Process - Task 9 of 10

Day 17: Evaluate Project Status

about 4.1% of the exam content - about 90 minutes - 14 practice questions

0:00 / --:--

Reading

Evaluating status is the discipline of knowing where you actually are, not where the plan said you would be, and not where the crew chief feels you are. It has two halves. The first is arithmetic: earned value management (EVM), which converts progress into dollars so schedule and cost can be compared on the same scale. The second is visual and behavioral: burn charts, cumulative flow, information radiators, and the honest conversations they provoke. The exam tests both, and it tests the EVM formulas hard.

Earned value S-curve at the GCHS six-month status date A cumulative-cost S-curve chart with dollars on the vertical axis and time on the horizontal axis, running from project start to a planned finish. Three lines rise together from the origin: planned value, which continues on the original baseline curve to 250,000 dollars at the status date; earned value, which lags below the planned value line at 220,000 dollars, showing work is behind schedule; and actual cost, which sits above earned value at 275,000 dollars, showing money spent has outpaced the value produced. A vertical dashed line marks today's status date. The vertical gap between earned value and planned value is labeled schedule variance, minus 30,000 dollars, and the vertical gap between earned value and actual cost is labeled cost variance, minus 55,000 dollars. $0 Time (months since project start) Status date (month 6) PV $250,000 EV $220,000 AC $275,000 SV = −30,000 CV = −55,000 Baseline (planned)
At the six-month status date, actual cost sits above earned value (a negative cost variance) and earned value sits below planned value (a negative schedule variance): the retrofit is both over budget and behind schedule.

The three measurements everything is built from

  • Planned value (PV): the budgeted cost of the work scheduled to be done by now. What the baseline said you would have accomplished.
  • Earned value (EV): the budgeted cost of the work actually done. Computed as EV = BAC x percent complete. This is the value of what exists, priced at plan rates.
  • Actual cost (AC): what you actually spent to produce that work.

BAC (budget at completion) is the total cost baseline. The trick to every EVM question is the same: EV is always the first term in a variance, and always the numerator in an index. Everything else follows.

The formula table

MeasureFormulaHow to read the result
Cost variance (CV)EV − ACNegative = over budget
Schedule variance (SV)EV − PVNegative = behind schedule
Cost performance index (CPI)EV / ACBelow 1.0 = over budget. CPI 0.80 means you get 80 cents of work per dollar spent
Schedule performance index (SPI)EV / PVBelow 1.0 = behind schedule
EAC (variance is typical)BAC / CPICurrent cost performance continues to the end. The default assumption
EAC (variance is atypical)AC + (BAC − EV)The overrun was a one-time event; remaining work will run at plan
EAC (cost and schedule performance both drive the remaining work)AC + (BAC − EV) / (CPI x SPI)Remaining work is affected by both cost and schedule performance
Estimate to complete (ETC)EAC − ACWhat the rest will cost from here
Variance at completion (VAC)BAC − EACNegative = forecast overrun
TCPI (to BAC)(BAC − EV) / (BAC − AC)Efficiency required on the remaining work to still land on the original budget
TCPI (to EAC)(BAC − EV) / (EAC − AC)Efficiency required to land on the revised forecast

A worked GCHS example

A 12-unit accessibility retrofit has BAC = 500,000 dollars. At the six-month mark: PV = 250,000, EV = 220,000, AC = 275,000.

  • CV = 220,000 − 275,000 = −55,000: over budget by 55,000.
  • SV = 220,000 − 250,000 = −30,000: behind schedule by 30,000 of work.
  • CPI = 220,000 / 275,000 = 0.80: 80 cents of value per dollar spent.
  • SPI = 220,000 / 250,000 = 0.88: running at 88% of planned pace.
  • EAC (typical) = 500,000 / 0.80 = 625,000.
  • ETC = 625,000 − 275,000 = 350,000 still to spend.
  • VAC = 500,000 − 625,000 = −125,000: forecast overrun.
  • TCPI to BAC = (500,000 − 220,000) / (500,000 − 275,000) = 280,000 / 225,000 = 1.24: the remaining work must run 24% more efficiently than plan to still hit 500,000, which, given a project running at 0.80, is not credible.
Key points
  • Anything negative is bad; any index below 1.0 is bad.
  • A TCPI far above the current CPI is the mathematical way of saying the budget is gone. Say so early.
  • SPI is a poor late-project indicator: as work finishes, EV converges on PV and SPI drifts toward 1.0 even on a project that finished late. Use the critical path for schedule truth near the end.
  • Schedule variance is expressed in dollars of work, not days. Converting it to days requires the schedule model.

