without delaying the project.

TermFormulaPlain meaning
Total floatLS − ES, or LF − EFHow long this activity can slip without delaying the project finish date
Free floatES of the earliest successor − EF of this activityHow long this activity can slip without delaying the early start of any successor
Critical pathLongest path; total float normally zeroThe sequence that sets the project duration
Negative floatTotal float below zeroThe schedule is already behind an imposed constraint: the plan is infeasible as drawn
Key points
  • Free float is always less than or equal to total float, never more.
  • A project can have more than one critical path, which raises risk, because there are more ways to slip.
  • Negative float is not a curiosity; it is a signal that you must compress, reduce scope, or move the date, and that a change request is probably coming.
  • Delaying a non-critical activity by less than its total float does not delay the project.

Compressing the schedule

CrashingFast-tracking
What you doAdd resources to critical path activities to shorten themPerform activities in parallel that were planned in sequence
Main costMoney: more crew, overtime, premium delivery Risk: rework, coordination errors
Best whenBudget exists and risk tolerance is lowBudget is fixed and the logic is discretionary rather than mandatory
Watch out forDiminishing returns; adding people to a crowded bathroom slows it down Overlapping mandatory logic: you cannot inspect rough-in that has been covered

Two disciplines apply to both: only compress activities on the critical path (crashing a non-critical activity costs money and changes the finish date by zero) and choose the lowest cost per day saved first. If activity X crashes 3 days for 6,000 dollars (2,000 per day) and activity Y crashes 2 days for 3,000 dollars (1,500 per day), you crash Y first, provided both are critical.

Watch for this on the exam

A question that offers a very cheap crash option on an activity that is not on the critical path is a trap. So is compressing before you have confirmed the finish date can even be recovered: the tested sequence is analyze impact, evaluate options, recommend, then process the change.

Resources: leveling versus smoothing

Both adjust the schedule around resource availability, and the difference is exactly one thing: whether the critical path may move.

  • Resource leveling is applied when resources are over-allocated or only available in limited quantities. It can change the critical path and can extend the project duration. If GCHS has one certified lead-safe renovator and three units need him at once, leveling is what you do, and the finish date probably moves.
  • Resource smoothing adjusts activities only within their available float. The critical path is not changed and the completion date is not delayed. It evens out peaks and valleys in resource demand but cannot fix a genuine over-allocation.

Rolling wave planning is the progressive-elaboration answer to uncertainty: plan the near-term work in fine detail and leave later work at a higher level, refining it as it approaches. It is legitimate planning, not laziness, and it is common in hybrid programs where the first three months are known and month nine is not.

Adaptive scheduling: cadence, velocity, and burn charts

Adaptive projects invert the constraint. Instead of fixing scope and letting the date move, they fix the timebox and let scope vary. The unit of planning is the iteration, and the forecasting tool is velocity: the number of story points a team actually completes per iteration, averaged over recent iterations. If a team completed 24, 30, 27, and 31 points, its average velocity is 112 / 4 = 28 points per iteration. With 168 points remaining in the release backlog, the forecast is 168 / 28 = 6 more iterations.

  • Iteration burndown: work remaining in the current iteration, trending toward zero.
  • Release burndown: remaining work across the whole release; when scope is added the chart can go up, which honestly shows the effect of new requests.
  • Burnup chart: plots work completed against a separate total-scope line, which makes scope growth visible as a rising ceiling rather than hiding it inside the remaining-work line. This is why many teams prefer burnup for stakeholder conversations.
  • Release planning: mapping which features are likely to land in which iterations, refreshed as velocity data accumulates.

Velocity is a forecasting tool for one team, not a performance score and never a cross-team comparison. Story points are relative to a single team's estimating baseline; comparing them across teams is meaningless and drives point inflation.

Do not do this

Do not update the schedule baseline just because reality diverged from it. The baseline changes only through approved change control. Update the schedule with actuals and forecasts, keep the baseline as the measuring stick, and if the date truly must move, raise a change request with the analysis behind it.

Practice Questions

1. A network has two paths: A(5 days) to B(8 days) to D(6 days), and A(5 days) to C(12 days) to D(6 days). What is the critical path duration?