Variance analysis versus trend analysis

Variance analysis asks how far off plan you are at this instant. Trend analysis asks which direction the number is moving over several periods. One data point tells you a story; three tell you the truth. A CPI of 0.96 is unremarkable, unless it was 1.02 two months ago and 0.99 last month, in which case something structural is degrading and the trend is the finding, not the value.

The project management plan sets control thresholds: the variance levels that trigger action. When a variance crosses one, the plan already tells you what to do; the tested behavior is consult the plan and follow it, not invent a response or escalate reflexively. And remember the data hierarchy: raw work performance data (hours charged, units installed) becomes work performance information once analyzed in context (CPI, SPI, forecasts), which becomes work performance reports when packaged for a specific audience.

Situational tell

When a question shows an adverse variance, the tested first move is almost never “tell the sponsor” or “submit a change request.” It is determine the cause. Analyze, then decide, then communicate, then change control if required. Escalation is the last resort, not the reflex.

Adaptive status: radiators, burn charts, and flow

Adaptive teams measure status with visible, low-ceremony artifacts rather than monthly reports.

  • Information radiators: big visible charts posted where the team and stakeholders walk past them. The point is that nobody has to request status; it is ambient. A task board in the GCHS field office is a radiator.
  • Iteration and release burndown: remaining work trending toward zero; burnup adds a separate total-scope line so growth is visible rather than hidden.
  • Cumulative flow diagram (CFD): stacked bands showing how many items sit in each workflow state over time. A widening band is a bottleneck: work is arriving faster than it is leaving. A flat completed band means nothing is finishing. CFDs make queues visible in a way a burndown cannot.
  • WIP limits: caps on how many items may be in a state at once. Limiting work in progress shortens cycle time, because a shorter queue means each item waits less. Teams that start everything finish nothing.
  • Cycle time is how long an item takes from when work begins to when it is done; lead time runs from when the request arrives to when it is done, so it includes the wait in the backlog. Lead time is what the customer experiences.

AI-assisted analytics increasingly flag emerging variances from historical patterns before a human sees them, and sustainability reporting is being folded into status: energy performance of completed units, diverted-waste tonnage, and benefits actually realized. Distinguish leading indicators (predictive: defect rates, cycle time trend) from lagging indicators (confirmatory: final cost, units delivered). Steering a project requires leading indicators; lagging ones only tell you how it ended.

Do not do this

Do not accept percent-complete numbers the team estimates by feel: the classic ninety-percent-done task that stays ninety percent done for six weeks. Tie earned value to objective rules: a fixed formula such as 0/100 or 50/50, verified milestones, or a definition of done. Status you cannot defend is not status.

Practice Questions

1. A project has BAC = 500,000 dollars. At month six, PV = 250,000, EV = 220,000, and AC = 275,000. What is the cost variance?

  1. minus 25,000 dollars
  2. minus 30,000 dollars
  3. minus 55,000 dollars
  4. plus 25,000 dollars

2. Using the same data, PV = 250,000, EV = 220,000, AC = 275,000, what is the schedule variance?

  1. minus 25,000 dollars
  2. minus 30,000 dollars
  3. minus 55,000 dollars
  4. plus 30,000 dollars

3. With EV = 220,000 and AC = 275,000, what is the cost performance index, and what does it mean?

  1. 0.80: the project is earning 80 cents of value per dollar spent
  2. 0.88: the project is 12 percent behind schedule because it earned less than was planned
  3. 1.20: the project is 20 percent under budget because earned value exceeds actual cost
  4. 1.25: the project is earning 1.25 dollars per dollar spent

4. With EV = 220,000 and PV = 250,000, what is the schedule performance index?

  1. 1.14
  2. 1.09
  3. 0.80
  4. 0.88

5. BAC = 500,000, EV = 220,000, AC = 275,000, CPI = 0.80. Assuming current cost performance continues, what is the estimate at completion?

  1. 555,000 dollars
  2. 625,000 dollars
  3. 400,000 dollars
  4. 500,000 dollars

6. BAC = 500,000, EV = 220,000, AC = 275,000. The overrun was caused by a one-time hurricane-driven material price spike that will not repeat. What is the most appropriate EAC?

  1. 555,000 dollars
  2. 500,000 dollars
  3. 672,700 dollars
  4. 625,000 dollars

7. BAC = 500,000, AC = 275,000, and the typical-variance EAC is 625,000 dollars. What is the estimate to complete (ETC)?

  1. 125,000 dollars
  2. 275,000 dollars
  3. 350,000 dollars
  4. 625,000 dollars

8. BAC = 500,000 and the typical-variance EAC is 625,000 dollars. What is the variance at completion (VAC), and what does it mean?

  1. Minus 125,000 dollars, the project is forecast to overrun the original budget
  2. Minus 55,000 dollars, the current cost variance
  3. Minus 30,000 dollars, the current schedule variance
  4. Plus 125,000 dollars, the project is forecast to finish under budget

9. BAC = 500,000, EV = 220,000, AC = 275,000, and the typical-variance EAC is 625,000. What is TCPI calculated against the revised EAC?

  1. 1.24
  2. 0.88
  3. 1.00
  4. 0.80

10. BAC = 500,000, EV = 220,000, AC = 275,000, CPI = 0.80, SPI = 0.88. Both cost and schedule performance are expected to keep affecting the remaining work. Which EAC formula applies, and what is the result?

  1. AC + (BAC minus EV) / (CPI x SPI) = about 672,700 dollars
  2. BAC = 500,000 dollars
  3. BAC / CPI = 625,000 dollars
  4. AC + (BAC minus EV) = 555,000 dollars

11. A project's CPI was 1.02 two months ago, 0.99 last month, and 0.96 this month. Looking at the direction of these three data points rather than just the current value is an example of what?

  1. Root cause analysis
  2. Earned value analysis
  3. Variance analysis
  4. Trend analysis

12. Hours charged by the crew and units installed this week, before anyone has analyzed what they mean, are best described as:

  1. Work performance reports
  2. Work performance data
  3. Work performance baseline
  4. Work performance information

13. The final total cost of a project, tallied after the project is complete, is an example of what kind of indicator?

  1. Leading indicator
  2. Lagging indicator
  3. Control threshold
  4. Trend indicator

14. A GCHS team's cumulative flow diagram shows the "in inspection" band steadily widening over three weeks while the "complete" band stays flat. What does this indicate?

  1. The team is finishing inspections faster than new items arrive
  2. Nothing meaningful; cumulative flow diagrams fluctuate naturally
  3. A bottleneck: work is arriving in that state faster than it is leaving it
  4. WIP limits should be removed to speed the team up

Glossary

Planned value (PV)
The budgeted cost of the work scheduled to be done by a given point in time.
Earned value (EV)
The budgeted cost of the work actually completed, calculated as BAC times percent complete.
Actual cost (AC)
The money actually spent to produce the work performed to date.
Cost performance index (CPI)
EV divided by AC; below 1.0 means the project is over budget.
Schedule performance index (SPI)
EV divided by PV; below 1.0 means the project is behind schedule.
Estimate at completion (EAC)
The forecast total cost of the project given current performance.
To-complete performance index (TCPI)
The cost efficiency required on remaining work to hit a target budget, either the original BAC or the revised EAC.
Cumulative flow diagram (CFD)
A stacked chart showing how many work items sit in each workflow state over time, used to spot bottlenecks.

Progress