  1. 42 days
  2. 19 days
  3. 23 days
  4. 31 days

2. Using the same network, A(5)-B(8)-D(6) at 19 days and A(5)-C(12)-D(6) at 23 days, how much total float does activity B have?

  1. 8 days
  2. 0 days
  3. 4 days
  4. 6 days

3. An activity has ES = 10, EF = 16, LS = 13, and LF = 19. What is its total float?

  1. 0 days
  2. 3 days
  3. 6 days
  4. 9 days

4. Activity D has an early finish of day 22. Its two successors have early starts of day 26 and day 24. What is D's free float?

  1. 0 days
  2. 6 days
  3. 4 days
  4. 2 days

5. Which definition of total float is correct?

  1. The amount of time added to an estimate as a buffer
  2. The time an activity can be delayed without delaying the early start of any successor
  3. The time an activity can be delayed without delaying the project finish date
  4. The difference between the budget and the actual cost

6. Which statement about the critical path is correct?

  1. It always contains the activities with the highest cost, so its length is set by the most expensive work packages
  2. A project can only ever have one critical path
  3. It is the shortest path through the network and represents the longest possible duration
  4. It is the longest path through the network and represents the shortest possible project duration

7. A GCHS crew estimates lead-safe abatement in a single unit at an optimistic 6 days, a most likely 9 days, and a pessimistic 18 days. Using the PERT (beta) formula, what is the estimated duration?

  1. 10 days
  2. 11 days
  3. 13 days
  4. 9 days

8. Framing on a GCHS unit cannot start until 5 days after demolition finishes, to let dust settle and allow an inspection. What is this relationship?

  1. Finish-to-start with a 5-day lead
  2. Finish-to-start with a 5-day lag
  3. Start-to-start with a 5-day lag
  4. Finish-to-finish with a 5-day lag

9. A GCHS renovation budget is fixed, but the finish date must be pulled in. The logic between two activities is discretionary rather than mandatory. What should the project manager do?

  1. Crash the critical path activities
  2. Apply resource leveling
  3. Apply resource smoothing
  4. Fast-track the discretionary logic by overlapping the activities

10. Two critical-path activities can each be crashed: Activity M saves 4 days for 8,000 dollars, and Activity N saves 2 days for 3,000 dollars. Which should be crashed first, and why?

  1. Activity M, because it saves more total days
  2. Both at the same time, to save the most total time
  3. Activity N, because its cost per day saved (1,500 dollars) is lower than M's (2,000 dollars)
  4. Neither, since crashing always changes the critical path

11. GCHS has one certified lead-safe renovator who is needed on three units at the same time. Leveling his schedule across the units will most likely do what?

  1. Eliminate the need to schedule him at all
  2. Extend the project duration and potentially change the critical path
  3. Have no effect on the schedule at all
  4. Only change float, never the finish date

12. A hybrid GCHS program plans the next three months of work in detail and keeps month nine at a high level, refining it as it gets closer. What is this technique called?

  1. Decomposition
  2. Rolling wave planning
  3. Critical path method
  4. Resource smoothing

13. An agile team completed 18, 20, 19, and 23 story points in its last four iterations, and 140 points remain in the release backlog. Using average velocity, how many more iterations should the team forecast?

  1. 7 iterations
  2. 8 iterations
  3. 5 iterations
  4. 6 iterations

14. Stakeholders on an adaptive GCHS project want a chart that shows completed work against total scope, so that scope growth is visible rather than hidden. Which chart should the team use?

  1. Burnup chart
  2. Iteration burndown
  3. Release burndown
  4. Cumulative flow diagram

Glossary

Total float
The amount of time an activity can be delayed without delaying the project finish date; LS minus ES or LF minus EF.
Free float
The amount of time an activity can be delayed without delaying the early start of any successor activity.
Critical path
The longest path through the network diagram, which sets the shortest possible project duration.
Crashing
A compression technique that adds resources to critical path activities to shorten duration, at added cost.
Fast-tracking
A compression technique that performs activities in parallel that were originally planned in sequence, at added risk.
Resource leveling
Adjusting the schedule to resolve resource over-allocation, which can change the critical path and extend duration.
Resource smoothing
Adjusting activities only within their available float so the critical path and finish date do not change.